HomeMy WebLinkAboutAgenda Report - April 17, 2013 C-14AGENDA ITEM C#' 4
CITY OF LODI�,.
Oq<IFOiL P COUNCIL
AGENDA TITLE: Adopt Resolution Awarding Contract for DeBenedetti Park ADA Access
Improvement Project to A. M. Stephens Construction Company, Inc., of Lodi
($126,736.50) and Appropriating Funds ($158,000)
MEETING DATE:
PREPARED BY:
April 17, 2013
Public Works Director
RECOMMENDED ACTION: Adopt resolution awarding contract for DeBenedetti Park ADA
Access Improvement Project to A. M. Stephens Construction
Company, Inc., of Lodi, in the amount of $126,736.50, and
appropriating funds in the amount of $158,000.
BACKGROUND INFORMATION: This project will improve accessibility to DeBenedetti Park. The
improvements will consist of a paved parking lot entrance, two
concrete ADA -compliant parking stalls, accessible paths to the
bottom of the north and south basins, sidewalk completion along Century Boulevard and other incidental
and related work, all as shown on the plans and specifications for the project. The proposed
improvements are shown in Exhibit A.
Plans and specifications for this project were approved on March 6, 2013. The City received the
following 10 bids for this project on March 27, 2013.
Bidder
Location
Bid
Engineer's Estimate
$ 158,055.00
A. M. Stephens Construction
Lodi
$ 126,736.50
A -Vet Construction
Woodbridge
$ 135,322.56
Abide Builders
Vacaville
$ 147,307.00
Biondi Paving
Sacramento
$ 142,571.00
Sierra National Construction
Carmichael
$ 171,125.00
BC Construction
Ceres
$ 171,591.25
Glissman Excavating
Loomis
$ 189,404.65
Andrew L. Lee, Inc.
Lodi
$ 214,390.00
Cazadores Construction
El Dorado Hills
$ 214,796.10
George Reed, Inc.
Modesto
$ 220,083.00
The requested appropriation of $158,000 covers engineering, construction, inspection and project
contingencies.
FISCAL IMPACT: There will be a small increase in the park's maintenance cost associated
with the addition of asphalt, concrete, signs and striping.
APPROVED: (-,
onradt Bartlam, City Manager
K:\WP\PROJECTS\PARKS\DeBenedetti(G-Basin)WDA Access Improvement\CAward.doc
4/1/2013
Adopt Resolution Awarding Contract for DeBenedetti Park ADA Access Improvement Project to
A. M. Stephens Construction Company, Inc., of Lodi ($126,736.50) and Appropriating Funds ($158,000)
April 17, 2013
Page 2
FUNDING AVAILABLE: Requested Appropriation:
Parks Impact Fees (1217043): $158,000
Jordan Ayers
Deputy City Manager/Internal Services Director
IJ , JIA 1 ..4. 1 - I
F. Wally 4ndelin
Public Works Director
Prepared by Sean Nathan, Associate Engineer
FWS/SN/pmf
Attachment
cc: Associate Civil Engineer
Management Analyst
Parks, Recreation and Cultural Services Director
K:\WP\PROJECTS\PARKS\DeBenedetti(G-Basin)\ADAAccess Improvement\CAward.doc 4/1/2013
DEBENEDETTI PARK ADA ACCESS IMPROVEMENT PROJECT
2150 South Lower Sacramento Road CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and A. M. STEPHENS CONSTRUCTION COMPANY, INC., herein
referred to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
DebenedettiParkADAAccess4.doc 1 03/27113
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of constructing a parking lot and entrance of 82 tons of asphalt and 477
square feet of concrete. Also includes construction of 3,210 square feet of concrete walkway
down the basin side slopes and 6,580 square feet of concrete sidewalks and other incidental
and related work, all as shown on the plans and specifications for "DeBenedetti Park ADA
Access Improvement Project, 2150 South Lower Sacramento Road".
CONTRACT ITEMS
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
1. Traffic Control LS 1 $ 1,500.00 $ 1,500.00
2. Clearing, Grubbing, and
Demolition LS
3. Remove and Salvage Existing
Chain Link Fence LF
1 $ 12,430.00 $12,430.00
1,815 $ 1.20 $ 2,178.00
4. Relocate Trees
EA
6
$
340.00
$ 2,040.00
5. Tree Planting
EA
2
$
340.00
$ 680.00
6. Basin Slope Walkway Grading
SF
9,060
$
1.25
$11,325.00
7. Pavement Excavation
CY
41
$
93.00
$ 3,813.00
8. Asphalt Concrete
TON
82
$
150.00
$12,300.00
9. Concrete Parking Stalls (ADA)
SF
477
$
6.50
$ 3,100.50
DebenedetiiParkADAAccess4.doc 2 03/27/13
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
10. 4 -Inch Thick Concrete Sidewalk,
Curb Ramp and Concrete
Transitions SF 6,580 $ 4.50 $29,610.00
11. 6 -Inch Thick Concrete Walk SF 3,210 $ 6.70 $21,507.00
12. Concrete Curb with 2 -Foot
17. Dead -End Barricade
(Pedestrian)
Openings
LF
81
$
23.00
$
1,863.00
13.
