HomeMy WebLinkAboutAgenda Report - March 6, 2013 C-12AGENDA ITEM C 401L
CITY OF LODI
COUNCIL COMMUNICATION
• TM
AGENDA TITLE: Accept Improvements Under Contract for Surface Water Treatment Facility Project
MEETING DATE:
PREPARED BY:
March 6, 2013
Public Works Director
RECOMMENDED ACTION: Accept improvements under contract for Surface Water Treatment
Facility project.
BACKGROUND INFORMATION: The contract was awarded to C. Overaa & Company, of Richmond,
on October 20, 2010, in the amount of $22,837,000. The contract
has been completed in substantial conformance with the plans and
specifications approved by City Council.
This project consisted of the construction of a raw water pump station in Woodbridge; approximately 500
feet of 30 -inch raw water transmission pipe, an operations building, chemical building, sedimentation
structure, 3 -million -gallon treated water storage tank, and treated water high service pump station at the
treatment facility's 4.2 -acre site adjacent to Lodi Lake; approximately 4,000 feet of 36 -inch treated water
transmission pipe and installation of chlorine and chemical injection systems at approximately 25 well
sites throughout the City; traffic signals and intersection work at Mills Avenue and Turner Road; and all
other site and utility improvements associated with the project.
The contract completion date was March 1, 2013. The final contract price was $25,515,343. The
difference between the contract amount and the final contract price is due to 15 change orders. A copy
of each of the executed change order forms is attached for reference. Complete supporting documents
are on file at the Public Works Department. Total change orders were $2,678,343 or 12% of the original
contract.
The project was substantially completed on November 1, 2012 and received the permit to operate from
the Regional Water Quality Control Board on November 26, 2012.
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of
Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors
that the project is complete and begins their 30 -day period to file a stop notice requiring the City to
withhold payments from the prime contractor in the event of a payment dispute.
FISCAL IMPACT: Increase in costs for operating the facilities will be approximately $1.7 million
the first year and approximately $1.4 million each year thereafter.
FUNDING AVAILABLE: This project was funded by the Water Fund (181011).
_4L
F. Wally SlAndelin
Public Works Director
Prepared by Gary Wiman, Construction Project Manager
FWS/GW/prof
Attachments
cc: Deputy Public Works Director —Utilities
APPROVED:
Bartlam, City Manager
K:\WP\PROJECTS\WATER\SurfaceWaterPlant\SWTF Project\CAccept SWTF.doc
2/20/2013
./CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C.O. NO: 1
PCO NO: 1
CONTRACTOR: C. Overaa & Co. RFI NO: 66
ARCHITECT/ENGINEER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
1. Due to the wetter than normal weather the site soil conditions required additional work as per the Project Design
Geotechnical Report provided by Youndahl Consulting Group, Inc., and confirmed by the Project Construction
Geotechnical Engineer (Krazan & Associates). To remedy the conditions an additional 8 days of grading activity
was required. (AM Stephens RFCO 1) $53,330.00
2. One additional sycamore tree had to be removed due to its proximity to the new entry road. (AM Stephens
RFCO 2) $1,610.00
3. Imported soil from the City Grape Bowl Facility and associated fence repair work. (AM Stephens RFCO 3 & 6)
$24,540.00
Total of items 1— 3 above = $79,480.00
General Contractor's Mark-up (51/o) = $3,974.00
Subtotal = $83,454.00
Bonds & Insurance (2%) = $1,669.08
Total Change Order = $85,123.08
Request, Pro oW, Recommendation And Approval
Requesting Official: Wally Sandelin Date of Request: 4/14/11 Schedule Impact -0—Days
Contractor Proposal Date: 4/27/11 Add Amount: $ 85,123.00 Deduct Amount: N/A
Reason For Change: Unknown Condition/Owner Requested Account 181011.1825.2300
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SMLAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
� rA
ORIGINAL CONTRACT $22,837,000.00
Contractor ell, Date
PREVIOUS ADDS $0
PREVIOUS DEDUCTS $0
on MDate
THIS CHANGE $85,123.00
3, r
CONTRACT TO DATE $22,922,123.00
Public Works Date
CONTRACT THAE ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City Manager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
S WTF PCO 1 5/26/2011
ITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Surface Water Treatment Facility i C.O. NO: 2
CONTRACTOR: C. Overaa & Co.
ARCHITECU/ENGINEER: HDR
PCO NO: 2
RFI NO:
FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This change order is for work related to the Railroad crossings. The Railroad notified the City on June 2, 2011 that they
would be closing Turner Road near Mills Ave to perform track crossing work beginning on Monday June 6, 2011.
Because this is the only access available to the project site, the contractor coordinated the road closures with the
railroad to maintain access to the SWTF site. Due to this required coordination, the City requested that the contractor
be responsible for all activities related to the railroad work that the City would typically perform. This work included:
traffic control, saw cutting of the asphalt and concrete, off -haul of the removed asphalt and concrete and repaving the
roadways impacted by the railroad work.
