AGENDA ITEM C 2
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Accept Improvements Under Contract for 2014 Crack Sealing, Various City Streets
MEETING DATE:
PREPARED BY:
December 3, 2014
Public Works Director
RECOMMENDED ACTION: Accept improvements under contract for 2014 Crack Sealing,
Various City Streets.
BACKGROUND INFORMATION: The contract was awarded to Graham Contractors, Inc., of San Jose,
in the amount of $60,416.13, on August 6, 2014. The contract has
been completed in substantial conformance with the specifications
approved by City Council on June 18, 2014.
This project consisted of crack sealing approximately 1,110,000 square feet of various City streets, as
shown in Exhibit A.
The contract completion date was October 22, 2014 and the actual completion date was October 22, 2014.
The final cost of the project was $60,416.13. There was no difference between the original contract
amount and final contract.
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of
Completion with the County Recorder's office. The notice serves to inform vendors and subcontractors
that the project is complete and to initiate the 30 -day period to file a stop notice requiring the City to
withhold payments from the prime contractor in the event of a payment dispute.
FISCAL IMPACT: By increasing the crack sealing effort, the useful life of the City streets will
be extended.
FUNDING AVAILABLE: This project was funded by Measure K (325028) funds.
c l—I ZZ -121
F. Wally Sandelin
Public Works Director
Prepared by Sean Nathan, Associate Civil Engineer
FWS/SN/pmf
Attachment
cc: Associate Civil Engineer Nathan
Utility Superintendent - PW
City Engineer/Deputy Public Works Director
APPROVED:
er, City Manager
\\CVCFILV02\PubWks$\WP\PROJECTS\STREETS\2014 Crack Seal\CAccept.doc 11/17/2014