HomeMy WebLinkAboutAgenda Report - January 19, 1983 (35)'40)�CITY COUNCIL MEETING
�p � JANUARY 19, 1983
ACCEPTANCE OF COUNCIL ACCEPTED THE IMPROVEMENTS IN "MAIN STREET STORM DRAIN,
"MAIN STREET ELM STREET TO LOCKEFORD STREET"AND DIRECTED THE PUBLIC WORKS
STORM DRAIN, DIRECTOR TO FILE A NOTICE OF COMPLETION WITH THE COUNTY
ELM STREET TO RECORDER'S OFFICE.
LOCKEFORD
STREET" The Contract was awarded to Wayne Fregien of Stockton on i
October 6, 1982 in the amount of $41,560.00 and has been
completed in substantial conformance with the plans and
specifications approved by the City Council. The final
contract price was $42,925.00.
i
17
"n 4It
I
t 4;yt
CITY OF LODI
PUBLIC WORKS DEPARTMENT
TO: City Council
FROM: City Manager
DATE: January 14, 1983
COUNCIL COMMUNICATION
SUBJECT: Acceptance of "Main Street Storm Drain, Elm Street to
Lockeford Street"
RECOMMENDED ACTION: That the City Council accept the improvements i.r
the above-mentioned project and direct the Public Works Director to file
a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Wayne Fregien of
Stockton on October 1982 in the amount of $41,560.00. The contract
has been completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was December 17, 1982 and the actual completion
date is January 14, 1983. The final contract price was $42,925.00.
The difference between the contract amount and the final contract price
Is due to the necessity to construct one additional manhole because of
a conflict with an existing owner's line, and some additional paving
outside the contract limits.
�� r
Ja L. Ronsko
Pub is Works Director
JCR:GER:dmw