HomeMy WebLinkAboutAgenda Report - January 19, 1983 (29)CLUFF AVENUE STORM DRAIN INDUSTRIAL WAY TO VICTOR ROAD City Manager Glaves presented the following bids which had bcen received for the Contract for"Cluff Avenue Storm Drain - Industrial Way to Victor Road": BIDDER Claude C. Wood R.N. Bertelsen Wm. G. McCullough Teichert Constr. Oak Grove Constr. Granite ConF tr. Swengel-Robbins H. M. Byars W. R. Thomason U. S. S. Engineers Est. SCHEDULE I II with at. Storm 8 St. Work $ 937,774.00 941,754.00 953,895.56 982,227.75 1,022,971.00 1,057,306.25 1,082,101.22 1,166,912.00 1,203,558.26 1,210,418.50 837,793.00 SCHEDULE III Sanitary S r $ 17,560.00 22,370.00 17,990.40 18,253.00 27,390.00 20,960.00 25,410.00 28,450.00 29,300.00 22,880.00 23,830.00 Public Works Director Ronsko reported that EDA approval is being sought and "we" anticipate no problems. "We" wish to award the contract as soon as possible to meet constru-'ion deadlines and request approval subject to EDA concurrence. It is also recommended that Schedule III, Cluff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, be awarded to C. C. Wood, Co., the low bidder. This portion of the project is not grant -eligible and was budgeted in the 1983 Capital Improvement Program. A reimbursement agreement will be prepared in order to repay the City as adjacen!: owners develop their property. The project was bid with additional schedules of work covering off-site improvements for the adjacent propert%, owners. "We" are in the process of working with the Dwoiers to see it they wish to install their improvements under our contract; thus approval to execute agreements andaward additional work is --quested at this time to expedite contract administration. Finally, additional funds are needed to complete the project. The total project cost is estimated as follows: $ 53,000 Engineering, Right-of-way, and administration to date 938,000 Construction contract 15,000 Construction engineering 21,000 Contingencies $1,021,000 Total -5- ,h T Continued January 19, 1983 The recommended funding is: b 560,000 EDA Grant 240,000 Master Drain Fund (budgeted for this project) 70,000 Master Drain Fund (budgeted for C -Basin development; this project would be deferred) 60,000 Master Drain Fund (excess budgeted for Cluff S. D. North of Victor Rd. 35,000 Master Dram Fund (1982/83 revenue, already received) 62,000 Transportation Development Act Fund (from Miscellaneous Widening account, to pay for that portion of the street work which is not usually paid by the $1,027,000 Master Drain Fund. The Master Drain Fund is charged for replacement of the existing street; under this project we are reinstalling a slightly wider and substantially heavier street. AWARD - CLNTRACT Following discussion, on motion of Council Member Pinkerton, FOR CLUFF AVENUE Olson second, Council adopted Resolution No. 83-5 awarding STORM DRAIN - the bid for Cluff Avenue Storm Drain - Industrial Way to INDUSTRIAL WAY Victor Road, Schedules I and II, Alternate B, to Claude C TO VICTOR ROAD Wood Co., the low bidder, in the amount of $937,774 and t e Cluff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, RES. NO. 83-5 Schedule III, in the amount of $17,560, all