HomeMy WebLinkAboutAgenda Report - September 28, 1988 (92)0CITY OF LODI`�PUBLIC WORKS DEPARTMENT
COUNCIL COMMUNICATION
TO : City Council Project _Data
Budgeted Fund: County Funded
FROM: City Manager Total Project Estimate: $21,500
Bid Opening Date: 6/29/88
MEETIlVG DATE: September 28, 1988
AGENDA TITLE: Accept improvements Under Building Removals, 207 West Elm
Street and 211 West Elm Street, Contract
RECOMMENDED t1CTdON.- That the City Counci 1 accept the improvements for
"Building Removals, 207 West Elm Street and 211 West Elm Street", and direct
the Public Works Director to file a Notice of Completion with the County
Recorder's office .
BACKGROUND D&ORMAUON: The contract was awarded to Don Lawley Company/
Conco West of Stockton on July 6, 1988, in the amount of $20,448.00. The
contract has been completed in substantial conformance with the plans and
specifications approved by the City Council
The contract completion date was October 7, 1988 and the actual completion
date was September 15, 1988. The final contract price was $21,081.00. The
difference between the contract amount and the final contract price is mainly
due to remov 1 of additional asbestos exposed during the work.
sti
Jac L. Ronsko
is Works Director
JLR/DC/mt
cc: Purchasing Officer
Building & Equipment Maintenance Supt.
APPROVED:
CELM3/TXTW.02M.
FILE NO.
September 20, 1988