HomeMy WebLinkAboutAgenda Report - August 16, 1989 (61)Project ata
Originally Bu getd ed: 1987/88
TO: City Col+nci 1 Budgeted Fund: 140-502.64-323
Amount Budgeted: $50,000.00
FROM: City Manager Total Project Estimate (this phase):
$100,000.00
MEETING DATE: August 16, 1989 Bid Opening Date: 12/20/88
AGENDA TITLE: Acceptance of Improvements Under Installation of Mechanical
Equipment and Iry Roof on Cafeteria Building at Hutchins
Street Square, 600 West Oak Street i
RECOMMENDED ACTION That the City Council accept the improvements for
"Installation of Mechanical Equipment and New Roof on Cafeteria Building at
Hutchins Street Square, 600 West Oak Street" contract and direct the Public
Works Director to file a Notice of Completion with the County Recorder's
office.
BACKGROUND Il%YCRMATION The contract was awarded to Diede Construction,.of
Woodbridge on January 4, 1989, in the amount of $83,997.00. The contract nas t .
been completed in substantial conformance with the plans and specifications ;
approved by the City Council.
Thr- contract completion date was April 14, 1989 and the actual completion
date utas June 20, 1989. The final contract price was $87,853.00. The
difference between the contract amount and the final contract price is mainly
due to addition of ree /roof drains, downspout, and scupper to improve
dra nag,.Jkl//
Ja k L Ronsko 1
Pub'ii Works Director
JLR/DC/nit
cc: Purchasing Officer
Building & Equipment Maintenance Supt.
Community Center Director
APPROVED:
1r;, Manager
FILE NO.