HomeMy WebLinkAboutAgenda Report - August 1, 2012 I-01AGENDA ITEM
Zoo '
&% CITY OF LODI
COUNCIL COMMUNICATION
im
AGENDA TITLE: Designatethe Overhead Grade Separation and Embankment Design as the
Exclusive Alternative for the Harney Lane Grade Separation Project
MEETING DATE: August 1,2012
PREPARED BY: Public Works Director
RECOMMENDEDACTION: Designate the overhead grade separation and embankment design
as the exclusive alternative for the Harney Lane grade separation
project.
BACKGROUND INFORMATION: At the June 17, 2009 City Council meeting, a resolution was adopted
establishing the Harney Lane grade separation as the City's preferred
projectfor the Measure K Railroad Grade Separation Program. On
August 10, 2010, a feasibility study report was completed by Mark Thomas & Company (MT&C) that
established four alternative designs for the Harney Lane grade separation. In November 2011, the
San Joaquin Council of Governments Board designated $12,100,000 in funding for this project in the
2012 Regional Transportation Improvement Program (RTIP). In March 2012, the California Transportation
Commission approved the funding program in the RTIP.
On October 5, 2011, City Council approved a professional services agreement with MT&C to prepare
environmental, right-of-way and construction documents for the Harney Lane grade separation. At the
March 17, 2012 Shirtsleeve meeting, MT&C presented four alternatives design concepts to the Council.
The first alternative, the exclusive alternative, is an overhead structure with side embankments.
Alternative 2 is an overhead structure with mechanically stabilized earth (MSE) walls on both sides of the
roadway; Alternative 3 is an undercrossing with retaining walls; and Alternative 4 is an undercrossing with
side slopes.
Environmental review of the project must comply with both the California Environmental Quality Act
(CEQA) and the National Environmental Protection Act (NEPA). Under CEQA, the project is statutorily
exempt and no environmental review is required. Under NEPA, the environmental review can be
processed underthe Categorical Exemption criteria if the Council selects the project alternative at this time.
Federal guidelines require that all alternatives be reviewed at a comparable level. In the case of the grade
separation project, the differences in the environmental impacts for each alternative are insignificant. For
example, the number of lanes and traffic operations are the same and, therefore, the air quality impacts will
be the same for each alternative. Also, the area of disturbance is the same for each alternative and,
therefore, the natural environment impacts will be the same. Finally, each alternative has associated visual
and noise impacts that can all be mitigated to less than significant levels.
Staff is requesting Council to designate the overhead grade separation with embankment design as the
exclusive alternative for this project. Justifications for this action are provided below. Cost comparisons,
sketches, typical cross section, and approximate right-of-way requirements for the four alternatives are
presented in Exhibit 1.
APPROVED: i X_,l
Konr t Bartlam, City Manager
K:\WP\PROJECTS\STREETS\HarneyGradeSeparation\CCPreferred Alternative- HarneyGrade.Sep.doc 7/24/2012
Designate the Overhead Grade Separation and Embankment Design as the Exclusive Alternative for the
Harney Lane Grade Separation Project
August 1, 2012
Page 2
Project Cost — The estimated cost for the overhead design of $18,060,000 is the least expensive of
the four alternatives, and the cost is within the project budget of $20,339,000. The other three
alternatives are not affordable in the foreseeable future.
Utility Relocation — The Kinder Morgan fuel line and AT&T's fiber optic cables existing along the
railroad tracks must be relocated for an undercrossing. The cost of these relocations is a significant
project expense and will add several months to the project schedule. Overhead wire utility
relocations are comparable for each alternative and are paid by the individual utility companies.
Noise — The embankment design will shield existing and future residents from train noise. Also, the
grade separated crossing will eliminate the requirement for trains to sound horns as the cross the
intersection.
Maintenance— The undercrossing alternatives, because they require a storm drainage pump station,
have the relative greatest maintenance cost. Not only will the pump station require maintenance but,
also, UPR requires the steel undercrossing structure to be made of steel and the City is required to
maintain the structure.
Land/Right-of-Way Requirements — The overhead with side embankments alternative requires the
greatest area of right-of-way to be acquired at 5.67 acres but it is $7.6 million less expensive than the
next higher cost alternative, overhead with retaining walls. The right-of-way required for the other
alternatives ranges from 3.38 acres (overhead with retaining walls) to 4.06 acres (underpass with
retaining walls) to 4.83 acres (underpass with slopes). The greater right-of-way requirement for the
underpass alternatives is due to the right-of-way required to re-route Harney Lane around the
construction area. Exhibit 2 includes diagrams presenting the right-of-way requirements for each
alternative.
6. Time and Coordination — Construction of the overhead alternative requires less time and the
construction phasing is most easily coordinated. Overall, an overhead crossing takes six to 10
months less to construct than an undercrossing. The following provides several examples of this:
6.1. The undercrossing alternative requires Harney Lane and the railroad to be re-routed around the
construction area. This adds approximately five months to the construction schedule and
significant cost to the project.
6.2. At the new railroad crossing of re-routed Harney Lane new crossing protection is required. This
is subject to the Public Utility Commission and Union Pacific Railroad (UPRR) approval
processes and adds six months project design period and significant additional cost.
6.3. The existing Kinder Morgan fuel and AT&T fiber optic lines will have to be replaced by the
affected utility that is separate from the project schedule.
6.4. The undercrossing alternative requires a structure supporting the railroad that is compliant with
UPR requirements. Approximately six months is added to the design phase associated with UPR
review and approvals and three months to the construction phase for this type of construction.
Harney Lane Open to Traffic — The overhead with embankments alternative allows Harney Lane to
stay open during of construction without incurring significant added cost. The overhead alternative
will be constructed in two segments, utilizing the existing roadway during the construction of the first
segment then detouring traffic to the new overhead structure while completing construction of the
second segment.
