HomeMy WebLinkAboutAgenda Report - July 20, 1983 (39)"HAM LANE AND STREET TRAFFIC SIGNAL INSTALLATION" AND DIRECTED THE PUBLIC
TOKAY STREET WORKS DIRBOMR TO FILE A NOTICE OF CCMPL ETION T 1.
S IGNhL
INSTAI.IATION The contract for this project was awarded to M 6 M Electric
APPROVED of Sacramento on April 20, 1983 in the amount of $29,229.00
and the contract has been completed in substantial
conformance with the plans and specifications approved by
the City Council
''�' Id,
\ Y.
.. � #•5. ' � - .a , � � , ; ✓mss
f n
y •„ .� . .
k
k 3 f y s o f9
s'c�, ,,C, lam• 5'(.51.�� r #sy ,y ,! ix��'T - .r, �" 4' ;,y H,at• `' } a .f�� . 'i.` _
?'fJ�
ri. '"irv""z 14 2� °
r1 i x .:" .n t r Z ),..r, d, ,;,c ` h. d. SC ti=+E, i'^ F .rte-: s2•
Ma�.., `moi L�,,,� a "•� s. � ��� .,+rG+.� e� � r �" �3 t�;>n3�� �'+ _ :��� .� �"=a.- � a �'' +:at4;e,r yv' i "�' 9. s�. ''% k sW'?�= `i
CITY O LODI
COUNCIL COMMUNICATI6N
PUBLIC WORKS DEPARTMENT
TO: City Council
FROM: City Manager
DATE: July 14, 1983
SUBJECT: Acceptance of "Marr. Lane and Tokay Street Signal installation"
RECOMMENDED ACTION: That the City Council accept the improvements in "Ham Lane
and Tokay Street Traffic Signal installation" and direct the Public Works Director
to file a Notice of Comp;etion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to M s M Electric of Sacramento
on April 20, 1983 in the amount of $ 29,229.00. The contract has been completed
In substantial conformance with the plans and specifications approved by the City
Council.
The contract completion date was June 2, 1983 and the actual completion date
Is July 12, 1983. The final contract price was $ 29,229.00.
IJac L. Ronsko
Pubc Works Director
`\ JLR/ ER/dh
APPROVED:
HENRY A. GLAVES, C ty.Manager
FILE NO.