subject to EDA concurrence; 1. Council further authorized the City Manager and the City Clerk to execute agreements between the City and adjacent property owners for the construction of off-site improvements; 2. Authorized the award of additional schedules of work to C. C. Wood Co., as said agreements are executed; and 3. Appropriated $62,000 of Transportation Development Act Funds from the Miscellaneous Widening account for street work included in this project and reallocate $165,000 Oil Master Drain funds to complete the project. c1F�. CITY OF LODI PUBLIC WORKS DEPARTMENT COUNCIL COMMUNICATION TO: City Council FROM: City Manager DATE: January 13, 1983 SUBJECT: Contract for Cluff Avenue Storm Drain - Industrial Way to Victor Road RECOMMENDED ACTION: That the City Council (1) award the bid for Cluff Avenue Storm Drain - Industrial Way to Victor Road, Schedules 1 and 11, Alternate B, to Claude C. Wood Co., the low bidder, in the amount of $937,774 and the Cluff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, Schedule lli, in the amount of $17,560, all subject to EDA concurrence; (2) authorize the City Manager and the City Clerk to execute agreements between the City and adjacent property owners for the construction of off-site improvements; (3) authorize the award of addition- al schedules of work to C. C. Wood Co. as said agreements are executed; and (4) appropriate $62,000 of Transportation Development Act Funds from the Miscella- neous Widening account for street work included in this project and reallocate $165,000 of Master Drain funds to complete the project. BACKGROUND INFORMATION: Plans and specifications for this project were approved by the City Council on November 17, 1982. Bids were opened on Thursday, January 6; 1983, and the following 10 bids were received: BIDDER Sched. 1, Sched.11 Schedule 111 with Alternate B (Sanitary Sewer) (Storm E Street Work) Claude C. Wood $ 937.714.00 $ 17,560.00 ft. N. Bertelsen 941,754.00 22,370.00 Wm. G. McCullough 953,895.56 17,990.40 Teichert Construction 982,227.75 18,253.00 Cak Grove Construction 1,022,971.00 27,390.00 Granite Construction 1,057,306.25 20,960.00 Swengel-Robbins, Inc. 1,082,101.22 25,410.00 H. M. Byars 1,166,912.00 28,450.00 W. R. Thomason 1,203,558.26 29,300.00 D.S.S. 1,210,418.50 22,880.00 Engineers Estimate 837,743.00 23,830.00 A tabulation of the bids has also been attached. The Engineer's Estimate has been reviewed with the low bidder. Based on those discussions and a review of the other bids, it is felt the bids are reasonable. APPROVED: FILE NO. HENRY A. CLAVES, City Manager W Council Communication January 13, 1983 Page 2 W EDA approval is being sought and we anticipate no problems. We wish to award the contract as soon as possible to meet construction deadlines and request approval subject to EDA concurrence. It is also recommended that Schedule 111, duff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, be awarded to C. C. Wood Co., the low bidder. `iis portion of the project is not grant -eligible and was budgeted in the 1983 Capital Improvement Program. A reimbursement agreement will be prepared in order to repay the City as adjacent owners develop their property. The