HomeMy WebLinkAboutAgenda Report - December 18, 1985 (92)�j
CI`_"Y COUNCIL FETING
DECEMBER 18, 1985
tt RE?4EKAL OF CONTRACT
WITH CONTRACT BUILDING
INSPECTOR APPROVED
Council authorized the renewal of a contract to .rune 30,
1986 with Harvey G. Benson to perform building
inspection for the City of Lodi.
• _,,,COUNCIL COI!'iMUNICAVON
TO: THE CITY COUNCIL
FROM: THE CITY MANAGER'S OFFICE
SUBJECT:
CONTRACT BUILDING INSPECTOR - RENEW CONTRACT
DATE NO
December 10, 1985
BACKGROUND: In June of this year the City Council authorized
-
t eCity Manager to enter into a contract with Harvey G. Benson to
perform building inspection. Mr. Benson was hired to assist the
Building Division during a period of very heavy building
activity. The large amount of work continues and the Chief
Building Inspector wishes to extend the contract until June 30,
1985.
Mr. Benson is on call and works a maximum of six hours a day. By
having him on the job, we are able to use another inspector to do
commercial plan check almost full-time. Without him we will fall
further behind. At the time of writing this memorandum, there
were 32 projects in commercial plan check (i.e. multiple -family,
commercial or industrial buildings).
1
Jamos B. Sc roeder
C-Mmunity Development Director