HomeMy WebLinkAboutAgenda Report - May 6, 1981 (68)0 CITY QF LODI
PUBLIC WORKS DEPARTMENT
COUNCIL COMMUNICATION
TO: City Council
FROM: City Manager
DATE: Ap r i 1 28, 1`981
SUBJECT: Plans and Specifications for "MUNICIPAL SERVICE CENTER, PHASE 111"
RECOMMENDED ACTION: That the City Council approve the plans and specifi-
cations for the above project and authorize the City Clerk to advertise for
bids to be received Wednesday, May 27, 1981.
BACKGROUND INFORMATION: The construction of Municipal Service Center Open
Storage was approved n the 1979-80 Capital Improvement Budget. This is the
last major phase of the MSC construction.
In general, the work consists of construction of access roadways, valley
gutters, and storage bins. Construction of underground drainage, fire pro-
tection and gravel storage areas have previously been accomplished by contract
and City forces.
The total cost of the remaining MSC work is estimated at $85,000. There
presently remains about $53,000 for completion of the MSC complex. Therefore,
a special allocation will be needed depending upon actual bid price.
4lic
L. Ronsko
Works Director
JLR:dmw
APPROVED:
HENRY A. CLAVES. City Manager
FILE NO.