project was bid with additional schedules of work covering off-site improve- ments for the adjacent property owners. We are in the process of working with the owners to see if they wish to install their improvements under our contract; thus approval to execute agreements and award additional work is requested at this mime to expedite contract administration. Finally, additional funds are needed to complei�,. the project. The total project cost is estimated as follows: $ 53,000 Engineering, Right -of -Way, and administration to date 938,000 Construction contract 15,000 Construction engineering 21,000 Contingencies $1,027,000 Total The recommended funding is: $ 560,000 EDA Grant 240,000 Master Drain Fund (budgeted for this project) 70,000 Master Drain Fund (budgeted for C -Basin development; this project would be deferred) 60,000 Master Drain Fund (excess budgeted for Cluff S.D. north of Victor Road) 35,000 Master Drain Fund (1982/83 revenue, already received) 62,000 Transportation Development Act Fund (from Miscellaneous Widening account, to pay for that $1,027,000 portion of the street work which is not usually paid by the Master Drain Fund. The Master Drain Fund is charged for replacement of the existing street; under this project we are reinstalling a slightly wider and substantially heavier street) a c L. Ronsko ubl c Works Director - Attachment JLR/RCP/ns cc: Finance Director 0 0 RESOLUTION NO. 83-5 AWARD - CONTRACT FOR CLUFF AVENUE STORM DRAIN INDUSTRIAL WAY TO VICTOR ROAD WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened by the City Clerk of this City on January 6, 1983 at 11:00 a.m. for the contract for Cluff Avenue Storm Drain - Industrial Way to Victor Road as described in the specifications therefor approved by the City Council November 17, 1982; and WHEREAS, said bids have been compared, checked, and tabulated and a report thereof filed with the City Manager as shown on Exhibit attached hereto, marked Exhibit "A", and thereby made a part hereof. WHEREAS, the City Manager recommends that the award for the contract for Cluff Avenue Storm Drain - Industrial Way to Victor Road, Shcedules I and II, Alternate B in the amount of $937,774 and the Cluff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, Schedule III, in the amount of $17,560, be made to Claude C. Wood Company, subject to EDA concurrence. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LODI that award of contract for Cluff Avenue Storm Drain -- Industrial Way to Victor Road be and the same is hereby made to Claude C. Wood Company - Schedules I and II, Alternate B in the amount of $937,774, and Cluff Avenue Sanitary Sewer, Lodi Avenue to Pine Street, Schedule III, in the amount of $17,560, all subject to EDA concurrence. DATED: January 19, 1983 I hereby certify that Resolution No. 83-5 was passed and adopted by the City Council of the City of Lodi in a regular meeting held January 19, 1983 by the following vote: Ayes: Council Members - Olson, Pinkerton, Snider, and Reid (Mayos) Council Members - None Council Members - Murphy Alice M. Reimche City Clerk CLUFF A,ErlUE STORM DRAIN. Industrial Way to Vic•or Road Tabulation of bids received January 6. 