All work was documented and tracked on a Time and Materials basis. The work was completed on June 20, 2011.
The total cost of this work is $58,968.00
Request, Pry sal, Recommendation And A roval
Requesting Official: Gary Wiman Date of Request: 6/6/11 Schedule Impact 0 Days
Contractor Proposal Date: 6/22/11 Add Amount: $58,968.00 Deduct Amount:
Reason For Change: Owner Requested Account 181011.1825.2300
Requested By: PW Department
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
G
ORIGINAL CONTRACT $22,837,000.00
Contracto Date
PREVIOUS ADDS $85,123.00
Z
PREVIOUS DEDUCTS $0
consftuwod Date
THIS CHANGE $58,968.00
7/6/1'
CONTRACT TO DATE $22,981,091.00
Public Wor Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City_Wairildger Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
SWTF PCO 2
6/22/2011
�fri�f
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C.O. NO: 3
PCO NO: 3
CONTRACTOR: C OPeraa & CO. RFI NO: 93.. 3002 48, .20,. 2004; 2005
A.RCFIITECUENGINEER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change Order Includes:
1. An additional 42 feet of 48" boring is required for the 36" transmission main to miss an AT&T duct bank. (RFI
93, Overaa COR #6) $24,796.00
2. The design engineer requested an additional 67 feet of restrained transmission main joints. (RFI 3002, Overaa
COR 7) $9,922.00
3. The City requests the entire Mills Ave roadway from Elm Street to Turner Road be replaced due to the impact
of the trenching related activities. (RFI 48, Overaa COR 8) $177,036.00
4. During demolition of the berm for the new access road, several unknown concrete structures were discovered
and had to be demolished. (RFI 2004, Overaa COR 9) $15,915.00
5. The City Water Dept. requested the contractor to purchase and delivered water pipe materials originally called
out to be provided by the City. The actual material costs are the same pricing as the City would have received.
(RFI 2005, Overaa COR 10) $43,786.00
rhe total of items 1 -5 above is $271,455.00
Request, Fra sad,. Recommendation And A roval
Requesting Official: PW Dept Date of Request: 6/2/11 Schedule Impact 0 -Days
Contractor Proposal Date: 6/29/11 Add Amount: $271,455.00 Deduct Amount: N/A
Reason For Change: Owner Requested, Change Condition, Plan Clarification Account 181011.1825.2300
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
9
7�c1�j
ORIGINAL CONTRACT $22,837,000.00
Contrado Date
PREVIOUS ADDS $144,091.00
PREVIOUS DEDUCTS $0
onshuCtion. rDaW
THIS CHANGE $271,455.00
CONTRACT TO DATE $23,252,546.00
public (ODate
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
5�-�
COMPLETION DATE: December 31, 2012
CityDate
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
SWTF PCO 3
7/6/2011
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
C_ .A & C�.
PROJECT. Surface Water Treatment Facility C. 0. NO: 4
PCO NO: 4
CONTRACTOR: C. Overaa & Co. RFI NO: 2006, 2008 and 2010
ARCHITECT/ENGINEER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change Order includes multiple items related to Mills Ave, the 36" Treated Water line conflicts with unknown
existing utilities, necessary associated utility upgrades/replacements and additional curb, gutter and sidewalk
replacement and ADA driveway and corner ramps requested by the City. Due to the time constraints for the work on
Mills Avenue the majority of this work was performed on a time and materials basis with all work and hours verified by
City Staff. (Overaa COR 14)
Total = $215,979.00
Request, Pro sal.. Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: 6/2/11 Schedule Impact 0 -Days
Contractor Proposal Date: 8/25/11 Add Amount: $215,979.00 Deduct Amount:
Reason For Change: Owner Requested/Unknown Conditions Account 181011.1825.2300
Requested By: Public Works Department
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
RVIPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
% //t
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $415,546.00
PREVIOUS DEDUCTS $0
100nstrucd0fM=
THIS CHANGE $215,979.00
CONTRACT TO DATE $23,468,525.00
Public Work,91 Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City Manager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
SWTF PCO 4 8/31/2011
CITY OF LODI C. OVERAA &CCI;
SEP 01 2011
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Surface Water Treatment Facility
CONTRACTOR: C. Overaa & Co.