Mark Thomas & Company and City staff had one-on-one meetings with each of the affected property
owners along the grade separation project boundaries. Staff also held an open workshop public meeting
on July 17, 2012. Approximately 20 persons attended this public meeting. Invitations were mailed to
1,287 stakeholders and notices of the meeting were published in the Lodi News Sentinel. A copy of the
public meeting report is provided as Exhibit 2.
K:\WP\PROJECTS\STREETS\HarneyGradeSeparation\C0Preferred Alternative- Harney GradeSep.doc 7/24/2012
Designate the Overhead Grade Separation and Embankment Design as the Exclusive Alternative for the
Harney Lane Grade Separation Project
August 1, 2012
Page 3
Staff received concerns and comments at these meetings and has strived to comply with each of the
issues raised. The issues and resolutions worked out with the various stakeholders are summarized
below. It should be expected that additional issues will arise as the project moves closer to construction.
Source Issues
Resolution
Modified access, driveway and
access, laydown and work areas
circulation plan
Varner Household
Traffic noise and landscape
Sound wall and landscape
boulders
improvements
Costa Family Farms
Packing house operations,
Full signalized intersection and
orchard operations, access and
driveway access on Harney Lane
property acquisition
Tsutsumi Vineyard
Vineyard operations and property
Full take of property probable
acquisition
Reynolds Ranch
Retail operations impacted by
Harney Lane to remain open to
road closure
traffic
Homeowner
Screening views of backyard
Construct masonry block wall
from overhead
behind sidewalk
Public Works staff concurs with these points and requests City Council to approve the overhead with side
slopes grade separation alternative.
FISCAL IMPACT: Not applicable.
FUNDING AVAILABLE: Not applicable.
�A I Ja
F. Wally Wdelin
Public Works Director
Prepared by Chris Boyer, Assistant Engineer
FWS/CB/pmf
Attachments
K:\WPIPROJECTS\STREETS%HameyGradeSeparation%CCPreferred ALmative- Harney Grade Sep.doc 7/24/2012
HARNEY LANE/UPRR GRADE SEPARATION
445�041� e�ti1444 �' ��1S1o4�
�4��',� mss
v�e� ae�4 ,5�, �4P Abe{Q
Roadway Items
$
6,000,000
$
6,000,000
Structure Items
$
3,500,000
$
3,500,000
Retaining Walls
$
-
$
5,000,000
Sound Walls
$
246,000
$
223,000
Railroad/Detour Items
$
300,000
$
1,400,000
Mobilization (10%)
$
1,005,000
$
1,613,000
Contingency 25%
$
2,512,000
$
4,031,000
Construction Subtotal
$
13563,000
$
21,767,000
$
1,100,000
$
1,600,000
$
Right of Way
$
1,500,000
$
1,000,000
Utility Relocation
$
300,000
$
300,000
Environmental Fees/Permits
$
300,000
$
200,000
Capital Cost Subtotal
$
2,100 000
$
1500,000`
1,800,000
$
1,800,000
$
250,000
Environmental/Design
$
1,530,000
$
1,530,000
Construction Mgmt
$
1,500,000
$
1,500,000
Construction Staking
$
200,000
$
200,000
Project Development Subtotal
$
3,230,000
$
3230 000
Grand Total 1 $ 18,893,000 1 $ 26,497,000 11
Exhibit 1 1
7/19/2012
$
6,400,000
$
6,200,000
$
5,000,000
$
5,200,000
$
2,500,000
$
800,000
$
240,000
$
220,000
$
2,300,000
$
2,900,000
$
1,644,000
$
1,532,000
$
4,110,000
$
3,830,000
$
22,194 000
$
20`682 000;
$
1,100,000
$
1,600,000
$
1,500,000
$
1,500,000
$
200,000
$
300,000
$
2,800 000
$
3,400,000
$
1,530,000
$
1,530,000
$
1,800,000
$
1,800,000
$
250,000
$
250,000
$
3,580,000
$
3,580 000
$
28,574,000 JFi-7
27,662,000
Exhibit 1 1
7/19/2012
Aut�rlatN�#1-� Jt�MtTt("
�: �,.� � ,�Z Marx •ntaar,�;, , ��•
r
x..f
IL
1
L
�
'
�
- __
'
���������•
_—
.,.ter I
�
WWII
rAly: =V f 4,20M MaEk tuaw+s { O'k
olz o59-tt 77
emx mzaAlr-
i
Ex PROP
P/W VAR
EaAr 2- AW
RAISED Im IAN
G91WCrE I W11GiETE
BARRIER SWIER
IH %%u 4Vi USE BALL
p�A�y� `RAI LRDAD AO�355 AND/CR
VETT A A UTI LILY ooRRIDOt
NDr TO SCALE
t
�: oss-t�-tit
e,�sr 12.5T.AG
-Farr%ml
AVtJ: 0-36-130-24
WW. V-I*AC-
MIX- W-?Z.Ar,
IC
-T "I
I >L
-Farr%ml
AVtJ: 0-36-130-24
WW. V-I*AC-
Draft
Public Information Meeting
Summary Report
Tuesday, July 17,2012
6:00 p.m. - 7:30 p.m.
Carnegie Forum
305 West Pine Street
Lodi, California
Prepared by Judith Buethe Communications
Exhibit 2
Harney Lane Grade Separation Project Public Information Meeting Summary Report
General Information about This Document
Whatisin this document?
This document is a summary report of a Public Information Meeting for the Harney Lane Grade
Separation Project, Lodi, California. This document describes what occurred at the meeting.
Whatshouldyou do?
♦ Please read this summary report.
♦ If you have any concerns about the summary report or questions about the proposed
project, please contact Judith Buethe, (209) 464-8707, Ext. 101;
Judith buethecommunications.com or P.O. Box 773, Lodi, CA 95201-0773.
