HomeMy WebLinkAboutAgenda Report - June 19, 2013 C-12AGENDA ITEM &01 L
CITY OF LODI
COUNCIL COMMUNICATION
• TM
AGENDA TITLE: Adopt Resolution Awarding Contract for 2013-2015 Sidewalk Repair Program and
Miscellaneous Concrete Work to Popuch Concrete Contracting, Inc., of Lodi
($198,600) and Authorizing Public Works Director to Execute Extensions
MEETING DATE: June 19, 2013
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution awarding contract for 2013-2015 Sidewalk Repair
Program and Miscellaneous Concrete Work to Popuch Concrete
Contracting, Inc., of Lodi, in the amount of $198,600 and authorizing
Public Works Director to execute extensions.
BACKGROUND INFORMATION: This project will provide the City with a unit -price bid for removing
and/or constructing curb, gutter, and sidewalk in various locations
throughout the city. This is a two-year contract and will be used to
implement the sidewalk installation and repair program and to repair curb and gutter as needed during
Fiscal Years 2013/14.and 2014/15. Provisions in the specifications will allow the City to extend the - - -
contract if it is mutually agreed upon by City staff and the contractor. Staff recommends authorizing the
Public Works Director to execute two two-year extensions to the contract when it is in the best interest of
the City to do so.
Specifications for this project were approved on April 17, 2013. The City received the following two bids for
this project on May 29, 2013. One bid was non-responsive as it did not include the Receipt of Addendum.
Bidder
Location
Engineer's Estimate $ 275,500
Popuch Concrete Contracting, Inc. Lodi $ 198,600
Jeff Case Construction Galt $ 230,025*
'Non -Responsive
FISCAL IMPACT: This contract is a key component in the Streets and Drainage Division's ability
to perform necessary maintenance. It also minimizes the risk of liability
associated with damaged and/or non-compliant concrete improvements.
FUNDING AVAILABLE: This project will be funded by Measure K (325054) and Transportation
Development Act(TDA) Bike/Ped (1241014).
Jordan Ayers
Deputy City M
Prepared by Sean Nathan, Associate Civil Engineer
FWS/SN/pmf
cc: Associate Civil Engineer Nathan
City Engineer/Deputy Public Works Director
rAlWa:Z�1����
r/Internal Services Director
F. Wally S.4hdelin
Public Works Director
Deputy Public Works Director— Utilities
Konradt Bartlam, City Manager
K:\WP\PROJECTS\STREETS\2013 SidewalkRepair\CAward.doc 6/11/2013
2013-2015 SIDEWALK REPAIR PROGRAM AND
MISCELLANEOUS CONCRETE WORK CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and POPUCH CONCRETE CONTRACTING, INC., herein referred to
as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
Contract.doc 1 05/29/2013
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
Perform the work necessary to remove and replace curb, gutter and sidewalk in various
locations throughout the City and other incidental and related work, all as described in the
specifications for the above project. This is a 2 -year unit price bid and the work will be divided
into work orders which will usually range in price between $500 and $20,000, all as shown in
the specifications for "2013-2015 Sidewalk Repair Program and Miscellaneous Concrete Work".
See Section 6-07 "Description of Bid Items" for additional information.
CONTRACT ITEMS
Bid
Item
Description
Unit
Estimated
Quantity
Unit Price
Total
No.
1
Saw Cut Concrete
LF
1,500
$ 3.80
$ 5,700.00
2
Remove Sidewalk or Asphalt Concrete
SF
12,000
$ 3.25
$ 39,000.00
3
Remove Commercial Sidewalk
SF
100
$ 5.00
$ 500.00
4
Remove Square -Type Curb and Gutter
LF
500
$ 8.00
$ 4,000.00
5
Remove Vertical -Type Curb and Gutter
LF
50
$ 9.00
$ 450.00
6
Remove Driveway -Type Curb and
LF
50
$ 11.00
$ 550.00
Gutter
7
Remove Commercial -Type Curb and
LF
50
$ 11.00
$ 550.00
Gutter
8
Root Surgery Under Sidewalk or in
EA
100
$ 250.00
$ 25,000.00
Planter Area
9
Root Surgery Under Curb and Gutter
EA
20
$ 300.00
$ 6,000.00
10
Install Sidewalk or Residential
SF
100
$ 10.00
$ 1,000.00
Driveway 0 - 75 SF
11
Install Sidewalk or Residential
SF
4,000
$ 6.50
$ 26,000.00
Driveway 76 - 300 SF
12
Install Sidewalk or Residential
SF
6,000
$ 4.70
$ 28,200.00
Driveway >300 SF
Contract.doc 1 05/29/2013
Bid
Item
Description
Unit
Estimated
Quantity
Unit Price
Total
No.