ARCMTECT/ENGINEER: HDR
Brief Description Of Work
This Change Order includes:
C. 0. NO: 5
PCO NO: 6
RFI NO: 2009A, 3000, 3001
FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
1. Change the Electrical Service from 4,000 amps to 2,000 amps per Lodi Electric Utility. RFI 2009A (Overaa
COR 15) $20,632.00 CREDIT
2. The waste lift station and associated sewer lines need to be relocated to a minimum of 50 feet away from the
water storage tank as required by the California Department of Public Health. RFI 3000 (Overaa COR 12)
$26,158.00
3. Coordination with Pall Corporation regarding final design and layout of the membrane filtration system.
Original bid documents were designed based on preliminary Pall documents. Final documents require alteration
of copper piping and control items. RFI 3001 (Overaa COR 13) $47,766.00
Total of items 1— 3 above = $53,292.00
Re ues% Proposal, Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: 7/19/11 Schedule Impact-0—Days
Contractor Proposal Date: 8/17/11 Add Amount: $53,292.00 Deduct Amount:.
Reason For Change: Plan Clarification Account 181011.1825.2250
Requested By: Public Works/EUD
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
s c
f
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $631,525.00
PREVIOUS DEDUCTS $0
Cowtm on M Date
THIS CHANGE $53,292.00
-F/ (.111
aLL
CONTRACT TO DATE $23,521,817.00
Public Works Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
[!ffanager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
SWTF PCO 6 8/31/2011
CITY OF LODI
W
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility
CONTRACTOR: C. Overaa & Co.
ARCMTECT/ENGINEER: HDR
C. 0. NO: 6
PCO NO: 5
RFI NO: 7,. 2003 A, B & C
FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change order includes:
1. Value Engineering Changes to eliminate the precast concrete lintels, wainscot and wall caps at the Operations
Building, High Service Pump Station and Chemical Building; and replace them with CMU headers.
Eliminating the 4" CMU veneer wainscot and reducing the size of the concrete wainscot. (Overaa COR 17)
$88,359.00 CREDIT
2. Eliminating 6 interior bollards is also included. (Overaa COR 16) $4,800.00 CREDIT
Total of items 1 & 2 above = $93,159.00 CREDIT
Request, Proposal, Recommendation And A roval
Requesting Official: Gary Wiman Date of Request: 515/11 Schedule Impact _0 Days
Contractor Proposal Date: 9/15/11 Add Amount: $ 0 Deduct Amount: $93,159.00
Reason For Change: Value Engineering Account 181011.1825.2300
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $684,817.00
PREVIOUS DEDUCTS $0
bnstruetson mimmi7ea Date
THIS CHANGE $93,159.00 CREDIT
4 / 2 - ��
CONTRACT TO DATE $23,428,658.00
Public Works Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City anager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
SWTF PCO 5 9/19/2011
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C. 0. NO: 7
PCO NO: 7
CONTRACTOR: C. Overaa & Co. RFI NO: $9, 101, 102, 103A, 2012
ARCBTrECT/ENGIlVEER: HDR FI NO:
Brief Description Of Work
This Change Order includes:
1. Paint Traffic Signal Control Panel Dunes Tan. (Overaa COR 4) $812.00
2. Add Floor Drain for Emergency Eye wash at Chemical Building per RFI 102. (Overaa COR 11) $3,357.00
3. Remove two additional Sycamore trees near new entry road as requested by the Parks Dept. (Overaa COR 18)
$1,601.00.
4. Change Water Storage Tank access ladder rung and mounting materials per RFI 101 to meet code requirements.
(Overaa COR 19) $5,537.00
5. Provide grating at interior Water Storage Tank openings per RFI 89. (Overaa COR 20) $6,367.00
6. Add code required trap primers at all floor drains per RFI 103A. A total of 78 trap primers are added. (Overaa
COR 21) $92,549.00
7. A conflict was discovered between the new 36" treated water pipe line and an existing 54" storm drain line and
an existing 8" water line. The 36" pipe was routed under the 54" and the 8" water was relocated out of the way
per RFI 109. (Overaa COR 22) $78,054.00
8. The contractor substituted ductile iron pipe fitting types which provided a credit to the City. (Overaa COR 23)
$9,973.00 CREDIT
9. A 36" butterfly valve was deleted near the treated water storage tank per RFI 118 creating a credit. (Overaa
COR 24) $3,410.00 CREDIT
10. The Public Works Dept requested the demolition of the block wall around a power pole on Turner Road near
the new entry road. (Overaa COR 25) $3,722.00
Che total of items 1 — 10 above is $178,616.00
Request Proposal, Recommendation And A ploy
Requesting Official: Gary Wiman Date of Request: 7/8/11 Schedule Impact 0 Days
Contractor Proposal Date:10/11/11 Add Amount: $191,999.00 Deduct Amount:$13,383.00 Net Change:$178,616.00
Reason For Change: Plan Clarification/Owner Requested Account 181011.1825.2250
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
%p 05 1
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $684,817.00
PREVIOUS DEDUCTS $93,159.00
o.nstru pn M
THIS CHANGE $178,616.00
6/2,-( ( 1 1
CONTRACT TO DATE $23,607,274.00
Public Worksd Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
Ci Manager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
PTF PCO 7 10/19/2011
CITY OF LODI
PROPOSED CHANGE ;ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C.O. NO: 8
CONTRACTOR: C. Overaa & Co.
