AGENDA TITLE: Receive Update on Emergency Condition at White Slough Water Pollution Control
Facility Digesters No. 1 and No. 2
MEETING DATE: August 20, 2014
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Receive update on emergency condition at White Slough Water
Pollution Control Facility Digesters No. 1 and No. 2.
BACKGROUND INFORMATION: White Slough Water Pollution Control Facility (WSWPCF) has four
covered anaerobic digesters that serve the purpose of breaking
down sewage sludge that enters the plant. On July 16, 2014,
Council declared an emergency condition in response to concurrent roof failures on Digesters No. 1 and
No. 2. Public contract code requires Council to review the emergency action at its next regularly -scheduled
meeting and each regularly -scheduled meeting thereafter until the emergency is terminated.
On July 21, 2014, representatives from the City and West Yost Associates (WYA) provided Western
Water Constructors, Inc., and Overaa Construction draft contract documents for their review. WYA and
City staff considered the contractor input, made revisions, and issued the final contract documents on
August 1, 2014 as scheduled. Staff submitted documents for the building permit on August 4, 2014, and
expects the permit review period not to interfere with the anticipated start of work.
The preliminary procurement and construction schedule reflecting project milestones is referenced below.
Please note the minor schedule changes. It is not anticipated these minor changes will impact the
contract completion dates at this time.
FISCAL IMPACT: Preliminary construction cost estimate to repair Digester No. 2 remains at
approximately $1,400,000 and to repair Digester No. 1 remains at
approximately $1,700,000 at this time.
FUNDING AVAILABLE: Wastewater Capital (171493) - An appropriation in the amount of
$3,100,000 was authorized by Council on July 16, 2014.
F. Wally ndelin
Public Works Director
Prepared by Charlie Swimley, City Engineer / Deputy Public Works Director
FWS/CES/prof
cc: Associate Civil Engineer Nathan
Charlie Swimley, City Engineer / Deputy Public Works Director
Wastewater Plant Supervisor
APPROVED: d [ �r
City Manager
K:\WP\PROJECTS\SEWER\WSWPCF\DigesterRepairs\Council Updates\CUpdate082014.doc 8/5/2014
ORIGINAL DATES REVISED DATES
Project Definition Meeting
July 21, 2014
Issue Final Contract Documents
August 1, 2014
Receive GMP Proposals
August 15 2014 August 20, 2014
Issue Notice to Proceed
Au@IUM 29 2014 September 8, 2014
Complete Digester No. 2 Improvements
April 30, 2015
Complete Digester No. 1 Improvements
December 7, 2015
FISCAL IMPACT: Preliminary construction cost estimate to repair Digester No. 2 remains at
approximately $1,400,000 and to repair Digester No. 1 remains at
approximately $1,700,000 at this time.
FUNDING AVAILABLE: Wastewater Capital (171493) - An appropriation in the amount of
$3,100,000 was authorized by Council on July 16, 2014.
F. Wally ndelin
Public Works Director
Prepared by Charlie Swimley, City Engineer / Deputy Public Works Director
FWS/CES/prof
cc: Associate Civil Engineer Nathan
Charlie Swimley, City Engineer / Deputy Public Works Director
Wastewater Plant Supervisor