Loading...
HomeMy WebLinkAboutAgenda Report - December 21, 2011 C-10AGENDA ITEM 'Gi 10 0CITY OF LODI COUNCIL COMMUNICATION M AGENDA TITLE: Accept Improvements Under Contractfor Water Meter Program Phase 1 and Adopt ResolutionAuthorizing City Managerto Execute Amendment No. 1 to Task Order No. 2 With RMC Water and Environment ($61,885) MEETING DATE: December21,2011 PREPARED BY: Public Works Director RECOMMENDED ACTION: Accept improvements under contract for Water Meter Program Phase 1 and adopt resolution authorizing the City Managerto execute Amendment No. 1 to Task Order No. 2 with RMC Water and Environment in the amount of $61,885. BACKGROUND INFORMATION: The projectwas awarded to Knife River, of Stockton, on March 16, 2011, in the amount of $1,872,285. The contract has been completed in substantial conformancewith the plans and specifications approved by City Council. The project consisted of the installation of 3,698 meters and the replacement of 4,220 feet of water main. The contract completion date was November30, 2011 and the actual completion date was November30, 2011. The final contract price was $1,999,379.98. The difference between the contract amount and the final contract price is mainly due to work added to reconstructthe water facilities within the area of the 2011 Alley Reconstruction Project (the alley north of Tokay Street from Stockton Street to Washington Street and the alley north of Eden Streetfrom Washington Streetto Garfield Street) becausethe existing facilities were too shallow. Additionally, the difference in the contract amount is due to six new services installed on Hutchins Street between Lodi Avenue and Oak Street; greaterwidth concrete collars placed around 193 water meter installations; and a reduction in overall contract quantities installed in the field. Task Order No. 2 with RMC Water and Environmentwas approved by the City Council on March 16, 2011 for construction administration services. The work included administration of the construction contract, observation of pipeline and water meter installations, and coordination of the projectwith the City's customers and water maintenance staff crews. The required efforts exceeded initial estimates of labor for inspection of each water meter inspection, coordination with contractor and City crews to implement main shut downs, and interacting with the City's customers. The contractor utilized the entire time allowed for construction. We had estimated the construction work would be substantially complete by the beginning of September. Due to these conditions, we are recommending Amendment No. 1 to Task Order No. 2, increasing the contract amount by $61,885 be authorized for execution by the City Manager. A copy of the task order amendment is provided as ExhibitA. Following acceptance by the City Council, as required by law, the City Engineerwill file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors A APPROVED: Konradt Bartlam, City Manager K:\WP\PROJECTS\WATER\Meters\Water Meter Program Phase 1\CAocept WMPP1 Amend TO2 mhm_ doc 1211212011 Accept Improvements Under Contract for Water Meter Program Phase 1 and Adopt Resolution Authorizing City Managerto Execute Amendment No. 1 to Task Order No. 2 With RMC Water and Environment ($60,377) December 12, 2011 Page 2 that the project is complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: Water main leak and service repairs will be reduced. No additional costs will be incurred for reading cfthe meters as they are automatically read concurrent with the reading of the electric meters. FUNDING AVAILABLE: Water Fund (181464): $61,855 Jor arTAvers Deputy City Manager/Internal Services Director ,J/1 /, If / k L -- F. Wally an elin Public Works Director FWS/pmf cc: Charlie Swimley, Deputy Public Works Director— Utilities K:\WP\PROJECTS\WATER\Meters\Water Meter Program Phase 1\CAccept WMPP1 Amend To 2 mhm_.doc 12/12/2011 DRAFT Exhibit A City of Lodi Water Meter Program Task Order No. 2 WMP Phase 1 Construction Management Services Amendment No. 1— Contract Close Out Task Order No. 2 with RMC Water and Environment was approved by the City Council on March 16, 2011 for Construction Administration services associated with the Water Meter Program Phase 1 construction project. The work included administration of the construction contract, observation of pipeline and water meter installations, and coordination of the project with the City's customers and water maintenance staff crews. The required efforts exceeded initial estimates for the following reasons: • Increased labor required for inspection of each water meter installation due to widely varying field conditions and subsequent surface restoration work. • Additional coordination with contractor and City crews and interacting with affected customers to implement main shut downs required