2 1 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Table of Contents
CoverSheet........................................................................................... 1
General Information about This Document...................................................... 2
Tableof Contents.................................................................................... 3
Chapter1: Introduction.......................................................................... 4
1.1 A Public Information Meeting Was Held ................................................... 4
1.2 Announcements of the Public Information Meeting ....................................... 4
1.3 Purpose and Goals of the Public Information Meeting .................................... 5
1.4 Format of the Public Information Meeting .................................................. 5
1.5 Summary of Concerns Expressed............................................................ 5
Chapter2: Meeting Proceedings............................................................... 6
2.1 Welcome......................................................................................... 6
2.2 Displays and Exhibits.......................................................................... 7
Station 1: Welcome Boards and Sign -in Tables ........................................ 7
Station2: Exhibits.......................................................................... 7
Station 3: Comment Station.............................................................. 7
2.3 Personnel on Hand............................................................................. 7
2.3.1 City of Lodi Staff................................................................... 7
2.3.2 Consultants........................................................................... 7
2.3.3. Elected Officials and Other Agencies ............................................ g
Chapter 3: Presentation with Questions and Answers .................................... 9
Public Questions and Comments......................................................... 9
Chapter4: Public Input.......................................................................... to
4.1 Written Comment Received at the Public Information Meeting ......................... 10
4. 1.1 Listing of Comment Sheets and Correspondence Received at the Public
Meeting............................................................................... 10
Chapter 5: Outcome of the Public Information Meeting .................................. 11
APPENDICES
AppendixA: Handouts............................................................................ 12
Agenda................................................................................................. 12
CommentSheet....................................................................................... 13
Sign -in Sheet.......................................................................................... 14
AppendixB: Exhibit Materials.................................................................. 15
WelcomeSign........................................................................................ 15
DisplayMaps......................................................................................... 16
3 1 P a g e
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Appendix C: Notices and Letters............................................................... 19
PostcardInvitation................................................................................... 19
Ad...................................................................................................... 20
PressRelease.......................................................................................... 21
Appendix D: Photographs at the Meeting ..................................................... 22
Appendix E: Public Comments.................................................................. 24
Appendix F: Meeting Sign -in Sheets............................................................ 25
Appendix G: PowerPoint Presentation........................................................ 28
4 1 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Chapter 1: Introduction
1.1: A Public Information Meeting Was Held
The City of Lodi Department of Public Works held a Public Information Meeting for the Harney
Lane Grade Separation Project at the following date, time, and place:
Tuesday, July 17,2012
6:00 p.m. — 8:30 p.m.
Carnegie Forum
305 West Pine Street
Lodi, Calif.
The City of Lodi held the meeting to present the Harney Lane Grade Separation Project
alternatives and the estimated costs of each alternative being considered. This Public Information
Meeting was an opportunity to provide comments or concerns about the project at a public
meeting.
1.2: Announcements of the Public Information Meeting
The project team planned and implemented the Public Information Meeting to invite members of
the public, businesses, agencies, and other potentially interested parties to learn more about the
project and to discuss individual concerns with representatives from the City of Lodi Public
Works Department, along with other specialists in engineering and planning.
The meeting was publicized through ajumbo postcard invitation that was sent by first-class U.S.
mail to a mailing list of approximately 1,286 property owners, residents, and stakeholders such
as local, state, and federal agencies; emergency responders; civic and community groups, the
Lodi District Chamber of Commerce and other business groups; environmental groups; and other
potentially interested individuals and organizations.
A news release was sent to print and broadcast media (mainstream and alternative) that serve the
project area. The news releases were sent to the following mainstream and alternative media
outlets: TheRecord, Lodi News -Sentinel, Citadel Broadcasting, Clear Channel, San Joaquin
Hispanic Chamber of Commerce, Lodi District Chamber of Commerce, Asian -Pacific Chamber
of Commerce, African-American Chamber of Commerce, KANM/KBUL, KAT Country 103,
KCBC-770 AM, KCIV-99.9 FM; KCSO Telemundo 33, KCSS-FM, KHKK 104.1 The Hawk,
KHOP, KJAX 1280, KJSN, KVFX, KKME, KQOD, KMRQ, KOSO, KRVR, KUYL, KVIN,
San Joaquin Farm Bureau News,Builders Exchange, Business Council, Inc., and San Joaquin
Partnership.
51 Page
Harney lane Grade Separation Project Public information Meeting Summary Report.
1.3: Purpose and Goals of the Public Information Meeting
The purpose of the Public Information Meeting was to provide an opportunity for the community
to review the Hai-ney Lane Grade Separation Project, learn about the proposed alternatives for
consideration and construction, and provide individual comments or concerns about the project
and the plans.
1.4: Format of the Public Information Meeting
Thirty people signed attendance sheets at the Public Information Meeting -21 members of the
public and nine project team members. The meeting was held in the Carnegie Forum, where the
City Council meetings are routinely held. At the door, the Public Outreach representative
welcomed attendees, explained the evening's format, asked attendees to sign in, and distributed a
comment sheet and a print program to each. The Public Outreach staff also introduced attendees
to technical members of the project team and answered questions of a general nature.
The meeting was conducted as an open house/map showing with a presentation, followed by a
question -and -answer session. This interactive format provided an opportunity for individual
members of the public to ask questions of and direct comments to members of the project team—
or to ask questions and make comments in a group setting. Attendees were encouraged to submit
written comments.
Project team members were available throughout the evening to explain the displays, answer
questions, and receive public input.
