AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Contract Change Order with
C. Overaa & Company, of Richmond, for Storm and Waste Water Pump Station
SCADA Integration Underthe Surface Water Treatment Facility Project Contract
.($450,000)
MEETING DATE: December 19,2012
PREPARED BY: PublicWorks Director
RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute contract change
order with C. Overaa & Company, of Richmond, for storm and waste
water pump station SCADA integration underthe Surface Water
Treatment Facility project contract, in an amount not to exceed $450,000.
BACKGROUND INFORMATION: The contract was awarded to C. Overaa&Company on October 20,2010.
The facility received an "Interim Approval to Operate" from the California
Department of Public Health on November 20, 2012 and is currently
undergoing a 30 -day performance test. Staff anticipates formal Council acceptance of the project in
January 2013.
As a part of the contract, all operating City well sites were integrated into the Surface Water Treatment
Facility (SWTF) SCADA system so they can be monitored and controlled at the SWTF operations center.
The requested change order will upgrade the nine City wastewater and 12 City storm water pump station
communication systems so they may be integrated into the SWTF SCADA system for monitoring and
control. Once this work is completed, PublicWorks staff will be able to monitor and ultimately control all
Public Works pump facilities from the SWTF operations center.
Work at each site will include SCADA packs, radio communication equipment, conduit, wiring, antennas
and computer programming. It is estimated that each site will require $21,000 worth of materials and
labor. Each site is slightly different and actual costs will not be known until the work begins. The change
order will be based on time and materials, not to exceed $450,000.
FISCAL IMPACT: Completion of this work will permit monitoring of these facilities at the Surface
Water Treatment Facility and reduce the funds currently paid to the Electric
Utility Departmentto monitorthe pump stations.
FUNDING AVAILABLE: Funding is available within the SWTF project contingency funds (181011).
Jordan Ayers
Deputy City Manager/Internal Services Director
Aall, Ja A"A 1—
F. Wally gAndelin
PublicWorks Director
Prepared by Gary Wiman, Construction Project Manager
FWS/GW/pmf
cc: Larry Parlin, Deputy PublicWorks Director— Utilities
C. Overaa & Company
APPROVED:
Bartlam, City Manager
K:OPT ROJECTS\WATER\SurfaceWaterPIant\SWTF CC Autho rize sto rm & waste pump SCADA C0.doc 12/4/2012
RESOLUTION NO. 2012-199
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING CITY MANAGERTO EXECUTE CONTRACT
CHANGE ORDER WITH C. OVERAA & COMPANY FOR
STORM AND WASTEWATER PUMP STATION SCADA
INTEGRATION UNDER THE SURFACE WATER
TREATMENT FACILITY PROJECT CONTRACT
------------------
WHEREAS, the contract for the Surface Water Treatment Facility Project was
awarded to C. Overaa & Company on October 20,2010; and
WHEREAS, as a part of the contract, all operating City well sites were integrated
into the Surface Water Treatment Facility (SWTF) Supervisory Control and Data
Acquisition (SCADA) system so they can be monitored and controlled at the SWTF
operations center; and
WHEREAS, the change order will upgrade the 9 City wastewater and 12 City
storm water pump station communication systems so they may be integrated into the
SWTF SCADA system for monitoring and control. Once this work is completed,
Public Works staff will be able to monitor and control all Public Works pump facilities
from the SWTF operations center.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute a contract change order with C. Overaa &
Company, of Richmond, California, for storm and waste water pump station SCADA
integration under the Surface Water Treatment Facility Project contract, in an amount
not to exceed $450,000.
Dated: December 19, 2012
------------------------
------------------------
I hereby certify that Resolution No. 2012-199 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held December 19, 2012, by the
following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, Mounce, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS— None
4CM JOHL
City Clerk
2012-199
CITY COUNCIL
ALAN NAKANISHI, Mayor
PHIL KATZAKIAN,
Mayor Pro Tempore
LARRY D. HANSEN
BOBJOHNSON
JOANNE L. MOLINCE
C. Overaa & Company
200 Parr Boulevard
Richmond, CA 94801
CITY OF LODI
PUBLIC WORKS DEPARTMENT
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209) 333-6706
FAX (209) 333-6710
EMAIL pwdept@lodi.gov
http:\\www.lodi.gov
December 13,2012
KONRADT BARTLAM
City Manager
RANDIJOHL
City Clerk
D. STEVEN SCHWABAUER
City Attorney
F. WALLY SANDELIN
Public Works Director
SUBJECT: Adopt Resolution Authorizing City Manager to Execute Contract Change
Order with C. Overaa & Company, of Richmond, for Storm and Waste
Water Pump Station SCADA Integration Underthe Surface Water
Treatment Facility Project Contract ($45,000)
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, December 19,2012. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunity to address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letterto City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letter to City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Randi Johl, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Gary Wiman, Construction
Project Manager, at (209) 333-6800, extension 2054.