ARCMTECT/ENGINEER: HDR
PCO NO: 8
RFI NO: 2015, 137, 3x74, 150, 17, 130A, 145, 149, 139, 150A
FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change Order includes:
1. Addition of stamped colored concrete at the Mills/Turner medians per RFI 2015. (Overaa COR 26) $12,715.00
2. Replacement of 21 water valve lids on Mills Ave, including raise to grade and patch paving, and additional
patch paving for water lines installed by City crews on Mills Ave side streets. (Overaa COR 27) $41,001.00
3. Add bell -up floor drain for 3/4" BFP at High Service Pump Station per RFI 137. (Overaa COR 28) $1,398.00
4. Additional Structural Steel Beams above openings at Ops Building line K per RFI 3004. (Overaa COR 29)
$10,206.00
5. Revised Ops Building top of CMU flat wall Embed plates per RFI 150. (Overaa COR 30) $22,871.00
6. Add code required roof access at the High Service Pump Station per RFI 17. (Overaa COR 31) $8,401.00
7. Revised Ops Building low roof embed plates at line K per RFI 130A. (Overaa COR 32) $4,954.00
8. Revised Ops Building structural steel for sloped roof elevation per RFI 145 & 149. (Overaa COR 33) $9,168.00
9. Additional waterstop at Chem Building containment wall per RFI 139. (Overaa COR 34) $802.00
10. Additional traffic signal work at Mills Ave/Turner Road as per Traffic Engineer. (Overaa COR 35) $5,204.00
11. Reimburse City staff time and materials for Mills Ave water valves damaged by contractor. (Overaa COR 37)
$7,416.00 CREDIT
12. Revised Ops Building top of raked wall embed plates per RFI 150A. (Overaa COR 38) $56,434.00
The total of the twelve (12) items above is $165,738.00
geguest, Proposal, Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: 10/19/11 Schedule Impact -0 -Days
Contractor Proposal Date: 12/14/11 Add Amount: $165,738.00 Deduct Amount:
Reason For Change: Plan Clarification, Owner Requested Account 181011.1825.2250
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
/
ORIGINAL CONTRACT $22,837,000.00
Contractor D afe
PREVIOUS ADDS $863,433.00
PREVIOUS DEDUCTS $93,159.00
C -ns am LW Date
THIS CHANGE $165,738.00
f l q 1 Z
CONTRACT TO DATE $23,773,012.00
Publl Wor Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
Ci an Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
SWTF PCO 8 12/21/2011
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C.O. NO: 9
PCO NO: 9
CONTRACTOR: C. Overaa & Co. RFI NO: 110, 144A, 155, 162, 172, 173, 2003, 2013, 2018, 2020
and Submittal 250
ARCHITECT/ENGINEER: HDR FI NO:
Submit al Within 15 PED iT n RED : t of This Lepest
Brief Desmirdion Of Work
Oversa
COR
RFI
Description
Responsibility
Amount
39
162
Block Veneer Support at openings
Design detail
$
2,181.00
40
2003
Metal Stud Additional Engineering costs
Owner Requested - VE related cost
$
5,577.00
41
2013
Revise two door frames at Ops Bldg due to conflict with
Structural items
Design conflict
$
2,638.00
42
172,173
Add time clock for Exterior lighting at Sed Basin & Plate
Settler area
Owner requested
$
1.060-00
43
Sub 250
Deleted Cathodic Protection at Reverse Filtration Waste Tank
Eng. Value Engineering CREDIT
$
(4,675.09)
44
TW Storage Tank Coatin&
Owner Requested to protect tank from
vandalism & ease of maintenance
$
33 549.00
46
110
Add stud furring at Ops Bldg CMU walls for Pipe chase needs
Design conflict
$
2,529.00
47
155
CMU embeds at Chem Building
Design detail
$
66 492.00
48
144A
. Add Floor tile in staff bathrooms and locker rooms
Owner Requested
$
13 599.00
49
1
additional Electrical bores
EUD Requested
$
31,115.00
50
2009B
Delete Electrical Bore
Owner R uested VE CREDIT
$
22,500.00
51
Delete Loading Doc
Owner Requested VE CREDIT
$
11 000.00)
52
2018
Add Safety Access Bar at TW Storage Tank Entrance
Owner Requested
$
1 699.00
53
2020
Provide 24 Well Site Flow Meters
Owner Requested
$
71 701.00
Requat PrepoSal, Recommendation And Approval
Total
$
193 65.00
Requesting Official: Gary Wiman Date of Request: 12/3/11 Schedule Impact 0
Contractor Proposal Date: 12/14/11 Add Amount: $193,965.00 Deduct Amount:
Reason For Change: Owner Requested/Plan Clarification Account 181011.1825.2250 - $162,850.OQ
Days
-$31,115.00
Requested By: PW Water Dept, EUD, PW Engineering Account b/r
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH TILE
REQUIREMENTS FOR SIMILAR WORK COVERED BY THE CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR THE
AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER IMPACT COSTS, NO WORK WILL BE STARTED UNTIL THIS PROPOSAL
IS ACCEPTED.
