HomeMy WebLinkAboutAgenda Report - April 17, 2013 C-17AGENDA ITEM C tol (1) 1 COUNCIL TM AGENDA TITLE: Adopt Resolution Awarding Contract for Reynolds Ranch Parkway Median Improvements Project to Anchor Concrete Construction, Inc., of Antioch ($29,846) and Appropriating Funds ($37,000) MEETING DATE: PREPARED BY: April 17, 2013 Public Works Director RECOMMENDED ACTION: Adopt resolution awarding contract for Reynolds Ranch Parkway Median Improvements Project to Anchor Concrete Construction, Inc., of Antioch, in the amount of $29,846 and appropriating funds in the amount of $37,000. BACKGROUND INFORMATION: This project consists of removing existing landscape elements in the narrow part of the median, installing stamped concrete, and other incidental and related work, all as shown on the plans and specifications for the project. The location of the project is shown on Exhibit A. The existing landscape elements in the median along Reynolds Ranch Parkway were installed in 2009, as part of the Reynolds Ranch improvements. The plants in the narrow part of the median, where the width is less than four feet, are not doing well and are difficult to maintain. The landscape elements in these narrow portions will be removed and replaced with stamped concrete, improving the esthetics of the median and also reducing the long-term maintenance costs in the area. Plans and specifications for this project were approved on March 6, 2013. The City received the following seven bids for this project on March 27, 2013. Bidder Location Bid Engineer's Estimate $ 28,965.00 Anchor Concrete Construction, Inc. Antioch $ 29,846.00 Sierra National Construction Carmichael $ 31,336.00 Cal Pacific Curb Salida $ 32,889.30 B & M Builders, Inc. Rancho Cordova $ 37,682.50 Biondi Paving Sacramento $ 38,797.00 A. M. Stephens Construction Lodi $ 42,566.00 A -Vet Construction Woodbridge $ 73,051.80 The requested appropriation of $37,000 covers engineering, construction, inspection, and project contingencies. FISCAL IMPACT: This project will reduce the long-term maintenance costs of the Reynolds Ranch Parkway median. _"COT:1 i Bartlam, City Manager K:\WPNPROJECTS\STREETS\ReynoldsRanchPkwyMedian\CAward.doc 4/4/2013 Adopt Resolution Awarding Contract for Reynolds Ranch Parkway Median Improvements Project to Anchor Concrete Construction, Inc., of Antioch ($29,846) and Appropriating Funds ($37,000) April 17, 2013 Page 2 FUNDING AVAILABLE: Requested Appropriation: Measure K (325058): $37,000 Jor an Ayers Deputy City Manager/Interna Services Director & a161 1,'� F. Wally SarElefin Public Works Director Prepared by Lyman Chang, Senior Engineer FWS/LC/pmf Attachment Cc: Senior Civil Engineer Management Analyst Deputy Public Works Director — Utilities K:\WP\PROJECTS\STREETS\ReynoldsRanchPkwyMedian\CAward.doc 4/4/2013 �Cy`�7rOQ OF • . PUBLIC WORKS DEPARTMENT EXHIBIT A Reynolds Ranch Parkway Median Improvement Project K:\CADD\PROJECTS\2013\013D003\013D003.dwg, EXHIBIT A, 02/14/2013 11:36:48 AM REYNOLDS RANCH PARKWAY MEDIAN IMPROVEMENT PROJECT CONTRACT CITY OF LODI, CALIFORNIA THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred to as the "City," and ANCHOR CONCRETE CONSTRUCTION, INC., herein referred to as the "Contractor." WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and agree with each other, as follows: The complete Contract consists of the following documents which are incorporated herein by this reference, to -wit: Notice Inviting Bids Information to Bidders General Provisions Special Provisions Bid Proposal Contract Contract Bonds Plans The July 1992 Edition, Standard Specifications, State of California, Business and Transportation Agency, Department of Transportation All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are intended to cooperate so that any work called for in one and not mentioned in the other is to be executed the same as if mentioned in all said documents. ARTICLE I - That for and in consideration of the payments and agreements hereinafter mentioned, to be made and performed by the City and under the condition expressed in the two bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with the City, at Contractor's cost and expense, to do all the work and furnish all the materials except such as are mentioned in the specifications to be furnished by the City, necessary to construct and complete in a good workmanlike and substantial manner and to the satisfaction of the City the proposed improvements as shown and described in the Contract Documents which are hereby made a part of the Contract. ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does hereby employ, the Contractor to provide all materials and services not supplied by the City and to do the work according to the terms and conditions for the price herein, and hereby contracts to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the General Provisions, in the manner and upon the conditions above set forth; and the said parties for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree to the full performance of the covenants herein contained. ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing wage rate and other employer payments for health and welfare, pension, vacation, travel time, and subsistence pay, apprenticeship or other training programs. The responsibility for compliance with these Labor Code requirements is on the prime contractor. 