HomeMy WebLinkAboutAgenda Report - February 6, 1985 (92)VARIQS PLANS AND Council approved the following plans and specifications and
SPECIFICATICNS authorized the advertising for bids thereon:
APPRXIO
WELL DRILLA ,
69ELL #21 , �;;��%;� , 1) Well Drilling, Lyell 21, 136 Lower Sacramento Road
2) Salas Park Playground Irprovements, Phase I, II, and III.
•'•+h/O l5
q '` xxGa
_
�.r
�
K
y A
_
4
�
'1
�' YTZB
Y
A
CITY OF LORI
PUBLIC WORKS DEPARTMENT
T0: City Council
FROM: City Manager
DATE: January 31, 1985
SUBJECT: Well Drilling, Well 21
136 Lower Sacramento Rd.
COUNCIL COMMUNICATION
Proiect Data
Approved in F.Y. Budget: 1985
Fund: Water Capital Outlay
Total Project Estimate
This Phase: $40,000.00 -
Bid Opening Date: February 27, 1985
RECOMMENDED ACTION: That the City Council approve the plans and specifications
for the above project and authorize advertisement for bids thereon.
BACKGROUND INFORMATION: This project involves the addition of a new water well
on Lower Sacramento Rd. This Master Plan addition is located north of Elm Street
on City owned property.
J.eck .L. Ron sko
Public Works Director
I,—
cc:
, cc: Assistant Finance Director
JLR/RCP/ns
cc: Fire Chief
APPROVED:
HENRY A. GLAVES, City Manager
FILE NO.
CITY OF LODI
PUBLIC WORKS DEPARTMENT
TO: City Council
FROM: City Manager
DATE: January 31, 1985
SUBJECT: Salas Park Playground
Improvements, Phase I, 11, b III
r
COUNCIL COMMUNICATION
Project Data
Approved in F.Y. Budget: 1984-85
Fund: Capital Outlay Reserve
Amount Budgeted: (Total) $107,000
Total Project Estimate: S 56,500
Phase 1 $32,700
Phase 11 6,6OG
Phase 111 17,200
Bid Opening Date: February 27, 1985
RECOMMENDED ACTION: That the City Council approve the plans and specifications
for the above project and authorize advertisement for bids thereon.
BACKGROUND INFORMATION: This project is a portion of the work required to com-
plete Salas Park. This project is funded through the Federal Land C Dater
Conservation Fund and expenditures will be reimbursed upon completion of project.
(50% matching funds)
Jdtk RL s ko
Pub orks Director
cc: Assistant Finance Director
Parks & Recreation Director
JLR/ML/eeh
Phase I Consists of constructing concrete walkways and miscellaneous
concrete work in the playground area.
Phase 11 Consists of constructing walkway lighting in the playground area.
Phase 111 Consists of furnishing park furniture and playground equipment.
APPROVED: FILE NO.
HENRY A. CLAVES, City Manager