ACCEPTANCE The contract for "Catch Basin Replacement", Washington
OF "CATCH Street and Pine Street, Washington Street and Locust
,BASIN Street, Pleasant Avenue and Chestnut Street and Pleasant
REPLACEMENT Avenue N/Sierra Vista Place which had been awarded to
Teichert Construction of Stockton on October 1, I9S0
in the amount of $24,133.60 has been completed in
substantial conformance with the plans and specification
approved by the City Council.
COUNCIL ACCEPTED THE IMPROVEMENTS IN "CATCH BASIN
REPLACEMENT, WASHINGTON STREET AND PINE STREET,
WASHINGTON STREET AND LOCUST STREET, PLEASANT AVENUE
AND CHESTNUT STREET, AND PLEASANT AVENUE N/SIERRA
VISTA PLACE" AND DIRECTED THE PUBLIC WORKS DIRECTOR TO
FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER'S
i7 ..� OFFICE. F . .. E
O
CITY of LODI
C,
COUNCIL COMMUNICATION
TO: City Council
FROM: City Manager
DATE: December 22, 1980
SUBJECT: Acceptance of "CATCH BASIN REPLACEMENT" Washington St. and Pine St.,
Washington St. and Locust St., Pleasant Ave & Chestnut St, and Pleasant
Ave. N/Sierra Vista Place
RECOMKENDED ACTION: That the City Council accept the Improvements in "CATCH
BASIN REPLACEMENT - Washington Street and Pine Street, Washington Street and
Locust Street, Pleasant Avenue and Chestnut Street, and Pleasant Avenue
N/Sierra Vista Place" and direct the Public Works Director to file a Notice
of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Telchert Construction of
toc ton on October 1, 1980, in the amount of $24,133.60. The contract has
been completed in substantiat conformance with the plans and specifications
approved by the City Council.
The contract completion date was December 21, 1980, and the actual completion
date is December 22, 1980. The final contract price was $24,133.60.
rJac L. Ronsko
Pub is Works Director