HomeMy WebLinkAboutAgenda Report - January 7, 2015 C-07AGENDA ITEM Cal
ANCITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Receive Update on Emergency Condition at White Slough Water Pollution Control
Facility Digesters No. 1 and No. 2
MEETING DATE: January 7, 2015
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Receive update on emergency condition at White Slough Water
Pollution Control Facility Digesters No. 1 and No. 2.
BACKGROUND INFORMATION: White Slough Water Pollution Control Facility (WSWPCF) has four
covered anaerobic digesters that serve the purpose of breaking
down sewage sludge that enters the plant. On July 16, 2014,
Council declared an emergency condition in response to concurrent roof failures on Digesters No. 1 and
No. 2. Public contract code requires Council to review the emergency action at its next regularly -scheduled
meeting and each regularly -scheduled meeting thereafter until the emergency is terminated.
The process of coating the interior of Digester No. 2 is complete. The digester roof manufacturer has
completed the fabrication process for both Digester No. 1 and No. 2 roof structures. Both roof structures
arrived on-site during the week of December 22, 2014; and work to assemble the roof of Digester No. 2 is
expected to begin early January 2015.
The procurement and construction schedule reflecting project milestones is provided below. There is no
substantial change from last report.
Project Definition Meeting
July 21, 2014
Issue Final Contract Documents
August 1, 2014
Receive GMP Proposals
August 20, 2014
Issue Notice to Proceed
September 15, 2014
Complete Digester No. 2 Improvements
April 2, 2015
Complete Digester No. 1 Improvements
August 27, 2015
FISCAL IMPACT: Not applicable.
FUNDING AVAILABLE: Not applicable.
F. Wally 96ndelin
Public Works Director
Prepared by Charlie Swimley, City Engineer/ Deputy Public Works Director
FWS/CES/smh
cc: Associate Civil Engineer Nathan Charlie Swimley, City Engineer/ Deputy Public Works Director
Wastewater Plant Superintendent Construction Project Manager
APPROVE
tep en Schwabauer, Cit Manager
OigesterRepalrs ncil Updates\CUpdate010715 doc 12/16/2014