SUBJECT: Acceptance of "Maple St. Storm. Drain, Stockton to Central"
RECOMMENDED ACTION: That the City Council accept the improvements in Maple
St. Storm Drain, Stockton to Central and direct the Public Works Director to
file a Notice of Completion �:ith the County Recorder's cffice.
BACKGROUND INFORMATION: The contract was awarded to Downer ; Associates of
Stockton on July 5, 1984 in the amount of $69,395.00. The contract has been
completed in substantial conformance with the plans and specifications approved
by the City Council.
The contract completion date was September 16, 1984 and the actual completion date
is June 21, 1985. The final contract price was $71,232.00. The difference between
the contract amount and the final contract price is due to extra work required
by existing underground utilities.
L
Jac L. Ronsko
Public Works Director
JLR/GER/em
APPROVED: �-� 1� (.� � FILE NO.
THOMAS A. PETERSON, City Manager