HomeMy WebLinkAboutAgenda Report - July 24, 1985 (95)Amarine irrigation System $18,702.13
$19,297.42
Western Well Drilling $19,166.00 ~
RES.N0.85-85 Following recccuendation of the City Manager, Council
adopted Resolution No. 85-85 awarding the contract for
"Well 21 PLurp and Motor (Lower Sacramento Road) " to
Noack Pump Company in the amount of $14,029.16.
-------7c=_
'✓'sem a'' .�, 3!:. x - 7 ��.L � •� i r � 3',.? �
CITY OFLODI
PUBLIC WORKS DEPARTMENT COUNCIL: COMMUNICATION
TO: City Council
FROM: City Manager
DATE: July 12, 1985
SUBJECT: Well 21 Pump & Motor
Project Data
Approved in F.Y. Budget: 1985
Fund: Water Capitai Outlay
Amount Budgeted: $175,000 (total)
Total Project Estimate: $23,000 (this
Bid Opening Date: 7/3/85 phase)
RECOMMENDED ACTION: That the City Council award the contract for the above
project to Noack Pump Co. in the amount of $14,029.16
BACKGROUND INFORMATION: This project consists of the purchase and installation
of a pump and above -ground motor for Well 21. The well is located on Lower
Sacramento Road north of Elm Street on a City -owned parcel (future fire house
site). -
Plans and specifications for this project were approved on June 19, 1985.
The City has received the following bids for this project:
BIDDER
Noack Pump
Central Pump Co.
Zim Industries
Amerine Irrigation System
Western Well Drilling
Eng-ineer's Estimate
LOCATION
Stockton
Modesto
Fresno
Oakdale
San Jose
The low bidder was also low under a 3 -year energy use analysis.
JJac L. Ronsko
Pub i c Works Director
cc: Assistant Finance Director
JLR/ RCP/eeh
APPROVED:
otM
$14,029.16
$15,326.00
$16,979.40
$18,702.13
$19,297,42
$19,166.00
$18,500.00
FILE 40.
RESOLUTION NO. 85-85
AWARD - CONTRACT FOR WELL 21 PUMP AND MO'T'OR
(LOWER SACRAMENTO ROAD)
WHEREAS, in answer to notice duly published in
accordance with law and the order of this Cit; Council,
sealed bids were received and publicly opened by the City
Clerk of this City on July 3, 1985 at 11:00 a.m. for the
contract for Well 21 Pump and Motor (Lower Sacramento Road)
as described in the specifications therefor approved by the
City Council June 19, 1985; and
WHEREAS, said bids have been compared, checked, and
tabulated and a report thereof filed with the City Manager
as follows:
Bidder. Amount
Noack $14,029.16
Amerine Irrigation System $18,702.13
$19,297.42
Zim I:.dustries $16,979.40
Central Pump Co. $15,326.00
Western Well Drilling $19,166.00
WHEREAS, the City Manager recommends that award be
made to the low bidder, Noack.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Lodi that award of contract for Well 21 Pump
and Motor be and the same is hereby made to Noack, the low
bidder, in the amount of $14,029.16.
Dated: July 24, 1985
I hereby certify that Resolution No. 85-85
was passed and adopted by the City Council
of the City of Lodi in an Adjourned regular
meeting held July 24, 1985 by the following
vote:
Ayes: Council Members - Olson, Pinkerton,
Reid, Snider, and
Hinchman (Mayor)
Noes: Council Members - None
Absent: Council Members - None
Al e M. eimche
City Clerk
85-85