13
install Commercial Driveway
SF
300
$ 9.00
$ 2,700.00
14
Install Square -Type Curb and Gutter 7-
LF
100
$ 42.00
$ 4,200.00
inch or less 0 - 20 LF
15
Install Square -Type Curb and Gutter 7-
LF
300
$ 37.00
$ 11,100.00
inch or less >20 LF
16
Install Square -Type Curb and Gutter
LF
100
$ 42.00
$ 4,200.00
Greater than 7 -inch 0 - 20 LF
17
Install Square -Type Curb and Gutter
LF
300
$ 37.00
$ 11,100.00
Greater than 7 -inch >20 LF
18
Install Vertical -Type Curb and Gutter
LF
50
$ 45.00
$ 2,250.00
0-20 LF
19
Install Vertical -Type Curb and Gutter
LF
50
$ 37.00
$ 1,850.00
>20 LF
20
Install Driveway -Type Curb and Gutter
LF
50
$ 48.00
$ 2,400.00
0-20 LF
21
Install Driveway -Type Curb and Gutter
LF
50
$ 42.00
$ 2,100.00
>20 LF
22
Install Tree Well
EA
5
$ 250.00
$ 1,250.00
23
Install Furnished Side -Inlet Catch
EA
2
$ 625.00
$ 1,250.00
Basin Assembly
24
Install Catch Basin Barrel
EA
2
$ 1,150.00
$ 2,300.00
25
Install Furnished Street Name Sign
EA
2
$ 100.00
$ 200.00
Base
26
Miscellaneous Concrete Subgrade
SF
12,000
$ 1.00
$ 12,000.00
Compaction
27
Move -In Cost for Jobs Less Than $200
EA
5
$ 550.00
$ 2,750.00
TOTAL: $198,600.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
Contract.doc 3 05/29/2013
ARTICLE VIII - The length of the contract will be twenty-four (24) months, starting July 1, 2013
and ending June 30, 2015. The contract may be extended if agreed upon by the Contractor
and the City.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Konradt Bartlam
City Manager
By: Date:
Title
Attest
City Clerk
(CORPORATE SEAL) Approved As To Form
D. Stephen Schwabauer
City Attorney 9��
Contract.doc 4 05/29/2013
RESOLUTION NO. 2013-108
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING AND
AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT FOR
2013-2015 SIDEWALK REPAIR PROGRAM AND MISCELLANEOUS
CONCRETE WORK AND FURTHER AUTHORIZING THE PUBLIC
WORKS DIRECTOR TO EXECUTE EXTENSIONS
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on May 29, 2013, at
11:00 a.m., for 2013-2015 Sidewalk Repair Program and Miscellaneous Concrete Work,
described in the specifications therefore approved by the City Council on April 17, 2013; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder Bid
Popuch Concrete Contracting, Inc. $ 198,600
Jeff Case Construction $ 230,025*
*Non -Responsive
WHEREAS, staff recommends awarding the contract for 2013-2015 Sidewalk Repair
Program and Miscellaneous Concrete Work to the low bidder, Popuch Concrete Contracting,
Inc., of Lodi, California, in the amount of $198,600.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for 2013-2015 Sidewalk Repair Program and Miscellaneous Concrete Work to the
low bidder, Popuch Concrete Contracting, Inc., of Lodi, California, in the amount of $198,600;
and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract; and
BE IT FURTHER RESOLVED that the Public Works Director is hereby authorized to
execute two 2 -year extensions if in the best interests of the City.
Dated: June 19, 2013
------------------------------------------------------------------------
------------------------------------------------------------------------
I hereby certify that Resolution No. 2013-108 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 19, 2013, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Mounce
ABSTAIN: COUNCIL MEMBERS — None
HL
City Clerk
2013-108