HomeMy WebLinkAboutAgenda Report - June 25, 1986 (70)CITY COUNCIL MEETING
JUNE 25, 1986
ACCEPTANCE PUBLIC
SAFETY BUIIDING
EVAPORATIVE CONDENSER
REPLACEMENT Council accepted the im;:,rovements for "PSB Evaporative
Condenser Replacement" and dire -ted the Put:,lic Works
CC -20 Director to file a Notice of Ccwpletion with the county
CC -14(a) Recorder's Office.
Council was apprised that this contract had been awai-do.d to
Energy Wise of Stockton on March 5, 1986 in the arz)ur:t of
$13,900. The contract has been ccrri leted in substantial
conformance with the plans and specifications approved 13y
the City Council. The final contract amount was $13,900.
CITY O `_ LO D COU'NCIL COIIIMUNICATION
PUBLIC WORKS DEPARTMENT
T0: City Council Project Data
FROM: City Manager Originally Budgeted: 1985-86
DATE: June 17, 1986 Budgeted Fund: 121-350.57-519
Amount Budgeted: $12,500
SUBJECT: Public_ Safety Building Final Project Cost: $16,053.64
Evaporative Condenser Replacement Over -run Fund: General Fund
RECOMMENDED ACTION: That the City Council accept the improvements for "PSB
Evaporative Condenser Replacement," and direct the Public Works Director to
file a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Energy Wise of Stockton
on March 5, 1986, in the amount of $13,900. the contract has been completed
in substantial conformance with the plans and specifications approved by the
City Council.
The actual completion date was May 23, 1986. Through an oversight, work started
without ? signed contract and as a consequen6e, the contract date is meaningless.
The final contract amount was $13,900.
Ja k L. Ronsko
Pub is Works Director
JLR/eeh