HomeMy WebLinkAboutAgenda Report - October 16, 1985 (53)Square D Ccanpany
Haycrdxd, CA 17,572.68 12,789.45 30,362.13 18
RTE Corporation
Waukesha, WI 14,953.42 15,788.80 30,742 22 12-14
Based on design data supplied by the bidders,
the life -cycle cost of transfon er losses has
been evaluated. Based on the mam-u m total
life -cycle cost of the transformer, City
Momager Peterson reconr ended that. the bid
be awarded to the _lowest bidder.
COUNCIL ADOPTED RESOLUTION NO. 85-147 ANAMING
THE BID FOR ONE 1500 kVA THREE-PHASE
PADMOUNT TRANSFORMER TO WESTINGiMSE E'BC'TRIC
SUPPLY COMPANY, THE LCW BIDDER, IN THE AMOUNT OF
$15,365.76.
COUNCIL ADOPTED RESOLUTION NO. 85-146
AWARDING THE BID E'OR THE PURCHASE OF TWO
1200 AMP, 15 -KV, VACUUM CIRCUIT BREAKERS
'DO SQUARE D COMPANY, THE LOW BIDDER, IN
THE AMOUNT OF $27,340.76.
A4OR.D - FADNSOUNT
TRANSFORMER
RES. NO. 85-147
City Manager Peterson presented the following
bids which had been received for one 1500
KVA three-phase padmount transformer:
TRANSFORMER BID EVALUATION
UD -E85-11
"A" "B" "A" + "13" Estimated
Price Cost of Life --Cycle Delivery
Supplier
With Tax Losses Cost (Weeks)
Westinghouse Electric
Supply Co.
Concord, CA
$15,365.76 $14,.117.05 $29,482.81 23-25
General Electric
Supply Co.
Emeryville, CA
16,355.80 13,917.95 30,273.75 15-17
Square D Ccanpany
Haycrdxd, CA 17,572.68 12,789.45 30,362.13 18
RTE Corporation
Waukesha, WI 14,953.42 15,788.80 30,742 22 12-14
Based on design data supplied by the bidders,
the life -cycle cost of transfon er losses has
been evaluated. Based on the mam-u m total
life -cycle cost of the transformer, City
Momager Peterson reconr ended that. the bid
be awarded to the _lowest bidder.
COUNCIL ADOPTED RESOLUTION NO. 85-147 ANAMING
THE BID FOR ONE 1500 kVA THREE-PHASE
PADMOUNT TRANSFORMER TO WESTINGiMSE E'BC'TRIC
SUPPLY COMPANY, THE LCW BIDDER, IN THE AMOUNT OF
$15,365.76.
'A19UNCIL C®R'iA'IUNICATIPN
TO THE CITY COUNCIL
FROM. THE CITY MANAGER'S OFFICE
SUBJECT: PURCHASE OF PADMOUNT TRANSFORMER (UD -E85-11)
DATE
OCTOBER 9, 1985
NO.
On Tuesday, October 8, 1985, bids were received for one 1500 KVA three-phase
padmount transformer. The transformer will be used to serve an expansion
project for a local industrial customer.
Based on design data supplied by the bidders, the life -cycle cost of
transformer losses has been evaluated. Column "B" is the dollar value
associated with these losses. Based on minimum total life -cycle cost of
the transformer, it is recommended that the bid be awarded to the lowest
bidder, Westinghouse Electric Supply Co., Concord, CA, in the amount of
$15,365.76.
Sufficient funds are available in the Electric Department's operating fund
.for this purchase.
Henry J. R.c
Electric Utility Director
RESOLUTION NO. 85-147
AWARD - PURCHASE OF ONE 1500 KVA THREE-
PHASE PADMOUNT TRANSFORMER
WHEREAS, in answer to notice duly published in
accordance with -law and the order of this City Council,
sealed bids were received and publicly opened by the City
Clerk of this City on October 8, 1985 at 11:00 a.m. for the
Contract for one 1500 KVA Three -Phase Padmount Transformer as
described in the specifications therefor approved by the City
Council August 21, 1985.
WHEREAS, said bids have been compared, checked and
tabulated and a report thereof filed with the City Manager as
shown on Exhibit "A" attached hereto and thereby made a part
hereof.
WHEREAS, the City Manager recommends that award be
made to the low bidder, Westinghouse Electric Supply Company.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Lodi that award of contract for one 1500 KVA
Three -Phase Padmount Transformer be and the same is hereby
made to Westinghouse Electric Supply Company, the low bidder,
in the amount of $15,365.76.
Dated: October 16, 1985
I hereby certify that Resolution No. 85-147 was
passed and adopted by the City Council of the City of
Lodi in a regular meeting held October 16, 1985 by
the following vote:
Ayes: Councilmembers - Olson, Snider, Pinkerton,
Reid, and Hinchman (Mayor)
Noes: Councilmembers - None
Absent: Councilmembers - None
ALICE M. REIMCHE
City Clerk
85-147
Q
�;,r.:,. �... , .. _.....,� ir.->.,;:....:Ka ..,.uu;, •. .. _ -+a:,� ,..:a.-cMu�.«::�v : s,,. _ .... °r �...:.,, ..... ., _
r
TRANSFORMER BID EVALUATION
UD -E85-11
"All "B" "A" + "B" Estimated
Price Cost of Life -Cycle Delivery
Supplier With Tax Losses — Cost (Weeks)
Westinghouse Electric Supply Co.
Concord, CA $15,365.76 $14,117.05 $29,482.81 23-25
General Electric Supply Co.
Emeryville, CA 16,355.80 13,917.95 30,273.75 15-17
Square D Company
Hayward, CA 17,572.68 12,789.45 30,362.13 18
RTE Corporation
Waukesha, WI 14,953.42 15,788.80 30,742.22 12-14