A brief presentation was made at 6:20 p.m. After housekeeping remarks by Judith Buethe, Public
Outreach Coordinator, Rob Himes, P.E., Principal, Mark Thomas & Company, Inc. addressed
the group with a PowerPoint presentation, providing project background, progress, alternatives
being considered, cost, and schedule. Mr. Himes' presentation was followed by a question -and -
answer period. [A copy of the PowerPoint presentation can be found in Appendix G.]
1.5: Summary of Concerns Expressed
The overall feedback from attendees about the breadth and depth of the information provided and
the accessibility of project team members was positive. One comment sheet was received at the
meeting. A list of dominant concerns or comments given at the meeting can be found in Chapter
4, "Outcome of the Public Information Meeting."
61 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Chapter 2: Meeting Proceedings
2.1: Welcome
The room set-up at the Public Information Meeting was developed according to the layout shown
below:
I larney Lane Grade Separation Project
Public Information Meeting
Tuesday, July 17,2012
Carnegie Forum
305 West Pine Street
Lodi, California
I
M
e
d
B
0
x
Display Boards
Projection
Screen
J
Projection
Screen
J11 -
A,_ _"A'_ )"
7 1 Page
./A
J11 -
A,_ _"A'_ )"
7 1 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
2.2: Displays and Exhibits
The informational display boards, exhibits and maps at the Public Information Meeting are
explained below. (Reduced copies of the informational display boards and graphics are included
in Appendix B.)
Station 1: Welcome Board and Sign -in Tables
A welcome board greeted attendees as they entered the meeting room. Attendees were asked to
sign in to maintain an attendance record and to ensure that all interested parties would be added
to the project mailing list. [See Appendix for the attendee list.] The Public Outreach
representative gave each attendee a print program with the logos of the City of Lodi, San Joaquin
Council of Governments (SJCOG), and Measure K. The print program welcomed attendees to
the public meeting, stated the evening's agenda, and provided the project purpose and project
description, funding, a project map, and information on how attendees could comment and stay
involved. The print program provided contact information for future questions, concerns, or
comments. The print program also included information on two pertinent upcoming meetings —a
Lodi City Council Shirtsleeve Session and a hearing before the Lodi City Council. [See
Appendix A.] Comment sheets provided space for comments and/or concerns and asked
attendees if they wished to be added to mailing lists for the projects. The Public Outreach
representative explained the format of the meeting and encouraged attendees to ask questions of
and make comments to the project team members who were present.
Station 2: Displays and Exhibits
Maps of the construction alternatives were displayed across the front of the City Council
chambers.
Station 3: Comment Station
A receptacle at the Welcome table was provided for comment sheets. One written comment sheet
was submitted during the Public Information Meeting. [See Appendix E.]
2.3: Personnel on Hand
The following personnel set up and conducted the meeting and were available to answer
questions from the public. Working at the direction of City of Lodi personnel, the persons in
charge of the meeting were Rob Himes, P.E., Principal, Mark Thomas & Company, Inc.; Phillip
Vulliet, P.E., Project Manager, Mark Thomas & Company, Inc.; and Judith Buethe, Judith
Buethe Communications.
2.3.1: City of Lodi Staff
Chris Boyer, P.E., Assistant Engineer
Wally Sandelin, P.E., Public Works Director
Charlie Swimley, City Engineer/Deputy Public Works Director
2.3.4: Consultants
Murk Thomas & Company, Inc.
Rob Himes, P.E., Principal
Phillip Vulliet, P.E., Project Manager
81 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Judith Buethe Communications
Judith Buethe, Owner
Loreen Huey, Administrative Assistant
2.3.5: Elected Officials and Other Agencies
Lodi City Council
Phil Katzakian
San Joaquin Council d Governments
Donald Mascardo
San Joaquin County
Jeffrey Levers, Public Works Department
91 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report.
Chapter 3: Presentation
At 6:20 p.m., after introductions and housekeeping remarks by Judith Buethe, Public Outreach
Coordinator, Rob Himes, Principal, Mark Thomas & Company, Inc. gave a PowerPoint
presentation that included the project development process, purpose and goals of the meeting,
existing conditions at the sight, the proposed project, project constraints alternatives —overand
under, alternatives being considered, a set of criteria for evaluating whether to build an underpass
or overhead structure, what experts say about underpasses vs. overhead structures, visual impacts
of the alternatives, cost, and the remaining project schedule. [See Appendix G for a copy of the
full PowerPoint presentation.]
Following is a list of the subsequent questions and comments by members of the audience.
PUBLIC QUESTIONS AND COMMENTS
1. What is theprojected number of lanes west d Hutchins Street?
2. Whyfour lanesfrom Hutchins Street to Lower Sacramento Road?
3. Could we cut trucks outfrom using the road?
4. Whatkind d separation do you anticipate building between the overpass andpedestrian
sidewalk?
5. Areyou concerned someone couldfall into the roadway?
6. Willsidewalks be built on both sides of the structure orjust one?
7. I'm still not understanding why there is no bypass road being considered with theAlternative
One overheadproposal.
8. Do you have any to -scale cross-section drawings of how big this thing isprojected to be?
9. Arguments for the overhead alternative because of cost advantages arepersuasive, butyour
diagrams are not to scale.
10. I would like more detail to get a better appreciation for what it will look like.
11. Who made the decision to go under when Kettleman was built?
12. On an overpass, how will water runoff be collected and sent toponds?
13. From digging to opening, how long will construction last?
14. How much of a shorter time if the whole road were to be closed?
a. 1.5 years.
15. Graffiti problems are everywhere. How accessible are the walls on the back side to allow
cleaning?
16. Do costs include access roads to the metal company?
17. What is the estimated traffic count on Maggio Circle?
18. Whatsort of roads do youproject building at the base of the embankmentfor maintenance
and safety?
