HomeMy WebLinkAboutAgenda Report - July 20, 1988 (62)COUNCIL COMMUNICATION TO: City Council FROM: City Manager, MEETING DATE: July 20, 1988 AGENDA TITLE: Review of Traffic Signal Installation at Highway 12 and Lower Sacramento Road - Discussion and Appropriate Action. RECOMMENDED ACTION: That the City Council approve City participation in the Lower Sacramento Road/Highway 12 signal project and authorize the City Manager to execute a cost-sharing agreement with San Joaquin County. BACKGROUND ll41IRMAHON San Joaquin County is the lead agency in the installation of a traffic signal at Highway 12 and Lower Sacramento Road. Caltrans and the County are splitting the $120,000 cost of the signal 50/50. The work is scheduled for fa71 1988 and includes left turn lanes with separate signal phases. Early in June, the County sent the City a letter regarding operational improvements on Lower Sacramento Road. They asked that the City contribute $64,000 to the project for right turn lanes and a pavement overlay (see attached June 1 letter). Staff responded, indicating vie were reluctant to take the request to the Council for a number of reasons (see attached June 15 letter). W were also concerned about the adequacy of the design and asked for more information. The County responded on June 30 (see attached letter), indicating they were proceeding with the project as designed, without the additional right turn lanes, City staff ran some rough level of service calculations based on available traffic counts. They indicate there will be a noticeable difference in the operation of the intersection with and without the right turn lanes (level of Service C versus D). W called the County and indicated v& _would take a recommendation to the Council for City participation in the right turn lanes without the overlay if they would provide a separate estimate.. They have done so and their rough estimate is $50,000. Staff still has some reluctance about participating in this project in this manner, but vie feel more strongly that it would be a disservice _to the- citizens of Lodi not to make these additional improvements. .Therefore; it'.is recommended that the Council approve City participation and au'thurize the APPROVED: FILE NO OMAS A. PETERSON, CUx Manager CSIGNAL/TXTW.02M ; July 12, 1988 City Council July 20, 1988 Page 2 City :tanager to execute a cost-sharing agreement with San Joaquin County. The project would then be included in the 1988/89 Capital Improvement Program. Jac L. Ronsko ubli Works Director JLR/RCP/ma Attachments SUBJECT: STATE HIGHWAY 12 AND LOWER SACRAMENTO ROAD TRAFFIC SIGNALS Dear Mr. Ronsko: The State of California and San Joaquin County have executed a Cooperative Agreement for the construction of a signal system with left turn phasing for the above referenced intersection. San Joaquin County has been designated as the lead agency for the design and construction of the facilities. Design of the signal system is essentially complete and is now being reviewed by Caltrans. The roadway improvements for the Lower Sacramento Road approaches are now being designed by a�Q1��N Public Works staff. C• `.�• ": •' COUNTY OF SAN JOAQUIN EUGENE DELUCCHI DEPARTMENT OF PUBLIC WORKS `"•`"D`ry'Tr'•""'o" . p O- BOX 1610 - 1810 E HAZELTON AVENUE THOMAS R FLINN STOCKTON. CALIFORNIA �4LjFOj�t��4 95201 D[rvTr wR[crDR (208/ 468-3000 MANUEL LOPEZ D[P1iTY OtR[CTOR HENRY M. HIRATA from within the City of Lodi, we are inquiring if the City of June I, 1988�� ,.• Mr. Jack L. Ronsko Director of Public P;orks City Cit of Lodi 221 West Pine Street ' • X�} �'' \; '�' �' �' I _ L _ 1 Lodi, California 95241 r clvc ..;:)=.:.RT..1VXT SUBJECT: STATE HIGHWAY 12 AND LOWER SACRAMENTO ROAD TRAFFIC SIGNALS Dear Mr. Ronsko: The State of California and San Joaquin County have executed a Cooperative Agreement for the construction of a signal system with left turn phasing for the above referenced intersection. San Joaquin County has been designated as the lead agency for the design and construction of the facilities. Design of the signal system is essentially complete and is now being reviewed by Caltrans. The roadway improvements for the Lower Sacramento Road approaches are now being designed by Public Works staff. Due to budget constraints, the roadway improvements on the Lower - Sacramento Road approaches will be limited to the widening required to accommodate a left turn lane, for a total estimated cost of $120,000.00 (see Exhibit "A"). - As this intersection is primarily impacted by traffic generated . from within the City of Lodi, we are inquiring if the City of Lodi would participate in financing additional operaL 1j- improvements to the intersection including right turn lanes and`a " structural overlay on Lower Sacramento Road (see Exhibit.. KB-) The estimated costs for the alternate with right turn lanes is. � $184,00.0_00 You: prompt reply is necessary as we are currently designing ;the with intentions to advertise the nr e -i :,, .. - - July,' 1988. Thank you for.your consideration of this matter. Very tr yours,: s �Y T.:.. R— Deputy. Director/Engineering '41 { TRF : Cit cr . F 8E402DECl >' # ` � l k CITY COUNCIL ,AMES W. PINKERTON. ir_. .savor CITY OF L O D I JOHN R. (Randy) SNIDER Mayor Pro Tempore CM HALL, 221 WEST PINE STREET DAVID M. HINCHMAN CALL BOX 3006 EVELYN M. OLSON LODI, CALIFORNIA 95241-1910 FRED &IL REID (209) 334-5634 TELECOPIER _(209)333-6:95 June 15, 1988 San Joaquin County Public Works Department Attention: Tom Flinn P.O. Sox 1810 Stockton, CA 95201 THOMAS A. PETERSON , City Manager ALICE M. REIMCHE City CIerk 808 McNATT City Attorney Subject: State Highway 12 and Lower Sacramento Road Traffic Signals Thank you for updating us on the status of the subject project. We are glad to see the project progressing. San Joaquin County Public Works Department June 15, i988 Page 2 Southeast corner the County Board of Zoning Adjustments conditionally approved the development (0-73-18). We do not have a record of the conditions, but it has been our experience that they typically include some type of deferred improvement requirement. The owners may be willing to instal: some of the improvements now in order to save relocation costs 1 ater. Again, thank you for keeping us informed on this project. If you have any questions, please contact Richard Prima at your convenience. Richard C. Prima, Jq Chief Civil Engineer : RCP/ly cc: City Manager ).• fit,. G Ct,�C`FOR�`P HENRY M. HIRATA DIRECTOR June 30, 1988 COUNTY OF SAN JOAQUIN DEPARTMENT OF PUBLIC WORKS P. O. BOX 1810 — 1810 E. MAZELTON AVENUE STOCKTON. CALtFORNM 95201 (2091 468-3000 Richard Prima Chief Civil Engineer City of Lodi 221 West Pine Street Lcdi, California 95241 SUBJECT: LOWER SACRAMENTO ROAD AND STATE HIGHWAY 12 TRAFFIC SIGNAL Dear tdr. . Prima: EUGENE DELUCCWI C.ler DePUTY DIRECTOR THOMAS R. FLINN DEPUTY DIRECTOR MANUEL LOPEZ DEPUTY DIRECTOR "E"'EIVED JUL V 5 1988 CITY OF LODI PUBLIC WORKS DEPARTMENT Mr. Richard Prima _2_ June 30, 1988 Our tentative schedule is to advertise this project in August, 1988, with construction to commence the following month. Thank you for your input and consideration of this matter. Very tru ours, l. R. eputy Director/Engineering TRF =MAS _to F 8F378DET1