CITY OF LODI
2 �
v'
PUBLIC WORKS
TO: City Council
FROM; City Manager
NIE11% DATE: September 6, 1989
COUNCIL COMMUNICATION
P.r ee t Grata
Ori inally Budgeted — 1988189
BuTgeted Fund : Capital Outlay
Amolmt Budgeted: $39,400
Total Project Estimate: (approx,) $47,000
Bid Opening Date: 1/18/89
Overrun Fund: Capital Outlay Reserve
AGENDA TITLE: Accept Improvements Under Carnegie Forum Hardscape, 305 'West
Pine Street, Contract
RECOMMENDED AC M- That the City Council accept the improvements for
' Carnegie Fonni Hardscape, 305 West Pine Street" and direct the Public Works
Director t o f f a Noti ce o f Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Case Construction of
Lodi on February 1, 1989, in the amount of $34,304.00. The contract has been
completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract and the actua? completion date was July 21, 1989. The final
contract price was $44,974.60. The difference between the contract amount
and the final contract price is mainly due to additional sidewalk, brick and
retaining wall at the east entrance needed to match existing grades and work
at the north side to accommodate the picnic tables. The Lodi City Employees
Association donated $4,575.00 for the purchase of the tables and installation
of the additional concrete pad and brick edging.
Spt Jack L. Ronsko
Public Works Director
JLR/RCP/mt
cc: Purchasing Officer
Street Superintendent