HomeMy WebLinkAboutAgenda Report - March 18, 1981 (36)ACCEPTANCE OF Council was apprised that the improvements in "Mu
"MUNICIPAL cipal Service Centex-, Phase II" have been complet
SERVICE CENTER, in substantial conformance with the plans and
PHASE II" specifications approved by the City Council.
The contract was awarded to Brown Sheet Metal
and Mechanical, Inc., of Oakdale on February 6,
1980 in the amount of $588,220.00. The final
contract price was $632,407.71. The difference
between the contract amount and the final contract
price is due primarily to the replacement of a
sewer line in the building area under this
contract.
COUNCIL ACCEPTED THE IMPROVEMENTS IN `°MUNICIPAL,
SERVICE CENTER, PHASE II" AND DIRECTED THE PUBLIC
WORKS DIRECTOR TO FILE A NOTICE OF COMPLETION
THEREON.
TO; City Cwncll
FROM: City Manager
®ATE: Ma rch 13, 1981
SUBJECT: Acceptance of 'Municipal Service Center, Phase 11"
RECOMMENDED ACTION: That the City Council accept the improvements in
Mun I c pal Sery ca Center, Phase 11" and direct the Public Works Director
to file a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Brown Sheet Metal &
Mechanical, Inc. of Oakdale on February 6, 1980, in the amount of $588,220.
The contract has been completed in substantial conformance with the plans
and specifications approved by the City Council.
The contract completion date was July 1, 1980, and the actual completion date
is March 13, 1981. The final contract price was $632,407.71. The difference
between the contract amount and the final contract price Is due primarily to
the replacement of a sewer line in the building area under this contract.
This work ($4o,475.85) was budgeted as a separate CIP project. There were also
additional costs for tying the roof drains to the storm drain system, additional
work on a block wall, and extra conduits and pull boxes for feeders to the
covered parking areas.
L. Ronsko
t Works Director
JLR/eeh
APPROVED
iZY A. VES• City Manager _._
FILE NO.