19. How much area is on both sides of the railroad?
20. How can theproject keep campers or transientsfrom lingering under the structure?
[End of question -and -answer period]
101 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Chapter 4: Public Input
Public input was received in three ways: 1) written comments received at the Public Information
Meeting, 2) oral comments received by the project team staff members, and 3) questions,
comments, and concerns expressed during the question -and -answer session.
3.1: Written Comments Received at the Public Information Meeting
3.1.1: Listing of Comment Sheets and Correspondence Received at the Public Information
Meeting
Jack Dunn
2232 Newbury
Lodi, CA
(209) 334-6754
Jack.sheila@mac.com
Clear, consist, well run meeting.
A copy of the original written comment sheet received at the meeting is included in Appendix E.
111 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Chapter 5: Outcome of the Public Information Meeting
The overall feedback about the breadth, depth, and usefulness of the information provided at the
Public Information Meeting was very positive. Dominant concerns, questions, or comments
expressed by attendees were the following:
• Number of lanes planned for the grade separation structure.
• Safety
• Sidewalks
• Desire for to -scale cross-section drawings.
• Water runoff
• Length of construction; other construction impacts
• Maintenance; potential graffiti
• Access roads to Valley Iron Works
• Potential impacts on Maggio Circle
• Breadth of area directly impacted by the proposed structure
121Page
Meeting
�Ellila
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Appendices
For Your Calendar
7:00 a.m. -8:008.10.
Tuesday, July 24.2012
Sbirtsleeve Session
Lodi City council
Carnegie Form
7:00 p.m.
Wednesday August I, 2012
Public HearingduringCityCmmcil Meeting
Lodi city Council
Carnegie Fonuu
For More Information
Judith Buethe
Publicoutresch Coordinator
Harney Lane Grade Separation Project
P.O. Box 773. Stockton, CA 95201-0773
Hodine: (209)464-4350
Hottiae@buethecoinsum cations.corn
Mankywa for mterrdliM this ewnhig3
Public h1(unnmiar Meering.
N
ct
ProteMap w
N W E
4
F. Harney Lane E.Haroeylame
is
Project Background
Harney Lane is a two-lane, east -west rnban collector near the City of
L.odi's southern city limit. Harney Lace intersects the Union Pacific
Railroad MRR) approximately'/. mile west of State Rome 99. Trafc
on Harney Lane is expected to increase as the City continues to grow.
Keeping the existing at -grade railroad crossing m Haney Lane would
pun sigttiflcaut traDic congestion on Harney lane. the surrounding
intersections, and the State Route 9941aruey Lane Laterchange. The
City's General Llan includes a railroad grade separation at the UPRR
crossing.
Project Alternatives
Tvo types ofproject alternatives are being considered—m underpass
below the UPRR tracks and an overhead about the UPRR tracks. The
grade separation will ultimately have four laces.
Welcometo the
Public Information Meeting
Tuesday,luly 17,2012
600p.m.-730p.m.
Camegle Forum
305 West Pine Street, Lodi
VJW!�;�—ra�ti
Tonight'sAgenda
July 17.2012
6:00 p.m. - 6:30 p.m.
Open House—Exhibits slid Hefrealinents
6:30 li ra
Wekome, lanednclions, Agenda oreniew
Judith littetbe
A,6Jtc 0"W-1, Cawdnmtor
Protect overview
Philip Vulliet. P.E.. Project Manager
Afntk Th -'—A
QHNHoustCemmeals
Audieuce
Open House Cuntlnues Uu111 7:30 p.m.
131 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Comment Sheet
141 Page
Harney Lane
Grade
Separation
Project
Comment Sheet
Name (Please print):
Date:
Mailing address:
Resident, Business, Organization, etc.: _
Phone:
_ Email:_
Comments:
ProjectHothne: (209) 464-8707, ext. 101 or toll-free (877) 464-4350
Fanail: Hotliae@bttetheconmmnunications.com
Write: Public Outreach Coordinator
Harney Lane Grade Separation Project
P.O.Box 773
Stockton, CA 95201-0773
141 Page
Ln N
=- as
rb 3
N '
Grade
Project
Date: Tuesday, July 17,2012
Please Print Your Name Organization, if any Address, City and Zi E-mail Phone
3
m
Gl
m
CL
m
m
m
v
d
4
0
3
O
ep
n
v
C
A
7
O
3
d
O
CD
7
tD
O
0O
to
C
3
3
w
a
0
a
Harney Lane Grade Separation Project Public Information Meeting Summary Report
W�#z& to the
Public
Meeting
161 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Public Meeting Postcard Invitation
YouAre Cordially Invited to a
Publiclnformation Meeting
'I'nesday, July 77,2012
6:00 p.m. - 7:30 p.m.
CaniegieFotwn
305 West Pine Street, Lodi. Calif.
�y of to i,
/1 U`� O YEl SV,i
�lFOP
Project Background
Harneey Lane is a hvalene, east-aeslurban collectornear the CityofLodi's
southam city limit. Harney Lane intersects die UnionPacido Pailxtad (UPRR-)
approximately'/4milewestofStateRoute99. TrafconHrmeyLaneis
expected to incrilm as the C by eondmsea to grow. K"pW the existing
at•grade railroadcroWng on Harney Lane would cause significant traf8
congestion out Harney Lane. the surrounding intersections, andilie State Route
9941amey Lane tutmtangs. The City's Nueva] Plea imlu*sa railroad grade
separation at the UPRRcrossing.
Project Attainaftes
TWotypes ofprojectalternativesarebeing considered,antmlMassbea wthe
UPRR Tracks and an overhead'above the UPRR tracks. Tlie grade separation
will tiitiinately have four lanes.
What Will Happen edits Pehile tnt&rmrtlon Most!"$?
At the public meeting on July 17, the project mauager for the design team
will present the project alternatives and the estimated costs of each alternative
being considered. The Project Manager will also discuss how the construction
may be staged to have the least hapact on surrounding properties, businesses.
and the traveling public.
biswbers of the public wi I I have an opportunity to ask gtmfioits and make
coULMW3 ontheproject.
