HomeMy WebLinkAboutAgenda Report - March 6, 2013 C-14AGENDA ITEM C'014
CITY OF LODI
9^`COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Contract for
'DeBenedetti Park Maintenance Yard Enclosure with Soracco & Sons, of Sutter
Creek ($188,091.11) and Appropriating Funds ($210,000)
MEETING DATE:
PREPARED BY:
March 6, 2013
Public Works Director
RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute contract for
DeBenedetti Park Maintenance Yard Enclosure with Soracco &
Sons, of Sutter Creek, in the amount of $188,091.11, and
appropriating funds in the amount of $210,000.
BACKGROUND INFORMATION: The master plan for DeBenedetti Park includes a maintenance yard
consisting of park maintenance facilities, a storm drainage pump station
and a municipal well at the southwest corner of Century Boulevard
and Heavenly Way. The pump station and well projects have been completed by the Public Works Department.
The City has received several critical comments regarding the appearance of the Public Works facilities.
Requests have been received to advance the construction of the maintenance yard enclosure.
This project consists of constructing a 7 -foot high masonry wall surrounding the maintenance yard and
Public Works facilities, as called for in the original master plan. The layout of the planned enclosure is
presented in Exhibit A. An objective of the project is to screen the existing pump station and well from
public view. The tall mechanical trash -handling facility at the pump station will be partially screened from
view, as represented in Exhibit B. The enclosure will look similar to the existing reverse frontage wall and
landscaping located on the southeasterly corner of the Century Boulevard and Heavenly Way intersection.
Plans and specifications for this project were approved on October 3, 2012.
The City received the
following 12 bids for this project on February
6, 2013.
Bidder
Location
Bid
Engineer's Estimate
$
188,652.00
Soracco & Sons
Sutter Creek
$
188,091.11
A. M. Stephens Construction
Lodi
$
209,618.50
B & M. Builders, Inc.
Rancho Cordova
$
225,528.50
Wickman Development
San Francisco
$
230,995.75
G Seven
Sonora
$
244,467.50
A -VET Construction
Woodbridge
$
252,356.50
Bobo Construction
Elk Grove
$
256,110.00
Mark Wallace Masonry
Auburn
$
273,759.11
BC Construction
Ceres
$
273,878.83
All-American Construction
Yuba City
$
285,365.44
Younger General Contractors
Rancho Cordova
$
338,450.00
David Smith Masonry
New Castle
$
471,687.90
APPROVED: : X It
Konradt Bartlam, City Manager
K:\W P\PROJECTS\PARKS\DeBenedetti(G-Basin)\MasonryWall\CAward.doc
2/20/2013
Adopt Resolution Authorizing City Manager to Execute Contract for DeBenedetti Park Maintenance Yard
Enclosure with Soracco & Sons, of Sutter Creek ($188,091.11) and Appropriating Funds ($210,000)
March 6, 2013
Page 2
FISCAL IMPACT: Staff anticipates maintenance costs for the masonry wall to be minimal.
FUNDING AVAILABLE: Requested Appropriation:
Storm Impact Mitigation Fees (175043): $84,000
Water Capital (181043): $84,000
Parks Capital (1212043): $42,000
Jordan yers
Deputy City Manager/Intern I Services Director
F. Wally ndelin
Public Works Director
Prepared by Charles E. Swimley, Jr., Deputy Public Works Director/City Engineer
Attachments
cc: Parks Superintendent
K:\WP\PROJECTS\PARKS\DeBenedetti(G-Basin)\MasonryWall\CAward.doc 2/20/2013
�f
CITY OF LOD]PUBLIC .. DEPARTMENT
M�7-
Exhibit A.
DeBenedetti Park
Masonry Mall Enclosure
0
Q
0
Cn
w
U
U
Q
w
CENTURY BOULEVARD
-----------------
----- -- - ❑���\
❑1
D ❑ ❑ I II I �
I III
❑\ I V I �
I III �
Q
I III =
I II I
I II I
EXISTING FENCE I III
TO REMAIN I III
II I
I ill
7—FOOT MASONRY WALL I�
SUGAF
SII i �❑
'� 111 111 1
111 I I
1111 111 / l
i /o
Exhibit B
Debenedetti Park
Masonry Wall Enclosure
DEBENEDETTI MASONRY WALL ENCLOSURE
2360 West Century Boulevard CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and , herein referred to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 2006 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
DeBenedettiwallenclosure4.doc 1 02/13/13
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of constructing a seven -foot eight -inch (7' 8") high masonry wall surrounding
the maintenance yard and Public Works facilities, including site grading and aggregate base
material and other incidental and related work, all as shown on the plans and specifications for
the "DeBenedetti Masonry Wall Enclosure, 2360 West Century Boulevard".
