HomeMy WebLinkAboutAgenda Report - August 7, 1985 (106)Ci'I'i' MEETING
3 ff,S 7, 11985
CHEROKEE LANE
-
CURB, GUTTER AND
SIDEMUR WEST
f j
SIDE NORTH OF
LOC EFORD STREET
Council was informed that no bids were received on the
"Cherokee Lane Curb, Gutter and Sidewalk West Side North of.
Lockeford Street" project at a bid opening held August 7,
1985. It is proposed that the project be readvertised with
a bid opening of September 11, 1985. This project includes
the installation of curb, gutter, sidewalk and turf along
the west side of Cherokee Lane fronting the Grape Festival
grounds. The County is participating in the construction
cost; the City is providing the engineering.
i
a
}
—
r
CITYOF LODIPUBLIC WORKS DEPARTMENT
COUNCIL COMMUNICATION
T0: City Council
FROM: City Manager
DAeE: August 1, 1985
SUBJECT: Award Contracts: California St. Reconstruction. - Lockeford to Turner
Cherokee Lane improvements, West Side N/Lockeford
The bid openings for the above two projects is August 7, 198„ the day of the
City Council meeting. Due to the amount of work to be done on California St.
and the desire to complete the Cherokee Lane improvements prior to the Grape
Festival, it is important they be awarded as soon as possible.
Assuming there are no problems with the bids, an award recommendation will be
presented at the Council meeting on August 7.
Jac L. Ronsko
Public Works Director
CP/eeh
APPROVED:
THOMAS A. PETERSON, City Manager
FILE NO.