CITY OF LODI -
TO: The State of California Attorney General, Department of
General Services, County, and City. Officials, and
Application Nos. 85-12-50 and 86-04-012 Service List:
Pacific Gas and Electric Company (PGandE) hereby gives
f Notice that in Application No. 86-09-001 filed with the
California Public Utilities Commission (CPUC or Commission)
jon September 2, 1986, it has requested authorization to
include in its rates and charges for electric servicethe
a` costs to PGandE of constructing a research"'and demonstration -
j;
project, Photovoltaics for Utility Scale Applications
(PWSA) at two sites in its service area.
PWSA is a research and development project which is
needed to determine which emerging photovoltaic technologies
r can be economically and technically viable in commercial
scale, utility applications. The basic concept -hof PWSA is
the side-by-side testing of multiple developing photovoltaic
technologies in a commercial scale, utilityenvironment.
Photovoltaics on a commercial scale would allow a renewable,
indigenous resource, the sun's energy.to be harnessed to
make electricity. PVUSA'Phase I construction is scheduled to
begin in 1987, with costs shared among PGandE, the
5 Department of Energy (DOE), the California' Energy'Commission
(CEC), the photovoltaic industry and other utility companies
and industry organizations. The project will be located at
two different sites which are representative of different
sunlight regimes within PGandE's service area. One site is
adjacent to the City of Davis and the other site is in the
Carrisa 'Plain.
The amount which PGandE seeks to include in electric
rates' for this project is $13.7 million, spread uniformly
over the time period 1987 through 1989. PGandE proposes to
recover the requested amount in rates effective January 11
1987, or.as soon thereafter as the Commission may authorize.
The proposed rate treatment would increase PGandE's electric
rates by $4.57 million in 1987 on an annualized basis.. On
January 1, 1990, rates would be a$justed to remove the $4.57
million. The proposed annualized amount would increase
PGandE's electric rates less than one percent, or .007 cents
per kWh over the rates in effect as the date'of_this
filing.
The state, counties'
and municipal corporations; `and
other 'interested .in
the above mentioned filing will
_parties
a cogy ..; hof
_Applcation No 86=09-001;
'Notice
'is
This
gi,•ren , in accordance .with- Rule 24 of
the Rules of Practice
and Procedure of the'California Public
Utilities Commission.'
Very truly yours,.
PACIFIC GAS AND ELECTRIC COMPANY,
f 1
BY ar-�
•=
SHIRLE A. WOO
a