AGENDA TITLE: Contract Agreement for Design and Preparation of Construction
Drawing for Hale Park, 209 East Locust Street
RECOMMENDED ACTION- That the City Council authorize the City Manager and
TiTy Clerk to execute the contract agreement between the City of Lodi and
Richard Bigler for providing construction plans and specifications for the
Hale Park improvements.
BACKGROUND ll i1U AJM- Under last year's Capital Improvement Program, the
City Council allocated block grant funds for phased construction and upgradd :Y:.':-`'`
of the Hale Park facilities. The improvements to be made with block grant
funds did not include the replacement of the Hale Park building. The
proposed addition to the existing parking lot will be designed by the Public
Works Department. A71 other improvements included i n the accepted Hale Park'
Master Plan are covered under this agreement.
The contract amount is $41,650. Forty thousand dollars has been budgeted for
.this work. Therefore, Council approval of this contract will include
allocating an ition 1 $1,650 from the General Fund Operating Reserve.
&el i
ck.nsko
rks Director