Public Outreach Coordinator
Harney bane Grate Separation Project
P.O. Box 773
Stockton. CA 95201-077
For Your Calendar
At the Shlrraleew Sessionon July 24.2012, the Lodi City Council will review
the alternatives and theresults of tiepubhc information IiLeeting and receive
thedesigu team's reconunteuded alternative.
At die City Council meeting on August I, 20112, the City Council will review
the aterns Lives, receive public comments, and select the altetuadye for tie
PWI-t.
For More lnformatlon
Call the Hotline at (209) 464.4350, Ext. 101, ore-ruail
Hotline@buethecomartmications.com. You are also welcome to mail your
written comments and inquiries about the project to Public Outreach
Coordinator, Harney Lane Specific Plan, P.O. Box 773. Stockton, CA
95201-0773.
Project Map
{r * a
r e
etw.a� r.tmmat+•
Project area
of
(
171 Page
Published in
the Lodi
News -Sentinel
on Thursday,
July5,2012
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Tuesday, July 17,2012
6:00 p.m. - 7:30 p.m.
Carnegie Forum
305 West Pine Street
Lodi, California
Project Background
Harney Lane is a two-lane, Cast-westurban collector near the City of Lodi's southern city
limit. Harney Lane intersects the Union Pacific Railroad (UPRR) approximately % mile west
of State Route 99. Traffic on Harney Lane is expected to increase as the City continues to
grow. Keeping the existing at -grade railroad crossing on Harney Lane would cause significant
traffic congestion on Harney Lane, the surrounding intersections, and the State Route
99/Harney Lane Interchange. The City's General Plan includes a railroad grade separation at
the UPRR crossing.
Project Alternatives
Two types of project alternatives are being considered—an underpass below the UPRR Tracks
and an overhead above the UPRR tracks. The grade separation will ultimately have four
lanes.
What Will Happen at the Public Information Meeting?
At the public meeting on July 17,2012, the project manager for the design team will present
the project alternatives and the estimated costs of each alternative being considered. The
Project Manager will also discuss how the construction may be staged to have the least
impact on surrounding properties, businesses, and the traveling public.
Members of the public will have an opportunity to ask questions and make comments on the
project.
For Your Calendar
At a Shirtsleeve Session on July 24, 2012, the Lodi City Council will review the
alternatives and the results of the public information inecti ng and receive the design team's
preferred alternative.
At the City Council meeting on August 1,2012, the City Council will review the alternatives,
receive public comments, and select the alternative for the project.
For More Information
Call the Hotline at (209) 464-4350, Ext. 101, or e -snail HotlineCa bttethecommttnicatiotis.coni.
You are also welcome to mail your written comments and inquiries about the project to Public
Outreach Coordinator, Harney Lane Grade Separation Project, RO. Box 773, Stockton, CA
95201-0773.
�.t OF t
V� X11 0� Harney lane M'iasux,F
FOR
181 Page
Press
Release
Harney Lane Grade Separation Project Public Information Meeting Summary Report
CONTACT: Judith Buethe FOR IMMEDIATE RELEASE:
(209) 464-8707, Ext. 101 July 5,2012
PUBLIC INFORMATION MEETING TO BE HELD ON JULY 17
FOR HARNEY LANE GRADE SEPARATION PROJECT
(Lodi, CaH)-4Aenbm of the public are invited to a public information meeting on Tuesday,
July 17,2012, to learn about and comment on the Harney Lane Grade Separation Project. The
meeting will be held from 6:00 p.m. — 7:30 p.m. at the Carnegie Forum, 305 West Pine Street,
Lodi, California.
At the public information meeting on July 17, the project manager for the design team will
present the project alternatives and the estimated costs of each alternative being considered. The
project manager will also discuss how the construction may be staged to have the least impact on
surrounding properties, businesses, and the traveling public. Members of the public will have an
opportunity to ask questions and make comments on the project.
Project Background and Alternatives
Harney Lane is a two-lane, east -west urban collector near the City of Lodi's southern city limit.
Harney Lane intersects the Union Pacific Railroad (UPRR) approximately '/a mile west of State
Route 99. Traffic on Harney Lane is expected to increase as the City continues to grow. Keeping
the existing at -grade railroad crossing on Harney Lane would cause significant traffic congestion
on Harney Lane, the surrounding intersections, and the State Route 99/Harney Lane Interchange.
The City's General Plan includes a railroad grade separation at the UPRR crossing.
Two types of project alternatives are being considered—an underpass below the UPRR tracks
and an overhead above the UPRR tracks. The grade separation will ultimately have four lanes.
For Calendars
At a Shirtsleeve Session at 7:00 a.m. on July 24,2012, the Lodi City Council will review the
project alternatives and the results of the public information meeting and receive the design
team's preferred alternative.
At the City Council meeting on August 1, 2012, the City Council will review the alternatives,
receive public comments, and select the alternative for the project.
For More Information
Hotline: (209) 464-4350, Ext. 101
Email: Hotlimftethecanmmications . can
191 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Appendix D: Photographs at the Meeting
201 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
211 Page
Harney Lane Grade Separation Project Public Information Meeting Summary Report
E
Sep
Comment Sheet
dame (Please print): Date: 7-17
1
Bailing address:
tesident, Business, Organization, etc.:
'hone: —4& .1c 'F Email: .t a �-�f .3�t e,i �a @ Wiac . cow
:omments: �Qa-akt e vx,pa,o� � ^•('
Project Hotline: (209) 464-8707, ext. 101 or toll-free (877) 464-4350
Email: Hotline@buethecommmunications.com
Write: Public Outreach Coordinator
Harney Lane Grade Separation Project
P.O. Box 773
Stockton, CA 95201-0773
221 Page
Date: Tuesday, July 17, 2012
Your Nante Organization, ff any Address, City and Zip Email Phone
�A� a �oc
•Z 473 e -
Q -Sc
-
.