r
ORIGINAL CONTRACT $22,837,000.00
Contractor ADM
PREVIOUS ADDS $1,029,171.00
PREVIOUS DEDUCTS $93,159.00
constuchowNfim9er Date
31t lel !-r—
THIS CHANGE $193,965.00
CONTRACT TO DATE $23,966,977.00
Public WorksO Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City Manager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
SWTF PCO 9
3/6/2012
J4
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Surface Water Treatment Facility C. 0. NO: 10
PCO NO: 10
CONTRACTOR: C. Overaa & Co. RFI NO: 171A, 205, 208, 218, 22, 2013
ARCHITECT/ENGINEER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change includes:
1. Value Engineering change at the Raw Water Pump Station Accoustic Wall insulation. (Overaa COR 36) $7,000.
CREDIT
2. Reduced size for the ACH tanks. (Overaa COR 54) $1,348. CREDIT
3. Additional Tile Wainscot at bathrooms. (Overaa COR 57) $1,850.
4. Add Top of wall flashing and replace metal faux beam end with box beam end. (Overaa COR 58) $29,169.
5. Lower ceiling height in bath/locker rooms 114, 115, 116 and 117. (Overaa COR 60) $825.
6. Add furring strips at CMU walls for siding support. (Overaa COR 61) $1,957.
7. Air district requires low emission water heaters. (Overaa COR 62) $7,853.
8. Additional detailing costs related to HVAC reroute over walls. (Overaa COR 63) $755.
9. Revised doors 132D and 134. (Overaa COR 64) $1,440.
10. Upgrade to City wide Security Access System software and Hardware due to addition of SWTF project. (Overact
COR 65) $22,83" 0"-
11. Code required Fire Alarm Preaction Detection System. (Overaa COR 66) $14,955.
Che total of the above 11 items is: $72,843.
Request Plro osal, Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: 3/8/12 Schedule Impact 0 Days
Contractor Proposal Date: 5/3/12 Add Amount: $72,843.00 Deduct Amount:
Reason For Change: Value Engineering, Owner Requested, Changed Conditions Account 181011.1825.2250
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONIRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
1
ORIGINAL CONTRACT $22,837,000.00
2
Eon' Date
PREVIOUS ADDS $1,223,136.00
d
PREVIOUS DEDUCTS $93,159.00
Construction . aaag Date
THIS CHANGE $72,843.00
CONTRACT TO DATE $24,039,820.00
Public Works Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City anager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
SWTF PCO 10 5/30/2012
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Surface Water Treatment Facility
CONTRACTOR: C. Overaa & Co.
ARCHITECT/ENGINEER: HDR
Brief Description Of Work
C. 0. NO: 11
PCO NO: 11
RFI NO: 260, 2024, 274, 150 155, 280 25G 2032, 2031,
2034.. 2035. 171
Overaa
COR
RFI
Amount
Description
67
260
$1,164.00
Add code required fire damper at room 127 HVAC
68
PALL
$8,962.00
Costs related to Pall Equipment size than e
69
2024
$8,189.00
Change bathroom and breakroom Counters to solid surface
70
270
$4,843.00
Add single ply roof walk pads toequipment areas
71
150,155
$15,515.00
Coatin s for additional CMU wall embeds
72
280
$3,888.00
Revised Locker layout
73
298
-$776.00
Change to TPO roofing at HSPS and RWPS
75
FI
-$16,500.00
Chain Link and post & Cable fence credit
77
FI
$5,256.00
Purchase 6" water meter
78
256
$2,677.00
Add enclosure for AIT 6009
80
2032
$6,131.00
change to stained concrete at Ops Building areas not carpeted
81
FI
$28,137.00
Add chemical fill stations at 23 wells and well T&M work
82
FI
$47,135.00
Additional T&M and boring work related to Mills Ave
83
2031
$1,513.00
Add ceiling mounted occupancy sensors at bath & Locker Rooms
84
2034
$56,504.00
Add 6" Water Recirculation Pipe line on Site
85
2035
-$9,000.00
Delete wood trellis at Ops Building
86
171
$33,639.00
171 sheet metal Rafter tail boxes
The total of the above 17 items: $197,277.00
Request:Lro , Recommendation And AppmyaI
Requesting Official: Gary Wiman Date of Request: 6/1/12 Schedule Impact_0 Days
Contractor Proposal Date: 6/5/12 Add Amount: $197,277.00 Deduct Amount:
