HomeMy WebLinkAboutAgenda Report - August 15, 1984 (61)AWARD City Manager Glaves presented the following bids which
C NIRACf FCR had been received for "Poplar Street Stone Drain,
POPLAR Stockton Street to Central Avenue":
mpimr Sim
DRAIN, BILDFR BID
STRELT TD Wayne Fregien $ 98,458.00 •-
CINIRAL
AVENUE Pacific Sun Construction, Inc. $102,944.85
Claude C. Wood C.orpany. Inc. $112,655.00
Mark III Engineering $115,352.35
This project includes the installation of 12" and 30"
stone drains in Poplar Street to relieve flooding on
Central Avenue, and curb and Butter replacement on
Central Avenue, from Poplar Street to Concord Street.
Following recenmendatton of the City Manager, Council
adopted the following Resolution:
RES. NO. RESOU117ICN ND. 84-120
84-120
RESOUMICN AWARDING THE CXNMACf FCR "POPLAR STREET SIORM
MAIN. STUC]UM SST TO (,'!:MEAT. AVRVV TO WAYNE
FRBGIEN IN IIIE AMaW OF $98.458.00.
CITY OF LODI
PUBLIC WORKS DEPARTMENT
VV
COUNCIL COMMUNICATION
TO:
City Council
Project Data
FROM:
City Manager
Approved in F.Y. Budget:
1984
Fund:
C,BG
DATE:
August 1C, 1984
Total Project Estimate:
$106,000
B i d Open ir}g Date:
8/10/84
SUBJECT:
Poplar Street Storm Drain
Stockton Street to Central Avenue
RECOMMENDED ACTION: That the City Council award the contract for the above
project to Wayne regien in the amount of $98,458.00.
BACKGP.OUND INFORMATION This project includes the installation of 12" and 30"
stormra nes in Poplar Street to relieve flooding on Central Avenue, and curb
and gutter replacement on Central A:enue, from Poplar Street to Concord Street.
Plans arsd specifications were approved on July 18, 1984.
The City has received the following 4 bids for this project:
BIDDER LOCATION BID
Wayne Fregien Stockton $ 98,458-.00
Pacific Sun Construction, Inc. Citrus Heights 102,944.85
Claude C. Wood Company, Inc. Lodi 112,655.00
Mark III Engineering Sacramento 115,352.35
Engineer's Estimate 92,000.00
A tabulation of the bids is attached.
'ack L. Ro o
Public Wor s Director
Attachment
cc: Assistant Finance Director
JLR:SB:dmw
APPROVED: I FILE X10.
HENRYA. CLAVES, City Manager
PdPIAR '0%ftT STORM DRA I N
Stocktbn Sirs et to Central
ITEM
NO.
2.
3.
4.
5.
6.
7.
8.
APPROXIMATE
ue
QUANTITY ..,.
DESCRIPTION
505 LF
Square-:ype Curb b Gutter
976 SF
S i dews l: b Residential
2.00
Drivaway
45 T
Asphalt Concrete
1,329 LF
30" Storm Drain
193 LF
12" Storm Drain
3 EA
48" Manhole
3 EA
Side Inlet Catch Basin
LUMP Sum
Excavation Safety
TOTAL
PACIFIC SUN
CONSTRUCTION. INC.
UNIT
TOTAL
PRICE
PRICE
S 13.00
$ 6,565.00
2.00
1,952.00
70.00
3.150.00
54.65
72,629.00
3.6:00
6,948.04
1,400.00
40700.00
500.00
1,500.00
LS
6.000.00
TOTAL $102.944.85
ENGINEER'S
ESTIMATE
UNIT
PRICE
$ 12.00
2.00
50.00
50.00
.)2.00
2,000.00
500.00
LS
CLAUDE C.
WOOD
COMPANY,
INC.
UNIT
TOTAL
PRICE
PRICE
$ 14.00
$ 7,070.00
4.00
3.904.00
110.00
4,956.00
61.00
81,069.00
34.00
6,5b2.00
1,200.00
39600.00
500.00
1,500.00
LS
4,000.00
$112,655.00
Tabulation of Bids received
TOTAL
PRICE
$ 6,060.00
1,952.00
2,250.00
66,450.00
6.176.00
6,000.00
1,500.00
1,612.00
$92,000.00
S98,4;.800
i�,a
WAYNE FRF.G I EN
UNIT
TOTAL
PRICE
PRICE1
$ 13.50
$ 6,817.5?
�z ;%
4.50
4.392.00
-00
sx
611.00
2,700`
56.50
7.5,;88-5Q'
.
20.003.860
00'->
I o2.00. 00
3,600 00
450.:00 '
1.350.0Y --k
.LS
65000
S98,4;.800
RESOLUTION NO. 84-120
AWARD - POPLAR STREET STORM DRAIN
STOCKTON STREET TO CENTRAL AVENUE
WHEREAS, in answer to notice duly published in
accordance with '.aw and the order of this City Council, sealed
bids were received and publicly opened by the City Clerk of
this City on August 8, 1984 at 11:00 a.m. for the contract for
Poplar Street Storm Drain, Stockton Street to Central Avenue.
as described in the specifications therefor approved by the
City Council August 15, 1984; and
WHEREAS, said bids have been compared, checked. and
tabulated and a report thereof filed with the City Manager as
follows:
BIDDER
Wayne Fregien
AMOUNT
$98,458.00
Mark III Enginneering $115,352.35
Pacific Sun Const. $102,944.85
Claude C. Wood Co. $112,655.00
WHEREAS. the City Manager recommends that award be
made to the low bidder. Wayne Fregien.
NOW, THEREFORE. BE IT RESOLVED by the City Council of
the City of Lodi that award of contract for Poplar Street
Storm Drain be and the same is hereby made to Wayne Fregien.
the low bidder, in the amount of $98,458.00.
Dated: August 15, 1984
I hereby certify that Resolution No. 84-120 was passed
and adopted by the City Council of the City of Lodi in
a regular meeting held August 15, 1984 by the
following vote:
Ayes: Council Members - llinchman, Pinkerton, Reid,
Olson, and Snider (Mayor)
Noes: Council Members - None
Absent: Council Members - None
AL:CE M. REINICHE
City Clerk
84-120