Council accepted the improvements for "Hann Lane
Improvements, Lodi Avenue to Elm Street" and directed the
Public Works Director to file a Notice of Completion with
the County Recorder's Office.
The contract was awarded to Granite Construction of
l Stockton on June 5, 1985 in the amount of $287,989.50. The
\ contract has been completed in substantial conformance with
the plans and specifications approved by the City Council.
The final contract price was $332,417.19. 'i'he difference
between the contract amount and the final contract price is
mainly due to the necessity of importing additional rock to
stabilize unsuitable subgrade, an overrun in the amount
of asphalt, and resolution of sane minor conflicts with
catch basin lines.