Reason For Change: Value Engineering, Owner Requested, Changed Conditions Account 181011.1825.2250
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
f
7/
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $1,295,979.00
h.i% t)
/
PREVIOUS DEDUCTS $93,159.00
Co .. Date
THIS CHANGE $197,277.00
CONTRACT TO DATE $24,237,097.00
Public W Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
Man er Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31 2012
SWTF PCO 11 7/30/2012
CITY OF LODI I
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C. 0. NO: 12
PCO NO: 12
CONTRACTOR: C. Overaa & Co. RFINO: 245, 272, 286, 2022, 292, 237, 291, 304, 2017,
12016,2026,2037,2038,2040
ARCHITECUENGINEER: HDR j FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
Overaa COR RFI
Amount
Description
88
$3,898.00
Additional Weeding and mowing as requested by PW
89
$4,049.00
Add Emergency Eye wash Flow switches at 6 locations on Site
90 245
$3,578.00
Relocate Sed Basin Stairs
91 272
$2,433.00
Add cold water line to ECU 2001
92
$12,716.00
Purchase 11 Well Site Pipe Spools requested by PW Staff
93
-$710.00
Credit for acce tin one 24" box tree and sixty 1 allon plants
94
$2,217.00
Additional Soil planting amendments based on Lab results
95 286
$5,210.00
Additional Costs associated with RWPS Building elevation discrepancies
96
$9,495.00
H dro seed park site area
97 2022
$8,200.00
Miscellaneous well site SCADA control changes at 23 well sites
98
$8,466.00
Add SCADA control of Storm Pump Stations 9, 14 and 16
99
$3,509.00
SCADA well master control programming changes requested by staff
100
$25,996.00
Add Well 4R to SCADA controls stem
101
$2,382.00
Convert single mode fiber cable from EUD to multimode fiber on site
102
$28,716.00
Asphalt oil cost escalation per Caltrans Standards
103 292
$659.00
Cost of relocating a pit Level indicator switch
104
$2,215.00
Installation of spare conduits for future VFD & RTU needs
105
$2,759.00
Change Pull box PB3C lid to traffic rated steel lid
106
$17,189.00
Radio Survey 25 Well sites and Chanes to well site radio antennas
107 237
$40,602.00
Install 81 additional site bollards for building/equipment protection
108 291
$35,349.00
VOIP Phones stem including all hardware, phones and installation
109
$6,380.00
Procure and install exterior building light fixtures
110
$1,474.00
Addition of code required fire alarms stem items per permit
111
$18,910.00
Additional electrical work at 23 Well Sites
112
-$5,667.00
Credit for Site changes
113
$5,804.00
Change main water meter vault and lid to traffic rated
114 304&2037
$10,676.00
Add instrument airs stem & ARVs to Pall Autos trainers
115
$9,319.00
Add Air dryer and filter to soda ash silo dust collector
116 2017
$6,185.00
Relocation of Sed Basin analyzer and control panels
118 2016
$15,090.00
Hardware changes to Security Access system requested t staff
119 2026
$6,953.00
SCADA wiring to work stations
120
$1,232.00
Add concrete sidewalk from HSPS to man gate at visitor pafking area
121 2038
$6,635.00
Add Ornamental Iron Fence at Waste lift Station
122
$739.00
Additional wording at Facility sign
123 2040
$2,899.00
1 Add pump at membrane room pipe pit sum
$305,557.00
1 of 2
Supporting documentation is attached.
h2quesProposal, Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: Schedule Impact -0 -Days
Contractor Proposal Date: Add Amount: $305,557.00 Deduct Amount:
Reason For Change: Changed Conditions, Owner Requested Account 181011.1825.2250
Requested By: City Staff
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
`1
?,Vj t ; 0 4
/0 9'
ORIGINAL CONTRACT $22,837,000.00
Contractor
PREVIOUS ADDS $1,493,256.00
!
PREVIOUS DEDUCTS $93,159.00
on Date
Ct C%
THIS CHANGE $305,557.00
.. &14
CONTRACT TO DATE $24,542,654.00
Public Wedod Date
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
CityManager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
2 of 2
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility
CONTRACTOR: C. Overaa & Co.