Glv\ p\vary.
`sZA /\a-:
N c-/-
okva,�l,c�—.
'�p4-8\s-30N?'
�X/ .
(OG
-�Q &C1444
oF1 lrc.-. W4,
/Z E ,S Cx
va s.0
d�
%012 t/��S�i
�,N
KV - ala i
Com'��
S'�ScLG� �2li(r
U w�1/�sc�vG�lzs ^t�
t6�✓j �O1/N
tv
/�.0 5 t d,'iiy/
osG. �
G' a/,
,6yo�•r��a7/t�ei:n,�t3', cotes
?i 'i °i^�avZg
kkLo IAOAN GWt_S
Z
Tri n^I L F -r
1 a 4 °t c- n/- hol.<.sT' La►v�
J ��'°� j P m��� y,
3 3 Y- 3 D
naakyaajoramwd&& Gradw wrma%bAvicla.
CQ
3.
Harnev Line
Date: Tuesday, July 17, 2012
Please Print Your Name
Organization, if —y
Address, City and Zi
Email
Phone
i�fm ?IleA,
239�u/lie G'r. lv�i 51�
e�6�9s2yaC.4--nom�lm
31�Hd'J46
c.4Q+LA
aS66 Ila IO Cr,d'L6d,
PC �et4/; (-S,Jfe, tj ef
/,p
Debm
MLAI)oUr4 C,tc.te
rcL e3yG cu>tr.�+
(03 923
48
GRkC� CDST✓9
/3)(ov N• V ST �,i9N�
AOL) I 95RY 12
�co�ds e lo�ihp�`�
co ✓^
�TQ3'oZS5- 2-
97�
3 -)- A&O ufy C/'4-
,'4,L o I t' Ca �s ay v
Z_
3 3 -lP7s
3�FF1��Y G�vERs
SAI. saA�rc�ru co.
Jle..�evs �Js�cay.a�
q�3-7fo31
6� 1 vtz
,Z�S i`?NL 60?Al f' (0I<(C(
2LiZCAAV -312Qli11'
,- -3 ;7 9
� 3
d
Tkankvoafor aaeadre. Grad= vorsaasWmela.
rbz
01 a
a
U4 0
rD 4
N
V1
Date: Tuesday, July 17, 2012
Please Print Yon Name Oxgani nation, if an Address,and Zi Email
Phone
%/,? X r15 /�� P.r
C 0, L
Zo-eesn
0 6 W"W"s
/yl % C, _
� rnankgorjoraaeneutg. GmdaspNw ea&Iwcic
OC
Harney Lane Grade Separation Project Public Information Meeting Summary Report
Appendix G: PowerPoint Presentation
261 Page
HARNEY LANEIUPRR GRADE SEPARATION
PROJECT
City Council Presentation
August 1,, 2012
nf - w"Wo4A
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
0fr.Impg IIKe
v
i
. T
��•� J
it
HARN
EY LANE
�
0fr.Impg IIKe
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Jroiect D
•1's
wre
FeasibilityEnvironmental
StudyM Studies Design Construction
Harnev Lane/UPRR Grade Separation — Council Meeting Auizust 1, 2012
Jroiect D
•1's
Uwe
FeasibilityEnvironmental
StudyM Studies Design Construction
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Feasibility
Study
Public
Meeting
Jevelor
Environmental
Studies
wre
Design
Construction
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Jevelor
Feasibility Environmental
Study Studies
Public City Council
Meeting
:1 Shirtsleeve
Session
wre
Design
Construction
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
61
wre
Feasibility Environmental
Study Studies Design
Public City Council City Council
Meeting
:1 Shirtsleeve:1 Selects
Session Alternative
Construction
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
61
wre
Feasibility Environmental
Design Construction
Study Studies
Public City Council City Council Finalize
Meeting
:1 Shirtsleeve:1 Selects :1Environmental
Session Alternative Process
Existing Conditions
• At Grade Crossing w/UPRR Tracks
• 161000 Vehicles (Including 95 Buses) Per Day
• 39 Trains Per Day
• Almost 2 Hours Delay
• Train Blows Whistle Approaching Crossing
• No Pedestrian or Bike Facilities
Proposed Project
• Approved in the City's General Plan and Discussed in
the Harney Lane Specific Plan
• Four Lane Expressway
• With Grade Separation — No Whistle Blowing
• Free -Flowing Traffic
• Improved Emergency Response
• Remove Conflict (Safer)
• Accommodates Pedestrians and Bicycles
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Prnipct C
• 1 X71-iRliy�.�+•_ If 1
I I - j --
LL I gERIC
C
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Proipct C
0 reTa "'I'm 0
qk _' s r �.
l , g
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Prnipct C
•
41
qk _' s rP�
�.
l � g
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Project Ca
A 4 ifi �-
LL
IL
i
� e
l �
r
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Prnipct C
.jj A ifi 1 1f j ^s-
LL
0�1 .. �W4
�k
i
l , g
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Prnipct C
0
LL
it
IL
WV
Iq
l � g
` I -.f �. •
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
0
9
4 �z
1'Allr
�k
� I
' e
l � g
. I _
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
0
0,
V
Grade Separations
Overhead
— Roadway OVER
railroad tracks
Alternatives Considered
Overhead Alternatives
Alternative 1
Alternative 2
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
0 0 r.", .
"Oj 'i WIM I
0
W_ 1k .i
t ILL
iii s: r zz.
