HomeMy WebLinkAboutAgenda Report - May 6, 1987 (56). °• 1T i r) I
PUSiliC WORKS DEPART"MEN,
COUNCIL COM.I'MU ICAsION
RECOMMENDED ACTION: That the City Council accept the improvements for the
"Traffic Signal Installations, Ham and Lockeford, Turner and Church, Contract"
and direct the Public Works Director to file a Notice of Completion with the
County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Collins Electric of
Stockton on ctober I, 1986. in the amount of $11+,441.50. The contract has
been completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion dste ;:as March 10, 1981, and the actual completion
date was April 17, 1987: The final contract price was $118,846.73. The
difference between the contract amount and the final contract price is mainly
due to additional curb, gutter, and sidewalk and driveway work.
/ J-ack . Ronsko
!, Publi `works Director
JL JF/ma
APPROVED: — — FILE H0.
6N, Cjty Mana er
April 29, 1987
CTRAFSIG/TXTW.02M
Pro ect D; to
TO:
City
Council
Originally Budgeted:
S160,000
Dev. Act
Budgeted Fund:
Trans.
FROM:
City
Manager
Amount Budgeted:
Final Project Cost:
$160,000
$171,500
MEETING DATE:
May
6, 1987
Overrun Fund:
Trans. Dev. Act
SUBJECT:
Accept
Improvements
Under Traffic Signal Installations, Ham
and
Lockeford, Turner and Church, Contract
RECOMMENDED ACTION: That the City Council accept the improvements for the
"Traffic Signal Installations, Ham and Lockeford, Turner and Church, Contract"
and direct the Public Works Director to file a Notice of Completion with the
County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Collins Electric of
Stockton on ctober I, 1986. in the amount of $11+,441.50. The contract has
been completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion dste ;:as March 10, 1981, and the actual completion
date was April 17, 1987: The final contract price was $118,846.73. The
difference between the contract amount and the final contract price is mainly
due to additional curb, gutter, and sidewalk and driveway work.
/ J-ack . Ronsko
!, Publi `works Director
JL JF/ma
APPROVED: — — FILE H0.
6N, Cjty Mana er
April 29, 1987