HomeMy WebLinkAboutAgenda Report - August 19, 1981 (38)PLEASANT AVE?JLJt:
CURB AND Gurri:k
REP IAC E14 ENT
APPROVED
Council was informed that the contract for "Pleasant
Avenue Curb and Gutter Replacement", which had been
awarder: to Teichert Construction Company of Stockton
on .Tune 3, 1981 in the amount of 531,331.70 has
been completed in substantial conformance with the
plans and specifications approved by the City Council.
COUNCIL ACCEPTED THE IMPROVDIENTS IN "PLEASANT
AVENUE CURB AND GUTTER REPLACEMENT - LODI AVENUE
TO WALNUT STREET" AND DIRECTED THE PUBLIC WORKS
DIRECTOR TO FILE A NOTICE OF COMPLETION WITH THE
COUNTY RECORDER'S OFFICE.
a
CITY OF LODI
PUBLIC WORKS DEPARTMENT
TO: City Council
COUNCIL COMMUNICATION
FROM: City Manager
DATE: September 14, 1981
SUBJECT: Acceptance of "Pleasant Avenue Curb b Gutter Replacement"
RECOMMENDED ACTION: That the City Council accept the improvements in "Lodi
Avenue to Walnut Street" and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Teichert Construction
of Stoc ton on June 3, 1981, in the amount of $31,331.70. The contract
has been completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion date was August 31, 1981, and the actual completion
date is September 11, 1981. The final contract price was $33.917.60. The
difference between the contract amount and the final contract price Is due
to the actual amount of asphalt concrete used to patch the street and changes
In the amount of sidewalk replaced.
Jack L. Ronsko
Public Works Director
JLR/eeh
APPROVED:
HENRY A. GLAVES. City Mana4er
FILE NO.