HomeMy WebLinkAboutAgenda Report - June 4, 1986 (65)IMPROVEMENTS IN NODI
GRAPE BOWL INTERIOR
FENCING ACCEPTED Council accepted the improvements for Lodi Grape Bowl
Interior Fencing and directed the Public Works Director to
CC -14(a) file a Notice of Completion with the County Recorder's
Office. The contract was awarded to Frontier Guardco, Inc.
of Sacramento on April 3, 1986, in the amount of $17,314.50.
The contract has been completed in substantial conformance
with the plans and specifications approved by the City
Council. The final contract price was $17,645.43. The
difference between the contract amount and the final
contract price is mainly due to relocation of fence posts
interfering with the full opening of the metal doors on the
restroom/concession building.
TO:
FROM:
DATE:
SUBJECT:
CITY OF LODI
PUBLIC WORKS DEPARTMENT
City Council
City Manager
May 28, 1986
Lodi Grape Bowl Interior Fencing
COUNCIL CONIMUNICATION
Pro iect Data
Originally Budgeted: 1985
Budgeted Fund: Capital Outlay Reserve
Amount Budgeted: $30,000
Fund Project Cost: Approx. $23,000
RECOMMENDED -ACTION: That the City Council accept the improvements for Lodi
Grape Bowl Interior Fencing, and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Frontier Guardco Inc. of
Sacramento on April 3, 1986, in the amount of $17,314.50. The contract has
been completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion date was June 5, 1986, and the actual completion date
is May 28, 1986. The final contract price was $17,645.43. The difference
between the contract amount and the final contract price is mainly due to
relocation of fence posts interfering with the full opening of the metal doors
on the restroom/concession building.
Jac L. Ronsko
Public Works Director
Parks G Recreation Director
JL R/ RCP/eeh
APPROVED: FILE NO.
THOMAS A. PETERSON, City Manager