T0: City Council
FROM: City Manager
MEETING DATE: October 4, 1989
COUNCIL COMMUNICATION
Project Data
U., 11 lnal y ete : 1987/88
Budgeted Fund: Water Capital Outlay
Amount Budgeted: $262,000 (total)
Total Project Estimate: $99,700
(this phase)
Bid Opening Date: 3715/8
AGENDA TITLE: Acceptance of Improvements Under Well Drilling, Well 23,
55 East Harney Lane, Contract
RECOHHENDED AC-ffiR That the City Council accept the improvements for 'Well
Drilling, Well 23, 55 East Harney Lane" and direct the Public Works Director tb
f i l e a Notice of Completion w i t h the County Recorder's of f 1 ce .
t
f
oi
BACKGROUND_ INFORMATION: The contract was awarded to Peylik Drilling, Inc. of i
La Habra on March 22, 1989, in the amount of $98,460.00. The contract has been
completed in substantial conformance with the plans and specifications approved'.
by the City Council.
The contract completion date was July 3, 198.), and the actual completion date
was July 14, 1989. The final contract price was $99,020;00. The difference �
between the contract amount and the final contract price is mainly due to
adjustment in wel i development time and liquidated damages, The delay in
accepting the project was due to the contractor's tardiness in submitting
payroll reports.
3
Jack L. Ronsko ?
Public Works Director
JLR/ML/mt