•I n' )!i Ali! -.' ... - _ � - W -��-� — -= -- — — — —_
Harnev Lane/UPRR Grade Separation — Council Meeting August 1, 2012
0ITt0 11 - . • Ki
=p �. 01-
AML
��,, "_i� • r. I� �r 11 �� ''�. . _"_ - '•.�;, ', �� :�
I - -
��
�W -
Harney Lane/UPRR Grade Separation — Council Meeting August 1, 2012
Y Z, FF
`Qe
46.1
Alternatives Considered
Underpass Alternatives
Alternative 3
Alternative 4
CITY OF LODI - HARNEY LANEIUPRR
EXHIBIT _ ALTERNATIVE 3
UNDERPASS (RETAINING WALLS)
no■ari ixoaer r rorrraxr, ixr.
Underpass Alternative
(Retaining Walls)
WAX
CITY OF LODI - HARNEY LANEIUPRR
EXHIBIT _ ALTERNATIVE 4
UNDERPASS (CUT SLOPSS)
64M not
■arr ixorler r rorrraxr, ixr.
Underpass Alternative
(Cut Slope)
cw SLOPES
Wim.
""Throw Away" Costs
Construction Duration
UPRR Involvement
R/W Acquisition
Construction Cost
Long -Term Maintenance
Utility Impacts
Noise Impacts
Visual Impacts
0
0
0
SAME +/-
0
0
0
v
v
SAME +/-
0
Best
r
Mitigated
Worst
What Experts Say
(From their Standards)
California Department of Transportation
"Railroads should be carried over (roadways) only when there
is no other reasonable alternative':
(HDM 208.9)
Union Pacific Railroad
"The most effective method of reducing interference to
Railroad operations for construction of a Grade Separation
Projects is to use an (Overcrossing) and avoid an
(Undercrossing)':
(UPRR Guide 4.1)
""Throw Away" Costs
Construction Duration
UPRR Involvement
R/W Acquisition
Construction Cost
Long -Term Maintenance
Utility Impacts
Noise Impacts
Visual Impacts
0
0
0
SAME
O
O
v
v
SAME +/-
0
Best
r
Mitigated
Worst
T
Noise Impacts
I
Overhead
Noise Impacts
�pp�� SovND WALT,
}
�oISE
Underpass
Harnev Lane/UPRR Grade Separation — Council Meeting August 1. 2012
Harnev Lane/UPRR Grade Separation — Council Meetin.R August 1. 2012
r
i r .mum. i
Harnev Lane/UPRR Grade Separation — Council Meeting August 1. 2012
.,F ••,:,•�`:-•--.... `rte--�= r _. -.. �1..
Dvprhpad
Visual Impacts
70
EXISTING
STRUCTURE\ B'SOUNDWALL
RAN
C=9TING FG
M
FENCE
17+46.59
LOCATION 1
13
RRYCIPLtE--
>; MULBEI
�44
75"
2
HARNEYLKNE
;v -v Jp
-31 7
rk
l�
Visual Impacts
qs`
EXISTING
STZU8GTURE
RAN
EX'6TINO
-ED r FENCE
W SOUNDWALL
2d
I---- . - - - _y - -
19+24.12
LOCATION 2
E3 7L
MULBERRY .7*
6 Tr
HARNEY UNE
N.
7-�
q
Visual Impacts
I
m m Q d I E7a8TfNG
FENCE rF. 06
20+61.23
LOCATION 3
• I +it h� � .. �; ter_ . -
y MULBERRY GiF3CLE _ -'�►R 'r
• •r,'cJ�� " jr/L, -�Y f' 3 . i� • ��" .� . 'dY � �'- i•? 4i � _� � ' y�''r - •Y�•T5 . ".� _ i _., -
r} �� 9'Y u5. _� ��_ . i•y''.i•- '4- �,+i'� .9f �.� � .}�i .� � _ _ , i.:dS`•y!� .�i �N
_�i.L A --.+y, t_ '.1 ti-' 'Sd _ _ �i.-'.. "i• .7I •,'Y.� ..
Visual Impacts
EXISTING
STRUCTU RNV
EXIS-nNG
ED FENCE
22+50.76
LOCATION 4
13
tAULBEIRRY G ZtE
7511�
C2
Tr
T7
FHMARNEY E
-7
v 77 -
Y
Trill, - -,
1m;
Harnev Lane/UPRR Grade Separation — Council Meetin.R August 1, 2012
11MI�1lI��IQI�1�!l���
��� �r .�::o���l� q[t�����lll11�►
f siT''�' ��11111IIIIIIlii11111111�1['lillll!'``-�
������`:����,� ��• 9.��Ililllllillllllli11111Ililli�;i�`��I611116i; � �;
��®�.�'�° ,A��: �► . ;�1l1i11111i 1111111111111�11l�IIIII!i' � �f lillll��� �� �`
��'ll�il111111illlli��i.":.:�li�lllllllllllllllllllllilllllllll�\�l!1!111
�®iIII���iQ��lllllllll�ifl�� /•: �lilllllilll:111lllllllllill�ill���!!I�R.'��I'1�I��1��.�r'
�;� �� Illllllillllll#IIIIIIMIIii�i:..�� ilillllll11111l1111111111111111i1�i����'' `'_
���l1119��
1111111111111iallll�il��l�I �1i1� 11�1111111�111111111111�1111� "I�_1��1l
a vvaii nein
Overhead
Hiiernauve gl
$18,800,000
Alternative nZ
$26,500,000
Underpass
Alternative #3
$28,500,000
i
Alternative #4
$27,700,000
Remaining Project Schedule
• Council Decision on Preferred Alternative
(August 1, 2012)
• Environmental Studies Finalized
(November 2012)
• Right -of -Way Appraisals &Acquisitions
(January 2013 -October 2013)
• Engineering &Permitting Completed
(December 2013)
0 Construction Start (2014)
Any Questions?
Bridge Abutment
al
r ,