198; SGIIED'JtE t ENGINEER'S ESTIMATE ITEM APPROXIMATE UNIT TOTAL h0. - QUANTITY DESCRIPTION PRICE PRICE 1, 81,300 SF Compact Original Ground S 0.12 S 9.756.00 7. 618 SF Concrete Subgrade Compaction 0.21 135.95 3• 51 LF Vertical Curb and Gutter 9.50 484.50 4. 204 SF Sidewalk 1.80 367.20 5. 44 LF Conrnercial Driveway 20.00 880.00 6. 8.450 SF Shoulder Paving 1.20 10.140.00 7. 2 EA Survey Monument 80.00 160.00 8. 4 EA Paddle Markers 80.00 320.00 9. 17 EA Adjust Water Valve/ Monument Frame to Grade 80.00 1,360.00 10.13 EA Adjust Manhole Frame to Grade 200.00 2.600.00 i1. 1.450 LF 60" Precast Storm Drain (North of Pump Station) 75.00 111,750.00 12. 960 LF 60" Precast Storm Drain (South of Pump Station) 100.00 96.000.00 13. LS 54" Storm Drain - CCT Crossing LS 25.000.00 14. 100 LF 54" Storm Drain (R.C.P. Cl. V at railroad) 86.00 8.600.00 15. 578 LF 54" Storm Drain (C.I.P.P. or R.C.P.) 76.00 43.928.00 16. 100 LF 48" Storm Drain (R.C.P. Cl. V at railroad) 72.00 7,200.00 17. 602 LF 48" Storm Drain (C.I.P.P. or R.C.P.) 63.00 37.926.00 18. 405 LF 48"Precast Storm Drain 97.00 39.285.00 19. 333 LF 42" Precast Storm Drain 74.00 24.642.00 20. 17 LF 15" Storm Drain 22.00 174.00 21. 203 LF 12" Storm Drain 18.00 3,654.00 22. LS Special Connection to Existing Storm Drain LS 7,000.00 23. 2 EA 48" Manhole 1,100.00 2.200.00 24. 5 EA 48" Saddle Manhole 1,000.00 5.000.00 25.' 8 EA Side inlet Catch Basin 500.00 4.000.00 26. _ 2 EA Drop Inlet Catch Basin 400.00 800.00 27. LS Excavation Safety LS 3.712.34 28. LS Pump Structure LS 90,000.00 29. LS Site Work - Civil is 64,000.00 30. 4 EA Duty Pump and Mntor 12.000.00 48.000.00 31. 2 EA Clean -Up Pump and Motor 12.000.00 24,000.00 32. LS Telemetering System LS 32.000.00 33. LS Motor Control Center LS 28.000.00 34. LS Site Work - Electrical LS 7.000.00 35. LS Wt.od Fence LS 225.00 TOTAL SCHEDULE i = 740,000.00 SCHEDULE 11 ALTERNATE A 1. 3.833 Cy Roadway Excavation (F) : 8,00 Z 13.415.50 2. 1,807 Ton Aggregate Base 12.00 18.070.00 3. 2.710 Ton Asphalt Concrete 33.00 70.460.00 TOTA'. ALTERNATE A Z 101.945.50 AL&ERHATE 4 1. 3.150 Cy Roadway Excavation (F) S 8.50 S 11,655.00 2. 3.313 Ton Asphalt Concrete 33.00 86.138.00 TOTAL ALTERNATE 8 s 97.793.00 TOTAL SCHEDULE I c SCHEDULE 11, ALT. A = 841,945.50 TOTAL SCHEDULE 1 t SCHEDULE Ii. ALT. B >: 837,793.00 (F) denotes Final Pay +Quantity CLAUDE C. HOOD CO. INC. 17EA Uri IT T NO. PRICE PRICE I. S 0.15 2. 1.00 3. 10.00 4. 2.00 5. 30.00 6. 0.50 7. 150.00 8. 50.00 9. 175.00 10. 400.00 11. 110.00 12. 130.00 13. 36,000.00 ib. 120.00 15. 44.00 16. 103.00 17. 42.00 18. 144.00 19. 110.00 20. 39.00 21. 30. CIO 72. 6,500.00 73. 1,400.00 74. 1,100.00 75. 550.00 26. 450.00 27. 5,500.00 28. 79.000.00 29. 19,000.00 p. I k,250.GOA 31. 11,000.006 32. 43,000:00 33. 18.000.00 34. 10,000.00 35. 700.00 TOTAL SCH. SCHEDULE 11 AL7ERNA7f A 8.00 2. 12.00 3. 33.00 TOTAL ALT. A ALTERNATE 8 8.50 2. 