to address deteriorated polybutylene service line restoration. • Increased field time due to the contractor utilizing the entire time allowed for construction. We had estimated the construction work would be substantially complete by the beginning of September. • Late issuance of the contract Notice -to -Proceed extended the original contract administrative and inspection duration by approximately two months. • Varying field conditions and decision/direction making process were underestimated resulting in the increase to regulate and observe the contractor activities, and process change orders. • Initial Field Intern Observer (FIO) hours (2000 -hours) were under estimated with actual FIO hours exceeding 20%. • Compilation of post meter installation data, and increased coordination with National Meter associated with correlation of installed meters to APN/Service addresses. This proposed Amendment No. Ito Task Order No. 2 would increase the contract authorized amount by $61,885 to address the higher level of effort and extended construction duration (beyond that assumed in Task Order No. 2). The additional effort is described further below bytask. Task 1— Engineering Services during Construction (ESDC) Original Scope: The Consultant will provide engineering services during construction for the City to address Contractor submittals, record drawings and to provide overall technical support. The ESDC effort will be led by Tom Dugan (Resident Engineer- RE) and supported by the WMP Phase 1design team of Mike Matson (Senior Review), Tony Valdivia (Project Manager), Kevin Smith (Project Engineer), and Victor Alaniz (CAD Production). The level of effort for ESDC activities is limited to the budgeted hours. WMP Phase lConstruction Management Services 1 November30,2011 Scope of Work City of Lodi Water Meter Program DRAFT Amendment No. 1 Modifications: Task 1 level cf effort increased as a result cf more Rfls than originally assumed due to widely varying field conditions. These included additional surface restoration requirements and additional service line piping modifications. These contractor and City issued Rfls caused additional engineer review time beyond what was originally estimated. Task 2 — Contract Administration Original Scope: The Consultant will provide construction contract administration services throughout the WMP Phase 1construction period. Services will include conducting construction meetings, supporting contract execution and modification process with the City, reporting and coordinating with City staff on construction issues and progress, reviewing and recommending action on contractor progress payment requests, negotiating and preparing construction change order documentation, reviewing the contractor's progress schedule, administering and coordinating engineering reviews and responses to RFIs, supporting the contractor's public notification activities, managing and coordinating the meter procurement vendor activities, and project closeout activities. Contract administration will be performed by Tom Dugan (RE)and supported by RMC and Nolte staff. Amendment No. 1 Modifications: Thefollowing modifications are made to the original scope: 1. The duration cf contract administration activities was extended by approximately one month due to late issuance by City of contractor NTP. The late NTP resulted in a contract end date cf November 30,2011. Closeout activities have been extended to mid-December, 2011. This has resulted in additional effort beyond that assumed in Task Order No. 2. 2. The level cf effort associated with contract administration was higher than anticipated in the original scope cf services. Increased contract administration effort was required to address unanticipated field conditions and associated contract quantity changes and change orders. The actions cf the City's contractor also required effort to enforce contract requirements and document non-compliance, including extensive negotiation cf the S WPPP requirements and resolution of a dispute on meter box lid requirements, increased coordination with City personnel regarding mainline shut downs to repair deteriorated polybutylene service lines and leaking valves, and increase coordination with the City's meter vendor National Meter, the contractor and City Information Service Division (ISD) to correlate the installed meters with the APN/Service Address. Task 3 — Field Observation Activities Original Scope: The Consultant will provide limited inspection services throughout the construction period. Services will include general field observation and inspection tasks, mainline and meter installation inspection, and providing and coordinating specialty inspections for the project. The task lead will be Tom Dugan (RE) supported by Ryan Wilson (Lead Inspector). Amendment No. 1 Modifications: field observation services performed by Nolte Vertical five (NV5) Lead Inspector were budgeted to be complete by the end cf September 2011. field work was completed on November 30,2011, two months past the originallyscoped construction period. This extended work duration resulted in additionalfield inspection time by the Lead Inspector to verify that the contractual obligations cf the contractor were met and to address resident complaints, provide more prompt in -field resolution to unforeseen field condition changes, and trackforced account work. Similarly, the meter inspection period for the field intern observers (F10s) were initially budgetedfor 2, 000 -hours under the Task Order No. 3 scope and budget. ;At the direction cf the City, RMC maintained the FIOs on the meter installation work until it was complete on November 30, 2011. The total FIO labor was over 2,400 -hours (+20% increase) to monitor the 3,698 meter installations and maintain the meter WMP Phase lConstruction Management Services 2 November30,2011 Scope of Work City of Lodi Water Meter Program DRAFT installation database that serves the dual purpose cf processing the contractor's pay requests and provides utility asset management data for the City. The hours exceeding the Task Order No. 3 budget are included in this amendment at the direction cf the City. Task 4 — Document Control Management and Project Closeout Services Original Scope: The Consultant will provide document management services, including project closeout activities. This task will be led by Tom Dugan (RE) and supported by the inspection team. Amendment No. 1 Modifications: The Task level cf effort increased as a result cf the unanticipated number cf change order items that required processing (e.g. twenty twoforce account work items to address differing field conditions, the 2011 Alley Reconstruction Project, and six additional service connections within Hutchins Street) and the increased effort to provide quality assurance on the meter installation database and the correlated installed meter toAPN/Service Address data collected by National Meter. WMP Phase lConstruction Management Services 3 November30,2011 Scope of Work RMC WATER AND ENVIRONMENT CITY OF LODI Signature Michael H. Matson Sr. Vice President Date Signature Printed Name Title Date ATTEST: RANDI JOHL City Clerk U1ZIZI Ti192&111ix; ti7:7i•i D. STEPHEN SCHWABAUER City Attorney W M P Phase 1Construction Management Services 4 November 30,2011 Scope of Work 0"M Water and Environment Fee Estimate City of Lodi -Water Meter Program Phase 1 Construction Management Services (Task Order 2, Amendment No. 1) 1. The individual hourlyrates includesalary, overhead and profit. 2 Subconsunants wil I be billed at actual cost 3.Otherdirectoosts(ODCs) such as reproduction.delivery. mileage (rateswill be those allowed by cumentlRSguidelines), and travel expenses,will be billed at actual cost plus 10%, 4. RMC reserves the rightto adjust its hourly rate structure and ODC markup at the beginningof the calendaryear for all ongoing contracts. RESOLUTION NO. 2011-190 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZINGTHE CITY MANAGERTO EXECUTE AMENDMENT NO. 1 TO TASK ORDER NO.2 FOR WATER METER PROGRAM PHASE 1 CONSTRUCTION ADMINISTRATION SERVICES WHEREAS, Task Order No. 2 with RMC Water and Environment, of Walnut Creek, California, was approved by the City Council on March 16, 2011, for construction administration services for Water Meter Program Phase 1, and the work included administration of the construction contract, observation of pipeline and water meter installations, and coordination of the project with the City's customers and water maintenance staff crews: and WHEREAS, the required efforts exceeded initial estimates of labor, and staff recommends authorizing the City Manager to execute Amendment No. 1 to Task Order No. 2, increasing the contract amount by $61,885. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve Amendment No. 1 to Task Order No. 2 for Water Meter Program Phase 1 Construction Administration Services with RMC Water and Environment, of Walnut Creek, California, in the amount of $61,885; and BE IT FURTHER RESOLVED that the City Council does hereby authorize the City Manager to execute the task order amendment on behalf of the City. Dated: December 21, 2011 ------------------------------------------------------------------- ------------------------------------------------------------------- I hereby certify that Resolution No. 2011-190 was passed and adopted by the City Council of the City of Lodi in a regular meeting held December 21, 2011, by the following vote: AYES: COUNCIL MEMBERS — Hansen, Katzakian, Nakanishi, and Mayor Mounce NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS —Johnson ABSTAIN: COUNCIL MEMBERS— None �LrHL City Clerk 2011-190