HomeMy WebLinkAboutAgenda Report - May 15, 1985 (106)Y
CITY COUNCIL MEETING
;,
;•� Nom' .15, 1985
AWARD CONTRACT
"GRAPE BOWL
PESTRO014
AND CONCESSION
STAND RENOVATION"
City Manager Peterson presented
the following bids which
had been received for "Grape Bowl Restroom and Concession
Stand Renovatior":
BIDDER
BID
•
RHS Construction, Inc.
$ 89,140
Lane Allen Construction
$ 89,748
Hughes Construction
$ 90,783
Diede Construction
$100,000
J r
E
OF LO®i COUNCIL COMMUNICATIONWORKS DEPARTMENT
TO: City Council Project Data
z:-
FROM: City Manager
Approved in F.Y. Budget: 1984
Fund: 148.0 r:
DATE: May -9, 1985 Amount Budgeted: $145,000 r,
Total Project Estimate: $100,000
SUBJECT: Grape Bowl Restroom and Bid Opening Date: 5/8/85 a
Concession Stand Renovation €'
RECOMMENDED ACTION: That the City Council award the contract for the above project
to RHS Construction Inc. in the amount of $89,140.
BACKGROUND.INFORMATION: This project consists of roofing, pa7nting, and re-
modeling of the two restroom and concession stands at the Grape Bowl. Work will
not interfere with high school graduation and will be completed prior to the
first football game.
The City has received the following four bids for this project:
BIDDER LOCATION BID
RHS Construction, Inc. Sacramento $ 89,140
Lane Allen Construction Jackson $ 89,748
Hughes Construction Stockton $ 90,783
Diede Construction Woodbridge $100,000
Architect's stimate $ 87,000
,N _
Jac ,L. Ronsko
Pub] 'c Works Director
cc. Assistant. Finance Director
Recreation & Parks Director
JLR/GER/een
t
f,
k
4
G'
3:
t
APPROVED: _ FILE NO.
THOMAS. A. PETERSON, City Manager