An Agreement was presented for Council's approval which
covers the installation of railroad grade crossing
protection at Washington Street. This project was
originally approved and budgeted for in the 1981 - 82
fiscal year. The improvements will be made by Southern
pacific Railroad Company and include the installation of
automatic gates and flashing light signals.
Federal funds cover 90% of the project. The City is
responsible for 10% which is estimated to be $13,600. TDA
funds in the amount of $7,000 had previously been budgeted
for this project. $7,000 of additional TDA funds will be
needed to cover the updated installation and engineering
costs. This special. allocation does not include funds to
cover the future extension of sidewalk or curb and gutter.