HomeMy WebLinkAboutMinutes - September 24, 1980232
CITY COUNCIL, CITY OF LODI
CITY HALL COUNCIL CHAMBERS
September 24, 1980
An adjourned regular meeting of the City Council of the City of Lodi
was held beginning at 7:30 p.m. on Wednesday, September 24, 1980 in
the City Hall Council Chambers.
I
Roll Call was recorded by City Clerk Reimche as follows:
I_
Present: Councilmen - Hughes, McCarty, Murphy, Pinkerton, and
Katnich (Mayor)
Absent: Councilmen - None
Also Present: City Manager Glaves, Assistant City Manager Glenn,
Utility Director Curry, City Attorney Stein, and
City Clerk Reimche
Background information and a description of the Lodi Electrical system
was given by Utility Director Dave Curry.
Various diagrams pertaining to the subject were presented for Council's
perusal by Mr. Curry during his presentation.
Mr. Curry gave a description, including projected savings and bene-
fits, for each of the following NCPA energy resources projects:
SHELL PROJECT
(SONOMA AND LAKE COUNTIES)
Capacity: 105.6 MW Lodi participation: 15.4 MW
Development Costs: $8,000,000 (Geothermal Field Development
by Shell)
Duration of Project: 25-30 years following commercial operation.
Project Financing: Tax exempt revenue bonds (Oct. '80)-25%
Tax exempt DOE guaranteed loan - 755
Baseload Application: 83% load factor
Lodi Participation: 14.56%
Project Cost to Date: $7.00 M (Lodi's share: $1,019,200;
$853,446 debt.) $165,754 Dev. Fund
Contribution
Total Project Cost: $68,500,000
Energy Lodi Portion: 111,791,167 KWH/yr.
Estimated Cost of Energy in 1982: 40-Mils/kwh*
compared to 40.0+** from
P.G.&E.
* increases at 6%/yr. (est.)
** Increases at 9%/yr.
Savings develop at 3%/yr.
x.33
Continued September 24, 1980
CALAVERAS HYDRO PROJECT
(North Fork of Stanislaus River)
Capacity: 200 MW (140 MW TDC) Lodi participation 19.7 MW
Development Costs: (Up to approximately $2.0 MIL) by NCPA,
to be refunded.
Duration of Project: 50 years following commercial operation
(First right to re -negotiate contract)
Project Financing: By CCWD from tax exempt revenue bonds
Peaking Application: 343 - 383 Load Factor
Lodi Participation: 9.853
1980-1981 Assessment: $31,520
1979-1980 Assessment: $19,700
Advanced to Date: $108,350 (est.)
Original Bond Limit: $350,000,000
Current (4/1980)Project: $425,000,000
Monthly payment to CCWD: $17,000+ (support of Hydro 0 & M
of plant/transmission by NCPA)
Energy - Lodi Portion: 55,652,500 kwh/yr. (min. normal)
Possibility of 100,000,000 kwh/yr.
Estimated cost of energy in 1984: 60 Mils/kwh + wheeling
(assume 108 = 6 mils
to cover wheeling and
estimate error) compared to
58.4 (min.) from P.G.&E.
Crossover point is less than
2 years. After crossover
point, savings will increase
at 9%/yr.
RFL GEOTHERMAL PROJECT
(Lake County)
Capacity: 63.4 MW (net) Lodi Participation: 9.23 MW
Development Costs: $15,000,000
Duration of Project: 25-30 years following commercial operation.
Project Financing: Tax exempt (?) revenue bonds.
Baseload Application: 833 load factor
Lodi Participation: 14.563
Project Cost to Date: $4.85M (Lodi's share $705,700;
$339,976 outstanding debt.)
$365,724 Dev. Fund Contribution
Total Project Cost: $175,000,000 + $6 M/yr. well replacement.
Energy Lodi Portion: 67,117,046 kwh/yr.
Estimated Cost of Energy in 1986: 68.0 Mils/kwh* compared to
58.0** from P.G.&E. Cross-
over point is approximately
-2-
Z34
Continued September 24, 1980
3 years hence. Savings
develop at 6%/yr. thereafter.
Current Status: NOI approved: AFC not started (requires 9
mo.).
Speculative Aspects: Resource, IRS tax ruling, financial image.