33.00 TOTAL ALT. TOTAL SCM. I AND SCM. Ii. ALT. A TOTAL SCH. I AND SCH. II. ALT. e corrected figure S 12,195.00 618.00 510.00 408.00 1,320.00 4.225.00 300.00 700.00 2.975.00 5,200.00 163.900.00 124.800.00 36,000.00 12.000.00 25,437.00 10,300.00 25.284.00 58.320.00 36,630.00 663.00 6.090.00 6,500.00 2.800.00 5.500.00 4,400.00 900.00 5,500.00 79,000.00 19.000.00 57,000.00 22,000.00 43.000.00 18,000.00 10,000.00 700.00 s 801,670.00 RAY N. BERTELSEN _ CO., INC. to UNIT TOTAL PRICE PRICE $ 0.20 S 16,76o.00 2.00 1,236.00 7.00 357.00 2.00 408.00 25.00 1,100.00 0.50 4,225.00 200.00 400.00 50.00 200.00 125.00 2,125.00 200.00 2,600.00 100.00 149,000.00 110.00 105,600.00 50.000.00 50,000.00 100.00 10,000.00 50.00 28,900.00 90.00 9.000.00 45.00 27,090.00 90.00 36,450.00 85.00 28.305.00 40.00 680.00 25.00 5.075.00 10,000.00 10,000.00 1.800.00 3,600.00 1.500.00 7.500.00 400.00 3,200.00 400.00 800.00 20,000.00 20.000.00 109.337.00 109.337.00 20,000.00 20.000.00 15.000.00 60.000.00 10,000.00 20,000.00 40.000.00 40,000.00 18,063.00 18.063.00 10.000.00 10,000.00 500.00 500.00 s 802.011.00 S 30,664.00 s 6.50 S 24,914.50 21,684.00 10.00 18,070.00 89.430.00 36.00 97.560.00 S 141,778.00 S 140,544.50 $ 26.775.00 s 6.50 S 20.475.00 109,329.00 36.00 119.268.00 S 136,104.00 $ 139.743.00 $ 943,448.00 $ 937.774.00 $ 942.555.50 $ 941,754.00 H.R. MCCULLOUGH. CO. Uri i T PRICE $ .12 .14 8.30 1.70 25.00 .78 110.00 42.00 125.00 250.00 115.00 144.40 29.756.00 130.00 57.00 110.00 43.00 77.00 88.00 32.00 29.00 7.658.00 3.400.00 2.100.00 590.00 612.00 17,890.00 90,000.00 10,500.00 14,000.00 9,729.00 48.900.00 17.975.00 9,950.00 380.00 S 6.20 8.91 32.00 S 6.20 31.38 TOTAL PRICE S 9.756.00 86.52 423.30 346.80 1,100.00 6.591.00 220.00 168.00 2.125.00 3.250.00 186.250.00 138.624.00 29.756.00 13.000.00 32.946.00 11.000.00 25.886.00 31,185.00 29,304.00 544.00 5,887.00 7.658.00 6.800.00 10.500.00 4.720.00 1.224.00 17,890.00 90,000.00 10.500.00 56.000.00 19.458.00 48,900.00 17.975.00 9.950.00 380.00 $ 830.403.62 $ 23.764.60 16,100.37 86,720.00 S 126,504.97 $ 19.530.00 103.961.94 S 123,491.94 S 956.988.59 $ 953.895.56 TOTAL SCM. 1 $ 875,031.00 $ 879,914.80 S 952.689.00 SCHEDULE 11 ALTERNATE A NUILUULt 1 8.00 s 30.664.00 S 6.00 S 22,998.00 S 3.50 S 13.415.50 2. OAK GROVE 17.166.50 9.50 • TEICIIERT CONSTRUCTION CONSTRUCTIC'1 CO. GRANITE CONSTRUCTION 67,072.50 37.00 SAL 28.25 76.557.50 TOTAL ALT. A ITEM UNIT = 140.434.50 S 109.850.00 ALTERNATE 8 140. PRICE PRICE I. $ 0.20 $ 16,260.00 $ 0.08 $ 6,504,00 $ 0.10 S 8,130.00 2. 1.00 618.00 0.20 123.60 0.50 309.00 3• 8.00 408.00 6.50 331.50 10.00 510.03 4. 2.00 408.00 1.80 367.20 2.00 408.00 S. 20.00 880.00 23.00 1,012.00 20.00 880.0 6. 1.10 9,295.00 0.60 5,070.00 0.60 5.070.00 7. 110.00 220.00 175.00 350:00 225.00 450.00 8. 35.00 140.00 30.00 120.00 100.00 400.00 9. 165.00 ;,805.00 117.00 1,989.00 225.00 3.825.00 ►0. 225.00 2,925.00 175.00 2,275.00 250.00 3,250.00 11. 110.00 163,900.00 130.00 193.7(.3.00 145.00 216.oS0.00 12. 150.00 144.000.00 145.50 )39,680.00 160.00 153.6oc.00 13. 28,000.00 28,000.00 22,000.00 22,000.00 24,000.00 24,000.00 14. 125.00 12,500.00 138.00 13,800.00 140.00 14.000.00 15. 62.00 35,836.00 77.50 44,795.00 110.00 63,580.00 16. 110.00 11,000.00 114.50 11,450.00 11C.00 11,000.00 17• 55.00 33,110.00 61.00 36,722.00 100.00 60.200.00 18. 100.00 40,500.00 142.50 57,%12.50 140.00 56,700.00 19. 110.00 36.630.00 113.00 37,629.00 125.00 41.625.00 20. 28.00 476.00 30.50 518.50 28.00 476.00 21. 20.00 4.060.00 28.50 5.785.50 25.00 5,075.00 22. 7.000.00 7.000.00 8.000.00 8,000.00 15,000.00 15.000.00 23. 