03/28/13 ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full compensation for furnishing all materials and for doing all the work contemplated and embraced in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its acceptance by the City, and for all risks of every description connected with the work; also for all expenses incurred by or in consequence of the suspension or discontinuance of work and for well and faithfully completing the work, and the whole thereof, in the manner and according to the Plans and Contract Documents and the requirements of the Engineer under them, to -wit: Perform the work necessary to remove existing landscape elements in the median, install colored stamped concrete, and other incidental and related work, all as shown on the plans and specifications for "Reynolds Ranch Parkway Median Improvement Project". CONTRACT ITEMS ITEM EST'D. NO. DESCRIPTION UNIT QTY 1. Traffic Control LS 1 2. Clearing and Grubbing LS 1 3. Storm Water Erosion Control LS 1 4. Miscellaneous Concrete Subgrade Compaction SF 2,290 5. Concrete Median SF 2,290 UNIT PRICE TOTAL PRICE $ 3,000.00 $ 3,000.00 $ 9,743.50 $ 9,743.50 $ 500.00 $ 500.00 $ 1.25 $ 2,862.50 $ 6.00 $13,740.00 TOTAL $29,846.00 ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the provisions of Section 3700 of the Labor Code, which requires every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract. ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there be any conflict between the terms of this instrument and the Bid Proposal of the Contractor, then this instrument shall control and nothing herein shall be considered as an acceptance of the said terms of said proposal conflicting herewith. ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to establish lines and grades for the work as specified under the Special Provisions. All labor or materials not mentioned specifically as being done by the City will be supplied by the Contractor to accomplish the work as outlined in the specifications. 2 03/28/13 ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15 calendar days after the City Manager has executed the contract and to diligently prosecute to completion within 30 CALENDAR DAYS. WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT. IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year and date written below. CONTRACTOR: CITY OF LODI M Title By: Konradt Bartlam City Manager Date: Attest City Clerk (CORPORATE SEAL) Approved As To Form D. Stephen Schwab uer City Attorney r RnniraM rine. 3 03/28/13 1. AA# 2. JV# U_ 1VIE�1 FUND # I • S SST BUS. UNIT # ACCOUNT # ACCOUNT TITLE AMOUNT A. SOURCE OF FINANCING 325 3205 (Fund Balance $ 37 000.00 B. USE OF FINANCING 325 325058 7720 Reynolds Ranch Parkway Median 37 000.00 Please provide a description of the project, the total cost of the project, as well as justification for the requested adjustment. If you need more space, use an additional sheet and attach to this form. Contract with Anchor Concrete Construction for the Reynolds Ranch parkway median improvement project. F Council has authorized the appropriation adjustment, complete the following: eting Date: Res No: Attach copy of resolution to this form. Department Head Signature: Submit completed form to the Budget Division with any required documentation. Final approval will be provided in electronic copy format. RESOLUTION NO. 2013-59 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT FOR REYNOLDS RANCH PARKWAY MEDIAN IMPROVEMENTS PROJECT AND FURTHER APPROPRIATING FUNDS WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on March 27, 2013, at 11:00 a.m., for the Reynolds Ranch Parkway Median Improvements Project, described in the plans and specifications therefore approved by the City Council on March 6, 2013; and WHEREAS, said bids have been checked and tabulated and a report thereof filed with the City Manager as follows: Bidder Bid Engineer's Estimate $ 28,965.00 Anchor Concrete Construction, Inc. $ 29,846.00 Sierra National Construction $ 31,336.00 Cal Pacific Curb $ 32,889.30 B & M Builders, Inc. $ 37,682.50 Biondi Paving $ 38,797.00 A. M. Stephens Construction $ 42,566.00 A -Vet Construction $ 73,051.80 WHEREAS, staff recommends awarding the contract for the Reynolds Ranch Parkway Median Improvements Project to the low bidder, Anchor Concrete Construction, Inc., of Antioch, California, in the amount of $29,846. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the contract for the Reynolds Ranch Parkway Median Improvements Project to the low bidder, Anchor Concrete Construction, Inc., of Antioch, California, in the amount of $29,846; and BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the contract; and BE IT FURTHER RESOLVED that funds in the amount of $37,000 be appropriated from Measure K funds for the project. Dated: April 17, 2013 I hereby certify that Resolution No. 2013-59 was passed and adopted by the City Council of the City of Lodi in a regular meeting held April 17, 2013, by the following vote: AYES: COUNCIL MEMBERS — Hansen, Johnson, and Katzakian NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — Mounce and Mayor Nakanishi ABSTAIN: COUNCIL MEMBERS — None RANDI JOHL City Clerk 2013-59