HomeMy WebLinkAboutAgenda Report - October 19, 1988 (51)CITY O L O D l COUP CI L COMMUNICATIONPUBLIC WORKS DEPARTMENT
RECOMMENDED ACTION: That the City Council accept the improvements for
"Orange venue/Mariposa Way Water Main and Lawrence Avenue Water Main, Main
Street to Washington Street", and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND P4FORMATION The contract was awarded to Claude C. Wood Company
of Lodi on April 6, 1988, in the amount of $71,598.00. The contract has been
completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion date was August 22, 1988, and the actual completion
date was October 6, 1988. The final contract price was $71,376.00. The
contractor was charged $810.00 in liquidated damages for the contract time
overrun which was due to a late start.
(Jack L. Ronsko
Publ c Works Director
JL RCP/mt
cc: Water/Wastewater Superintendent
Purchasing Officer
APPROVED: . %� _ f�,-�_ f�—' � FILE N0.
CWATERM5/TXTW.02M
October 12, 1988
Pro Data
TO:
City Counci 1
Originally Bu gete :
1987/88
Budgeted Fund: Water Capital Outlay
FROM:
City Manager
Amount Budgeted:
949,000
Total Project Estimate:
$86,000
MEETING DATE:
Cciober 19, 1988
Bid Opening Date:
3/30/88
AGENDA TITLE:
Accept Improvements Under
Orange Avenue/Mariposa
Way Water
Main and Lawrence Avenue
Water Main, Main Street
to
Washington Street, Contract and Direct the Public
Works
Director to File a Notice
of Completion with the
County
Recorder's Office
RECOMMENDED ACTION: That the City Council accept the improvements for
"Orange venue/Mariposa Way Water Main and Lawrence Avenue Water Main, Main
Street to Washington Street", and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND P4FORMATION The contract was awarded to Claude C. Wood Company
of Lodi on April 6, 1988, in the amount of $71,598.00. The contract has been
completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract completion date was August 22, 1988, and the actual completion
date was October 6, 1988. The final contract price was $71,376.00. The
contractor was charged $810.00 in liquidated damages for the contract time
overrun which was due to a late start.
(Jack L. Ronsko
Publ c Works Director
JL RCP/mt
cc: Water/Wastewater Superintendent
Purchasing Officer
APPROVED: . %� _ f�,-�_ f�—' � FILE N0.
CWATERM5/TXTW.02M
October 12, 1988