1,000.00 2,000.00 2.560.00 5,120.00 2.500.00 5.000.00 24. 1.600.00 8,000.00 1.450.00 7,250.00 2.500.00 12.500.00 25. 400.00 3,200.00 1.170.00 9.360.00 950.00 7,600.00 26. 320.00 640.00 650.00 1.300.00 900.00 1,800.00 27. 27.000.00 27,000.00 1,000,00 1.000.00 1.00 1,00 28. 110,000.00 110,000.00 102.000.00 102,000.00 73.500.00 73.500.00 29. 23,000.00 23.000.00 17,000.00 17.000.00 30.000.00 30.000.OG 30. 15.000.00 60,000.00 14,500.00 58,000.00 14,000.00 56,000.00 31. 11.000.00 22.000.00 11,150.00 22,300.00 10.500.00 21.000.00 32. 42,000.00 42,000.00 40,000.00 40.000.00 32,000.00 32.000.00 33. 17.000.Go 17.000.00 16,5oo.00 16.5o0.00 19,000.00 19.000.00 34. 9.000.00 9,000.00 9,800.00 9.800.00 9.000.00 9,000.00 35. 220.00 220.00 350.00 350.00 750.00 750.00 TOTAL SCM. 1 $ 875,031.00 $ 879,914.80 S 952.689.00 SCHEDULE 11 ALTERNATE A 8.00 s 30.664.00 S 6.00 S 22,998.00 S 3.50 S 13.415.50 2. 9.50 17.166.50 9.50 17,166.50 11.00 19.877.00 3. 24.75 67,072.50 37.00 100,270.00 28.25 76.557.50 TOTAL ALT. A $ 114,903.00 = 140.434.50 S 109.850.00 ALTERNATE 8 $.Do S 25.200.00 S 6.50 $ 20.475.00 S 3.50 s 11,025.00 2. 24.75 81.996.75 37.00 122,581.00 28.25 93.592.2] TOTAL ALT. B S 107,196.75 $ 143,056.00 S 104,617.25 TOTAL $CH. I AND SCH. It. ALT. A $ 989.934.00 $1,020,349.50 $1.062.539.00 TOTAL SCN. 1 AND SCK. 11. ALT. B $ 982,227.75 $1.022.971.00 $1.057.306.25 • corrected figure SCHEDULE 1 4.15 i. . SNENGEL-ROBBINS. I1� ITEM UNIT TOTAL NO. PRICE PRICE I• $ 0.10 S 8,130.00 2. 0.19 117.42 3• 8.00 408.00 4.1.70 346.80 5. 76.25 1,155.00 6. 1.41 11,914.50 7. 95.00 190.00 8. 40.00 160.00 9. 132.00 2,244.00 10. 160.00 2,080.00 11. 130.00 193.700.00 12. 158.00 151.680.00 13. 25.900.00 25,900.00 14. 130.00 13,000.00 15. 79.00 45.622.00 16. 104.00 10,400.00 17. 55.00 33.110.00 18. 155.00 62.775.00 19. 122.00 40,626.00 20. 84.00 1,428.00 21. 36.00 7.308.00 22. 6.300.00 6.300.00 23. 2,100.00 4,200.00 24. 1.365.00 6.825.00 25. 1.260.00 10,080.00 26. 1,050.00 2,100.00 27. 25.200.00 25,200.00 28. 107..500.00 102.500.00 29. 14.850.00 14,850.00 30. 67,co0.00 67.000.00 31. 30.000.00 30,000.00 32. 43.000.00 43,000.00 33. 20,000.00 20,000.00 34. 15.000.00 15,000.00 . 35. 350.00 350.00 TOTAL SCH. SCHEDULE 11 ALTERNATE A 1. $ 4.15 i. 8.75 3. 33.00 TOTAL ALT. A ALTERNATE 8 1. $ 4.15 2. 33.00 TOTAL ALT. 8 TOTAL SCM. 1 AND SCH. 11, ALT. A TOTAL SCH. I AHO SCH. 11, ALT. 8 • corrected figure $ 959.739.72 S 15.906.95 iS.811.25 89.430.00 S 121.148.20 H.M. SYARS CONSTRUCTION Coda S 0.16 S 1.00 12.00 2.00 33.00 0.50 190.00 28.00 120.00 170.00 120.00 143.00 28,675.00 309.00 124.00 270.00 102.00 99.00 105.00 20. Do - 18.00 29,743.00 2.200.00 I,S50.00 400.00 400.00 45.000.00 106.045.00 15,847.00 20,840.00 10,100.00 40.000.00 17,500.00 13,000.00 800.00 S 8.00 12.00 34.00 13.008.00 618.00 612.00 408.00 1.452.00 4.225.00 380.00 112.00 2,040.00 2,210.00 178.800.00 137.283.00h 28.675.00 30,900.00 71,672.00 27.000.00 61,404.00 40,095.00 34.965.00 340.00 3.654.00 29.743.n0 4,400.00 7.750.00 3.200.00 800.00 45.0oo.00 106,045.00 15.847.00 83,360.00 20.200.00 40,000.00 17.500.00 13.000.00 800.00 $ 1,027,495.00 $ 30.664.00 21.684.00 92.140.00 S 144.488.00 W.R. 7HOMAS0-1. IrIC. $ 0.13 0.16 8.08 1.70 26.50 