Concrete Curb
LF
106
$
19.00
$
2,014.00
14.
Truncated Dome Panels
SF
66
$
32.00
$
2,112.00
15.
Concrete Wheel Stop
EA
2
$
45.00
$
90.00
16.
Bollards and Chain with
65.00
$ 1,300.00
21. Signage and Striping
LS
1
$
3,330.00
Reflectors
LS
1
$
1,100.00
$
1,100.00
17. Dead -End Barricade
(Pedestrian)
EA
1
$
510.00
$ 510.00
18. Replace Turf on Impacted Areas
SF
5,850
$
2.20
$12,870.00
19. Install 3 -Inch Diameter Schedule
80 PVC Irrigation Sleeve
LF
38
$
28.00
$ 1,064.00
20. Install 8 -Inch Diameter Schedule
80 PVC Irrigation Sleeve
LF
20
$
65.00
$ 1,300.00
21. Signage and Striping
LS
1
$
3,330.00
$ 3,330.00
TOTAL
$ 126,736.50
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
DebenedettiParkADAAccess4.doc 3 03/27/13
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE Vlll - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 35 CALENDAR DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Konradt Bartlam
City Manager
By: Date:
Title
Attest
City Clerk
(CORPORATE SEAL) Approved As To Form
D. Stephen Schw��,
City Attorney
Debenedet iParkADAAccess4.doc 4 03/27/13
1. AA#
2. JV#
�+REQUES:T°A�:1lZS
ME,. ,�0 b RIA ASYLI$'-. 0 B
FUND # BUS. UNIT # ACCOUNT # ACCOUNT TITLE AMOUNT
A.
SOURCE OF
FINANCING
1217 3205 Fund Balance 158 000.00
B.
USE OF
FINANCING
1217 1217043 1825.2300 DeBenedetti Park ADA $ 158 000.00
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Contract withy AM Stephens for DeBenedetti Park ADA access improvement project.
If Council has authorized the appropriation adjustment, complete the following:
Meeting Date: lRes No. _I Attach copy of resolution to this form.
Department Head Signature:
Submit completed form to the Budget Division with any required documentation,
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2013-65
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING AND
AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT FOR
DEBENEDETTI PARK AMERICANS WITH DISABILITIES ACT ACCESS
IMPROVEMENT PROJECT AND FURTHER APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of this
City Council, sealed bids were received and publicly opened on March 27, 2013, at 11:00 a.m., for
the DeBenedetti Park Americans with Disabilities Act (ADA) Access Improvement Project described
in the plans and specifications therefore approved by the City Council on March 6, 2013; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with the
City Manager as follows:
Bidder Bid
Engineer's Estimate
$
158,055.00
A. M. Stephens Construction
$
126,736.50
A -Vet Construction
$
135,322.56
Abide Builders
$
147,307.00
Biondi Paving
$
142,571.00
Sierra National Construction
$
171,125.00
BC Construction
$
171,591.25
Glissman Excavating
$
189,404.65
Andrew L. Lee, Inc.
$
214,390.00
Cazadores Construction
$
214,796.10
George Reed, Inc.
$
220,083.00
WHEREAS, staff recommends awarding the contract for the DeBenedetti Park ADA Access
Improvement Project to the low bidder, A. M. Stephens Construction Company, Inc., of Lodi,
California, in the amount of $126,736.50.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the
contract for the DeBenedetti Park Americans with Disabilities Act (ADA) Access Improvement
Project to the low bidder, A. M. Stephens Construction Company, Inc., of Lodi, California, in the
amount of $126,736.50; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract.
BE IT FURTHER RESOLVED that funds in the amount of $158,000 be appropriated from the
Parks Impact Fees account for this project.
Dated: April 17, 2013
I hereby certify that Resolution No. 2013-65 was passed and adopted by the City Council of
the City of Lodi in a regular meeting held April 17, 2013, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, and Katzakian
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Mounce and Mayor Nakanishi
ABSTAIN: COUNCIL MEMBERS — None
JOHL
City Clerk
2013-65