* Increases at 3%/yr. (est.)
** Increases at 9%/yr.
Information pertaining to Santa Clara's proposal to Development
Fund Members for expeditious implementation of NCPA Project No. 1
(RFL) as received from William A. Gissler, Mayor of the City of
Santa Clara was presented to the Council as follows:
REASON FOR PROPOSAL
This project is doomed to failure unless immediate action
is taken. It was delayed for many months because of the RFL
bankruptcy and resulting negotiations. A plan of action
including necessary funding should have been in place so that
at least one and maybe two additional wells could have been
drilled this summer, immediately following the settlement.
Instead, nothing has occurred, resulting in the following
situation:
1. The "Authority to Construct" (air quality permit)
has expired.
2. We are in danger of losing all rights obtained under
the RFL Agreement and Settlement due to failure to
obtain an extension to the Sunedco Farmout require-
ment for a second well. There is insufficient time
to comply with Sunedco's requirements if they will
not give an extension.
3. The sump in Well No. 1 has not been winterized.
4. By not too distant October 1981 a commercial reser-
voir must be proven or by agreement is deemed proven
and further large payments are due to satisfy the
settlement agreement.
5. Substantial sums of money will need to be paid by
October 1981 which only become due and payable upon
completion of a commercial reservoir if we proceed
expeditiously.
Because of these and other failures to proceed with the
project, the City of Santa Clara feels the project is
doomed to failure unless immediate and continued aggressive
action is taken on this project. Santa Clara feels it must
have the authority to accomplish the above action in order
to protect its substantial financial commitment to the Project.
Santa Clara proposes the following three alternative
methods of participation to our other partners in the Project
for their consideration:
ALTERNATIVE 1 - For each of those Members who wishes to
proceed with Project No. 1 in an aggressive manner and have
the financial resources to do it:
Conditions:
1. Member will sign an agreement to out up funds as
will be spelled out for an aggressive development
program.
23t15
Continued September 24, 1980
2. Member will agree to designate the City of Santa
Clara as Project Manager.
ALTERNATIVE 2 - For each of those Members who wishes to
obtain some power from the Project but does not have the finan-
cial resources to continue with its development.
Conditions:
1. Member signs an agreement with SantaClarawhereby
Santa Clara will agree, as Project Manager, to
sell up to 25% to Member of its current percentage
participation in a 66 MW Project, at Project
cost, when and if Project is commercial.
2. Santa Clara will agree that Member will not incur
any further risk or financial commitment to the
Project.
ALTERNATIVE 3 - For each of those Members who wishes to dissolve
all further interests in the Project.
Conditions:
1. Member releases all interests in Project to Santa
Clara.
2. Santa Clara will now repay the Member 25% of all
costs properly allocated to Member for Project
expenditures to date.
3. Santa Clara will later repay the Member the remain-
ing 75% of all costs properly allocated to Member
for Project expenditures to date when Project
goes into Commercial Operation.
in order to effectuate this proposal it will be necessary
for Member and Santa Clara to execute documents to carry out
the intent of the proposal above.
A proposed agreement covering Santa Clara proposal including three
alternative methods of participation was reviewed at length by the
Council.
Each alternative was scrutinized by the Council with questions being
directed to Staff and to the City Attorney.
Mr. John Talbot, 800 Maplewood Drive, Lodi addressed the Council,
stating that he opposed additional funding going to NCPA and urged
that this is a job that could be done just as well by private
enterprise--P.G.&E.
Lengthy discussion followed with additonal questions being directed
to Staff and to Mr. Talbot.
On motion of Councilman Pinkerton, Hughes second,Council directed that
the City of Lodi go forward with the Shell Project and the Calaveras
Hydro Project, and further that the City of Lodi selects to proceed
under Alternative two (2) of the aforementioned agreement covering
Santa Clara's proposal to Development Fund members for expeditious
implementation of NCPA Project No. 1 (RFL'), whereby the City of Lodi
will take a mini_num of 25& as provided in this alternative but will
negotiate up from that percentage to the=best possible deal.
There being no further business to come before the Council, Mayor
Katnich adjourned the meeting at approximately 10:00 p.m.
Attest:
ALICE M. REIMCHE
Citv Clerk