CONTRACT ITEMS
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
1.
Clearing and Grubbing
EA
1
$
4,800.00
$
4,800.00
2.
Water Pollution Control
ACRE
1.5
$
1,666.67
$
2,500.01
3.
Install Masonry Wall
LF
760
$
171.05
$ 129,998.00
4.
Fence Removal
LF
910
$
3.51
$
3,194.10
5.
Install Chain Link Fence
LF
105
$
59.04
$
6,199.20
6.
Install Double Swing Gate
EA
1
$
5,400.00
$
5,400.00
7.
Install Single Swing Gate
EA
1
$
2,900.00
$
2,900.00
8.
Install Man Gate
EA
1
$
1,000.00
$
1,000.00
9.
Place Crushed Rock
CY
95
$
96.84
$
9,199.80
10.
Miscellaneous Work
LS
1
$
22,900.00
$
22,900.00
TOTAL BID
$ 188,091.11
DeBenedettiwallenclosure4.doc
2
02/13/13
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 60 CALENDAR DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
Title
By:
Konradt Bartlam
City Manager
Date:
Attest
City Clerk
(CORPORATE SEAL) Approved As To Form
D. Stephen Schwabau_ er
City Attorney
DeBenedettiwallenclosure4.doc 3 02/13/13
1. AA#
2. JV#
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
FUND #
BUS. UNIT #
ACCOUNT #
ACCOUNT TITLE
AMOUNT
A.
SOURCE OF
FINANCING
175
3205
(Fund Batance
$ 84 000.00
181 3205 (Fund Balance
84 000.00
1212 3205 (Fund Balance
42 000.00
B.
USE OF
FINANCING
175
175043
1825.2300
IDeBenedetti Park Enclosure
$ 84 000.00
181 181043 1825.2300 IDeBenedetti Park Enclosure
1 84 000.00
1212 1212043 1825.2300 IDeBenedetti Park Enclosure
42 000.00
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2013-28
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACT
FOR DEBENEDETTI PARK MAINTENANCE YARD ENCLOSURE,
2360 WEST CENTURY BOULEVARD, AND FURTHER
APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of this City
Council, sealed bids were received and publicly opened on February 6, 2013, at 11:00 a.m., for the
DeBenedetti Park Maintenance Yard Enclosure, 2360 West Century Boulevard, described in the plans
and specifications therefore approved by the City Council on October 3, 2012; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with the City
Manager as follows:
Bidder Bid
Soracco & Sons
$
188,091.11
A. M. Stephens Construction
$
209,618.50
B & M. Builders, Inc.
$
225,528.50
Wickman Development
$
230,995.75
G Seven
$
244,467.50
A -VET Construction
$
252,356.50
Bobo Construction
$
256,110.00
Mark Wallace Masonry
$
273,759.11
BC Construction
$
273,878.83
All-American Construction
$
285,365.44
Younger General Contractors
$
338,450.00
David Smith Masonry
$
471,687.90
WHEREAS, staff recommends awarding the contract for the DeBenedetti Park Maintenance Yard
Enclosure, 2360 West Century Boulevard, to the low bidder, Soracco & Sons, of Sutter Creek, California,
in the amount of $188,091.11.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the
contract for the DeBenedetti Park Maintenance Yard Enclosure, 2360 West Century Boulevard, to the low
bidder, Soracco & Sons, of Sutter Creek, California, in the amount of $188,091.11; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the contract;
and
BE IT FURTHER RESOLVED that funds in the amount of $210,000 be appropriated for this
project from Storm Impact Mitigation Fees, Water Capital, and Parks Capital.
Dated: March 6, 2013
I hereby certify that Resolution No. 2013-28 was passed and adopted by the City Council of the
City of Lodi in a regular meeting held March 6, 2013, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, Mounce, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
NHL
City Clerk
2013-28