HomeMy WebLinkAboutAgenda Report - March 5, 2014 C-04AGENDA ITEM C do LA
da CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Awarding Contract for Fire Station No. 3 Parking Lot Improvements,
2141 South Ham Lane, to MHK Construction, Inc., of Denair ($53,732)
MEETING DATE: March 5, 2014
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution awarding contract for Fire Station No. 3 Parking Lot
Improvements, 2141 South Ham Lane, to MHK Construction, Inc., of
Denair, in the amount of $53,732.
BACKGROUND INFORMATION: The project consists of reconstructing the parking lot (approximately
4,400 square feet) with asphalt concrete, constructing a drive
approach and van accessible parking stalls, and other incidental
and related work, all as shown on the plans and specifications for the project.
Plans and specifications for this project were approved on January 15, 2014. The City received the
following 11 bids for this project on February 12, 2014.
Bidder
Location
Bid
Engineer's Estimate
$
51,231.20
MHK Construction, Inc.
Denair
$
53,732.00
ALB, Inc.
Pittsburg
$
54,206.00
A.M. Stephens Construction Company
Lodi
$
54,999.00
R&R Construction
Winters
$
56,000.00
A&S Construction, Inc.
Victor
$
57,250.22
Central Valley Engineering & Asphalt
Roseville
$
57,351.84
Rodgers Construction
Stockton
$
57,384.00
Sierra Asphalt, Inc.
Rancho Cordova
$
67,882.00
Sinclair General Engineering Construction
Oakdale
$
70,089.00
BRCO Construction
Loomis
$
78,000.00
Martin General Engineering
Rancho Cordova
$
94,480.00
FISCAL IMPACT: The project will decrease maintenance costs.
FUNDING AVAILABLE: This project wAbe funded through Capital Projects (1211037).
Jordan`Ayers '
Deputy City Manager/Internal Services Director
F. ally andelin
Public Works Director
Prepared by Sean Nathan, Associate Civil Engineer
FWS/SN/pmf
cc: Fire Chief
APPROVED:
, Intorim City Manager
K:\WP\PROJECTSWIISC\FireSta3\Parking Lot Improvements\CAward.doc
2/13/2014
FIRE STATION NO. 3 PARKING LOT IMPROVEMENTS
2141 South Ham Lane CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and MHK CONSTRUCTION, INC., herein referred to as the
"Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare; pension, vacation, travel time,
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
Contract.doc 1 02112/14
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
Perform the work necessary to reconstruct the parking lot (approximately 4,400 square feet)
with asphalt concrete, constructing a drive approach, a van accessible parking stalls, and other
incidental and related work, all as shown on the plans and specifications for "Fire Station No. 3
Parking Lot Improvements".
See Section 6-07 of the Special Provisions for additional description of bid items.
CONTRACT ITEMS
Item
Description
Unit
Qty
Price
Total
1
Clearing and Grubbing
LS
1
$ 5,462.00
$ 5,462.00
2
Compact Original Ground
SF
4,094
$ 1.00
$ 4,094.00
3
Concrete Gutter / Curb &
LF
59
$ 44.00
$ 2,596.00
Gutter
4
Concrete Curb
LF
88
$ 29.00
$ 2,552.00
5
Concrete Hose -Washing
SF
100
$ 23.80
$ 2,380.00
Apron
6Concrete
Parking Stall & Path
SF
448
$ 6.75
$ 3,024.00
7
Modified Commercial -Type
SF
288
$ 10.50
$ 3,024.00
Gutter and Driveway
8
Replace Drop Inlet Catch
EA
1
$ 1,700.00
$ 1,700.00
Basin
9
Striping
LS
1
$ 1,300.00
$ 1,300.00
10
Signage
LS
1
$ 700.00
$ 700.00
11
Pavement Excavation
CY
80
$ 56.25
$ 4,500.00
12
Asphalt Concrete
TON
135
$ 140.00
$18,900.00
13
Landscape Area Modifications
LS
1
$ 3,500.00
$ 3,500.00
TOTAL $ 53,732.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
Contract.doc 2 02112/14
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 21 CALENDAR DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
D. Stephen Schwabauer
Interim City Manager
By: Date:
Title
Attest
City Clerk
(CORPORATE SEAL) Approved As To Form
Janice D. Magdich
Interim City Attorney CK,
Contract -dor: 3 02/12114
RESOLUTION NO. 2014-25
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE
CONTRACT FOR THE FIRE STATION NO. 3 PARKING LOT
IMPROVEMENTS, 2141 SOUTH HAM LANE
------------------------------------------------------------------------
------------------------------------------------------------------------
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed proposals were received and publicly opened on February 12, 2014, at
11:00 a.m., for the Fire Station No. 3 Parking Lot Improvements, 2141 South Ham Lane,
described in the plans and specifications therefore approved by the City Council on
January 15, 2014; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Bid
MHK Construction, Inc.
$ 53,732.00
ALB, Inc.
$ 54,206.00
A.M. Stephens Construction Company
$ 54,999.00
R&R Construction
$ 56,000.00
A&S Construction, Inc.
$ 57,250.22
Central Valley Engineering & Asphalt
$ 57,351.84
Rodgers Construction
$ 57,384.00
Sierra Asphalt, Inc.
$ 67,882.00
Sinclair General Engineering Construction
$ 70,089.00
BRCO Construction
$ 78,000.00
Martin General Engineering
$ 94,480.00
WHEREAS, staff recommends awarding the contract to the low bidder,
MHK Construction, Inc., in the amount of $53,732.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for the Fire Station No. 3 Parking Lot Improvements, 2141 South Ham Lane, to the
low bidder, MHK Construction, Inc., in the amount of $53,732; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract.
Dated: March 5, 2014
------------------------------------------------------------------------
------------------------------------------------------------------------
I hereby certify that Resolution No. 2014-25 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held March 5, 2014, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Mounce, and Mayor Katzakian
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Nakanishi
ABSTAIN: COUNCIL MEMBERS — None
f��JOHL-OLSON
City Clerk
2014-25