1.33 200.00 50.00 100.00 200.00 162.00 159.00 40.000.00 2c7.00 72.00 202.00 66.00 201.00 275.00 22.00 20.00 5.000.00 2.500.00 1.800.00 400.00 300.00 5.000.00 77,000.00 16,000.00 25,000.00 8.Goo. co 43,000.00 18,000.00 11,000.00 $40.00 S 3.98 8.48 36.00 S 10,569.00 98.88 412.08 346.80 1,166.00 11.238.50 400.00 200.00 1.700.00 2,600.00 241.380.00 152.640.00 40,000.00 20.700.00 41.616.00 20.200.00 39,732.00 81.405.00 91.575.00 374.00 4.060.00 5.000.00 5.000.00 9,000.00 3.200.00 600.00 5.000.00 77.000.." 16,000.00 100.000.00 16.000.00 43.000.00 18,000.00 11,000.00 540.00 $ 1.071.753.26 S 15.255.34 15.323.36 97,560.00 i 128.138.70 S 13.072.50 S 8.50 $ :6.775.00 $ 3.96 S 12,537.00 109.329.00 34.00 112.642.00 36.00 119.260.00 S 172,401.50 S 139.417.00 = 131.805.00 $ 1.080,887.91 $ 1.082.141.22 $ 1.171,983.00 S 1,166.912.00 i t,i99.$91.g6 S 1.203.558,26 SCHEDULE i DSS COMPANY ITEM UNIT TOTAL NO. PRICE PRICE 1• S 0.10 S 8.130.00 2. 0.15 92.70 3. 6.00 306.00 4. 1.70 346.80 5. 18.00 792.00 6. 0.80 6,760.00 7. 120.00 240.00 8. 30.00 120.00 9. 120.00 2.040.00 lo. 150.00 1,950.00 11. 150.00 223,500.00 12. 147.00 141,170.00 13. 50,000.00 50.000.00 14. 192.00 19.200.00 15. 67.00 38,726.00 16. 187.00 18.700.00 17. 61.00 36,722.00 18. 186.00 75.330.00 19. 255.00 84.915.00 20. 100.00 1.700.00 21. 25.00 5.075.00 22. 20,000.00 20.000.00 23. 1.300.00 2.600.00 24. 2,000.00 10.000.00 25. 1,200.00 9,600.00 26. 500.00 1.000.00 27. 25.000.00 25,000.00 c8. 140.000.00 140,000.00 2°. 12,000.00 12,000.00 30. 15.000.00 60.000.00 31. 12.500.00 25.000.00 32. 40.000.00 40.000.00 33._ 20.000.00 20.000.00 34. 10,000.00 10.000.00 35. 1,000.00 1.000.00 TOTAL SCH. 1 S 1,091.965.50 SCHEDULE it ALTERNATE A 1. $ 5.00 S 19,165.00 2. 11.00 19.877.00 3. 31.00 84.010.00 TOTAL ALT. A S 123,052.00 ALTERNATE 8 1. $ 5.00 i 15.750.00 31.00 102.703.00 TOTAL ALT. 8 $ 118,453.00 TOTAL SCH. i AND SCH, 11, ALT. A S 1,215.017.50 TOTAL SCH. 1 AND SCH. 11. ALT. 8 S 1,210,418.50 *,corse i figure CLUff AVEIIVE STORM GRAIN, industrial Way to Victor Road SCHEDULE til Engineer's Estimate ITEM APPROXIMATE UNIT NO. QUANTITY PRICE 1. 1155 Lf 8" Sanitary Sewer $ 16.00 2. 2 EA 46" Manhole 1100.00 3. 7 EA 4" Sanitary Sewer Service 450.00 TOTAL Wx. 0. McCullough Telchert Comg,any Construction Co. 1. S 10.88 S 12,566.40 S 12.60 S 14,53.00 2. 1270.00 2.540.00 800.00 1.600.00 3. 412.00 2.884.00 300.00 2,100.00 TOTAL $ 17,990.40 $ 18,253.00 N.M. Byars %"=I -Robbins Inc. Construction Co. 1. s 17.00 $ 19.635.00 S 20.00 $ 23.100.00 2. 1050.00 2.100.00 1100.00 2.200.00 3. 525.00 3.675.00 450.00 3,150.00 TOTAL $ 25.410.00 $ 28,450.00 TOTAL PRICE $ 18,480.00 2.200.00 3.150.00 $ 23.830.00 Claude C. Wood Co., Inc. UNIT TOTAL PRICE PRICE S 12.00 S 13.860.00 800.00 1.600.00 300.00 2.100.00 S 17.560.00 Oak Grove Constryction_Co. S 18.00 S 20,790.00 12CO.00 2.400.00 600.00 4.,'00.00 S 27,390.00 V.R. THOMASON. INC. i 20.00 S 23.100.00 1000.00 2.000.00 600.00 4,200.00 S 29.300.00 Ray N. Bertelsen Co. tnc. $ 14.10 S 16.170.00 1000.00 2.000.00 600.00 4.200.00 S 22.370.00 Granite Construction Co. S 12.00 $ 13.860.00 1:00.00 2.200.00 700.00 4.900.00 S 20.960.00 OSS COMPANY, INC. S 16.00 S 18.480.00 800.00 1.600.00 400.00 2.800.00 $ 22.880 00 E7