BLACK & VEATCH
ENGINEERS —ARCHITECTS TEL. (4151944-5770
Proposal for Engineering Services
to Prepare a Wastewater Treatment
Plant Expansion Schedule Report
City of Lodi
221 West Pine Street
Lodi, CA 95240
Attention: tar. Jack L. Ronsko
Gentlemen:
3470 BUSKIRK AVENUE
MAILING ADDRESS: P.O. BOX NO. 4247
WALNUT CREEK. CALIFORNMA 94596
B & V Project 00003.51-16
July 24, 1984
We are pleased to present this letter proposal to prepare a wastewater
treatment plant expansion schedule report in accordance with the standard
provisions B.5 of the NPDES permit for White Slough. We propose to do
this work on a time and mzterials basis not to exceed $2,800.
A letter report for submission to the State by the City will be prepared to
address the three specific items of the standard provision. The contents of
the report will be based upon the basic data developed by the White Slough
staff, with additional evaluation of the expansion date based upon plant
performance. In addition, we will develop a preliminary project budget
and the scope of any additional study that should be initiated in the near
future to maintain the project schedule. We have also included time to
present the report to the City staff and/or council.
If you have any questions regarding our proposal, please contact me at
your convenience.
Very truly yours,
BLACK S C
/David 'A. Requa/
er
RECEIVED
JUL 2 5 1984
CITY OF LODI
FWLIC WORKS DEPARTMENT
MEMORANDUM, City of Lodi, Public Works Department
TO: City Manager
FROM: Pubiic Works Director
DATE: August 31, 1984
SUBJECT: Wastewater Treatment Plant Expansion S� edule Report
The requirements of the City's Wastewater Discharge Permit for the White
Slough Treatment Facility requires that we submit a report to the California
Regional Water Quality Control Board at such time that our treatment facility
reaches 75% capacity. This report must include such items as population and
flow projections, establishment of an expansion program including a prelim-
inary project budget, an outline of the additional specific studies and
engineering which must be accomplished and when. Attached is Section B-5
of the Standard Provisions made part of our discharge permit which :over
this reporting requirement.
Attached for general information is a population and flow projection which
has been formulated by the White Slough Lab staff. The population projection
was obtained from the Community Development Department. it is felt that
this is a conservative projection since it does not include any possible
effect of Measure A. The wastewater flow is based on a 120 gallon per
capita per day usage. Based on these projections, the yearly average flow of
the plant will reach our design capacity of 5.8 million gallons per day
somewhere around the year 1993• Our calculations show that at a yearly
average flow of 5.4 mgd, we will experience approximately 20 days where the
actual flow is over the design capacity of 5.8. Where the yearly average is
5.6, there will be 70-90 days where the flow is over the design capacity of
5.8. Therefore, based on the projections shown on the attached exhibit,
we will have to look at a plant expansion sometime prior to 1993•
it is felt that the City cannot be too conserva-ive in the planning of an
expansion at our White Slough Treatment Facility. The financing of future
expansions is going to become more critical due to the changes in the State
and Federal Grant Guidelines. Grants are no longer being given to provide
for plant expansions which are needed because of normal growth. These
types of expansions will have to be fully funded by the local agency.
Therefore, if money is going to have to be set aside, we should be looking
at the project planning and funding requirements now.
It is, therefore, recommended that $2800 be allocated for the purpose of
having the firm of Black b Veatch prepare the required Wastewater Treatment
Plant Expansion Schedule Report in conformance with their attached proposal
letter of Jul 4, 1984. A Special Allocation Request is attached.
eI
L.Ronsko
I Works Director
J
Attachments
cc: Water/Vastewater Superintendent
�CITY�� OF •
r7%a
SPECIAL ALL=REQUEST
TO: Finance Director
City Manager Date: 8/11/84
i
FROM: Pub] is Works Di rer_tor Account Number:t,-
Request is made for funds to accomplish the Following which was not included in the
current budget:
PROJECT DESCRIPTION & JUSTIFICATION
Wastewater Treatment Plant Expansion Schedule Report
Recommend that funds be allocated for purpose of having
Black b Veatch prepare above report per attached proposal
letter. See attached memo.
FUND OR ACCOUNT TO BE CHARGED
ESTIMATED COST
$2800.00
Current Budget
S
Prior Year Reserve
$
Contingent Fund
$
General Fund Surplus
$
Capital Outlay Reserve
S
Reimbursable count
$
1L �
Utility Outloy Reserve
S
/?EsE72tiE Fun./)
$ X800• `
of er
i
APPROVALS
Fund Verification
Approval
Finance Di
City Manager
dote
0 City Council
Amount Approved $ J
Submit this form in triplicate.