ARCMTECT/ENGMER: HDR
Brief Description Of Work
C. 0. NO: 13
PCO NO: 13
RFINO: 2039,2042, 279,98,222, 301,3001, 311,312,2041,
287A,2043, 250,2000,244, 309 175,297,. 2044
FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Overaa
COR
RFI
Amount
Description
56
$9,841.00
Concrete slab and pipe rack installation at MSC Yard
124
$10,503.00
Add 10" OIP Screen at Well 411 control Panel
125
2039
$2,103.00
Add Camera at Lobby
126
$10,371.00
Well 411 Chemical Treatment facilities
127
2042
$2,264.00
Add Sample ports at analyzer panels
128
$1,798.00
Change Level transducer at Treated Water Storage Tank
129
279
$2,420.00
Relocate Pall System CIP Tank Heaters to meet code
130
98
$4,163.00
Add Pipe supports at 8" RFS overflow
131
222
$4,118.00
Relocation of the Soda Ash Silo
132
301
$15,950.00
Sodium Hypochlorite tank size increase, reroute electrical and piping
133
$2,561.00
Sedimentation basin MOV shaft extensions
134
$7,350.00
Add anti -siphon valves at 24 well sites
135
$0.00
Not Accepted by Owner
136
3001B&
C
$30,057.00
Change Chemical tote containment system
137
311 &
312
$7,281.00
Drainage and track at main slide gate
138
$4,155.00
Add domestic back flow preventers at sodium hypo & Soda ash
systems
139
2041
$1,386.00
Add light fixture to hypo generation room
140
$4,385.00
Add exterior light fixtures & wiring to HSPS and Chemical Building
141
$18,218.00
Provide and install conduit label and Tagging system to entire facility
142
$29,861.00
Repair Lighting along Lodi Lake Bike Path for SWTF egress
143
$0.00
VOID - included in COR 142
144
287A
$4,833.00
Coat Chemical Metering Pump Supports
145
2043
$1,779.00
ADD CIP Valve to Pall System discharge line
146
$1,359.00
Add Sedimentation Sample Panel drain to sewer
147
$5,713.00
Add code required ladder -up extensions 6 ladder locations
148
$2,515.00
Glass washer glassware rack system
149
$17,992.00
Add Domestic water booster pump at Chemical Building
150
-$2,095.00
Credit for unused shop tool budget
151
-$617.00
Credit for voice system analog trunk module
152
$827.00
Add Water Tower 1/0
153
$4,787.00
Replace Finish Turbidity analyzer with Hach model for micro meter
1541
$3,508.00
Paint lintels and "windows" at RWPS
SWTF PCO 13 1/3/2013
155
Requesting Official: Gary Wiman Date of Request: 12/3/12 Schedule Impact -0 Days
156
Reason For Change: Owner Requested, Changed Conditions Account 181011.1825.2250
157
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
158
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
159
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
160
ORIGINAL CONTRACT $22,837,000.00
161
PREVIOUS ADDS $1,798,813.00
162
PREVIOUS DEDUCTS $93,159.00
163
THIS CHANGE $347,324.00
164
250
165
CONTRACT TIME ADJUSTMENT 0 DAYS
166
2000
167
244,
309
168
175
169
297
170
177
2044
TOTAL
$4,787.00
$15,771.00
$5,026.00
$13,557.00
$6,687.00
$11,851.00
$4,223.00
$4,517.00
$2,815.00
$12,852.00
$3,787.00
$20,943.00
$3,944.00
$20,070.00
$5,026.00
$2,082.00
$347,324.00
12" Flowmeter for well site as requested by City Water Dept Staff
Purchase 3 toughbook laptop computers for PW Electricians
Well 611 Remobilization
Room 133 Chemical Tote Fill lines and seismic anchora
Void - Not used
Add Post and Cable Fence along east side of entry road
Well 411 Trenching and Paving work for SCADA integration
Add SCADA Temperature inputs at Chem & HSPS Buildings
Provide 2 exterior light fixtures and HP Communication Switch
Sed Basin Handrail Modifications required for sludge pump mounts
RWPS Site Survey and SWTF Parcel Split
Added Fire Hydrant and 6" water service per Fire Dept Requirements
Infrastructure work associated with the Soda Ash Silo utility needs
Relocation of the Altitude Sensing Valve
Add Stl Pipe Supports at the Autostrainers, RF pumps & Recirc
Pumps
Well 19 Remobilization Costs
Add ADA path of travel markings as required by Building De
Request, Proposal, Recommendation And Approval
Requesting Official: Gary Wiman Date of Request: 12/3/12 Schedule Impact -0 Days
Contractor Proposal Date: 1/2/13 Add Amount: $347,324.00 Deduct Amount:
Reason For Change: Owner Requested, Changed Conditions Account 181011.1825.2250
Requested By: City Staff
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
y
low
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $1,798,813.00
PREVIOUS DEDUCTS $93,159.00
on
THIS CHANGE $347,324.00
7 t i
CONTRACT TO DATE $24,889,978.00
CONTRACT TIME ADJUSTMENT 0 DAYS
*P"ubD11i1WW0;rkfjDate
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
anager Date
ADJUSTED CONTRACT
COMPLETION DATE: December 31, 2012
SWTF PCO 13 1/3/2013
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Surface Water Treatment Facility C.O. NO: 14
PCO NO: 14
CONTRACTOR: C. Overaa & Co. RFI NO:
ARCHITECT/ENGMER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change Order includes all work associated with adding 9 wastewater and 20 storm water pump stations to the
SCADA control system at the Surface Water Treatment Facility. This work was authorized by City Council in
Resolution 2012-199. The work is to be performed as "Not to Exceed" $450,000 based on the attached estimates and
actual field conditions.
