HomeMy WebLinkAboutAgenda Report - July 17, 2013 C-07AGENDA ITEM C-07 CITY OF LODI COUNCIL COMMUNICATION • TM AGENDA TITLE: Accept Improvements Under Contract for Lodi Transit Station and Parking Structure Security and Safety System Project MEETING DATE: July 17, 2013 PREPARED BY: Public Works Director RECOMMENDED ACTION: Accept improvements under contract for Lodi Transit Station and Parking Structure Security and Safety System Project. BACKGROUND INFORMATION: The contract was awarded to 3D Datacom, of Rancho Cordova, in the amount of $280,892, on October 3, 2012. The contract has been completed in substantial conformance with the plans and specifications approved by City Council. The project included a network -based video surveillance and assessment system for the Lodi Transit Station and parking structure. Images are displayed on a LCD monitor located at the Lodi Transit Station clock tower and monitored by Transit's contract security guards and authorized individuals via the City's network. The images are recorded and saved on a server and accessible for investigations. The project included a total of 31 Internet Protocol (IP) type fixed -position and pan/tilt/zoom cameras. At the Lodi Transit Station, the project included cameras inside and outside the station buildings, monitoring the fare collection activity and the buses parked overnight in a non -secured area. At the parking structure, the project included cameras monitoring each floor, access points and elevator activities. Traffic calming (speed bumps) were included at the north and south entrances, slowing inbound and outbound traffic and allowing the cameras to record license plates. As part of this project, the Lodi Electric Utility Department crews installed fiber optic to the parking structure. The contract completion date was May 22, 2013. The final contract price was $294,899.50. The difference between the contract amount and the final contract price is due to a change order in the amount of $14,007.50 which upgraded all of the cameras to current, better quality products. Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: There will be an increase in the long-term maintenance costs associated with the installation of the security and safety equipment that will be funded by Transit operations. FUNDING AVAILABLE: This project was funded by Federal Transit Administration ARRA (CA -96-X052), Transportation Development Act/State Transit Assistance, and Proposition IB (TSSSDRA) funds. J F. Wallydelin Public Works Director Prepared Gary Wiman, Construction Project Manager FWS/GW/pmf cc: Transportation Manager/Senior Transportation Engineer n APPROVED: o adt Bartlam, City—Manager K:\WP\PROJECTS\TRANSIT\Securityand Safety\2012\CAccept.doc 6/25/2013