HomeMy WebLinkAboutAgenda Report - June 17, 1987 (70)TO. THE CITY COUNCIL DATE
FROM: THE CITY MANAGER'S OFFICE June 17, 1987
SUBJECT. SPECIFICATIONS FOR THE FT-RC'_iASE OF POWER TRANSFORMER (EUD-87-5)
N0
RECOMMENDED ACTION: That the City Council approve the specifications for
the purchase of one 60/12 kv, 35 MVA, three-phase power trap -former and
authorize advertisement for bids thereon. The bid opening date has been
set for August 4. 1987.
BACKGROUND INFORMATION: This power transformer will be installed at
McLane Substation as a part of the Phase 2 development now in progress.
The second McLane Substati 7. transformer is required to supply the area
load, including a large industrial load now being developed, under 'emergency'
conditions, commencing with the 1988 summer season, and will be needed to
supply the 'normal' load in subsequent veers. The cost estimate for this
Funding for this purchase is ircluded in the Electric Utility Department's
1987-88 budget.
Henry J. RiA All_
Electric Utility Director
cc: Assist. Electric Utility Director
Electrical Engineer
Purchasing Officer