Ir
Request, Proposal, Recommendation And Approval
Requesting Official: Wally Sandelin Date of Request: 11/27/12 Schedule Impact-60—Days
Contractor Proposal Date: 12/10/12 Add Amount: $450,000 Deduct Amount:
Reason For Change: Owner Requested Account 181011.1825.2250
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
2 '
ORIGINAL CONTRACT $22,837,000.00
Contractor Date
PREVIOUS ADDS $2,146,137.00
PREVIOUS DEDUCTS $93,159.00
Cans on
THIS CHANGE $450,000.00
CONTRACT TO DATE $25,339,978.00
Public Date
CONTRACT TIME ADJUSTMENT 60 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: December 31, 2012
City Manager Date
ADJUSTED CONTRACT
COMPLETION DATE: March 1, 2013
SWTF PCO 14
2/4/2013
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT. Surface Water Treatment Facility C.O. NO: 15
PCO NO: 15
CONTRACTOR: C. Overaa & Co. RFI NO:
ARCIMECT/ENGMER: HDR FI NO:
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
This Change Order includes:
Overaa
COR RFI
Amount
Description
172
$94,695.00
RS Logix Software Licensing for 5 Licenses
176
$5,184.00
Additional Landscape Rock
178
$4,909.00
Add Boiler Control to BMS System
179
$8,870.00
Add Soda Ash water softener
180
$49,005.00
Fixed Network Collector Sites
181
$2,515.00
Additional Landscape Bark and Quick coupler
182
$608.00
Install Tamper Proof bolts at landscape Boxes
183
$1,862.00
Install Domestic Back-flow at boiler 2001
184
$7,717.00
Add post & Cable Fence along east side of entry road
Total 1 $175,365.00
E uest, Proposal, Recommendation And Approval
Requesting Official: Wally Sandelin Date of Request: 1/16/13 Schedule Impact -0 -Days
Contractor Proposal Date: 2/4/13 Add Amount: $175,365.00 Deduct Amount:
Reason For Change: Owner Requested Account 181011.1825.2250 $126,360.00
Requested By: Gary Wiman P '�C � �s17o� 2S' $ �� .� 2,7co
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY TEE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
r
ORIGINAL CONTRACT $22,837,000.00
or
f Ddw
PREVIOUS ADDS $2,596,137.00
z
PREVIOUS DEDUCTS $93,159.00
Mnsdactionn
Date
THIS CHANGE $175,365.00
/
2t 2 1 (;3
CONTRACT TO DATE $25,515,343.00
Public 0
Date
CONTRACT TIME ADJUSTMENT 0 DAYS
_
ORIGINAL CONTRACT
.
COMPLETION DATE: December 31, 2012
City mauger
Date
ADJUSTED CONTRACT
COMPLETION DATE: March 1, 2013
SWTF PCO 15 2/20/2013
RESOLUTION NO. 2012-199
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING CITY MANAGER TO EXECUTE CONTRACT
CHANGE ORDER WITH C. OVERAA & COMPANY FOR
STORM AND WASTE WATER PUMP STATION SCADA
INTEGRATION UNDER THE SURFACE WATER
TREATMENT FACILITY PROJECT CONTRACT
WHEREAS, the contract for the Surface Water Treatment Facility Project was
awarded to C. Overaa & Company on October 20,201 a, and
WHEREAS, as a part of the contract, all operating City well sites were integrated
into the Surface Water Treatment Facility (SWTF) Supervisory Control and Data
Acquisition (SCADA) system so they can be monitored and controlled at the SWTF
operations center; and
WHEREAS, the change order will upgrade the 9 City wastewater and 12 City
storm water pump station communication systems so they may be integrated into the
SWTF SCADA system for monitoring and control. Once this work is completed,
Public Works staff will be able to monitor and control all Public Works pump facilities
from the SWTF operations center.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute a contract change order with C. Overaa &
Company, of Richmond, California, for storm and waste water pump station SCADA
integration under the Surface Water Treatment Facility Project contract, in an amount
not to exceed $450,000.
Dated: December 19, 2012
I hereby certify that Resolution No. 2012-199 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held December 19, 2012, by the
following vote:
AYES: COUNCIL MEMBERS– Hansen, Johnson, Katzakian, Mounce, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS – None
ABSENT: COUNCIL MEMBERS – None
ABSTAIN: COUNCIL MEMBERS – None
f— �- —
RANDI JOHL
City Clerk
2012-199