• PUBLIC WORKS DEPARTMENT
COUNCIL COMM11NICATION F
Project Data
Oriqinally Budgeted: 1987/88
TO: City Council Budgeted Fund: Wastewater Capital
Outlay (17.2)
FROM: City Manager Amount Budgeted: $175,000
Total Project Estimate: $175,000
MEETING DATE: May 4, I988 Bid Opening Date: 10/ 14/87
AGENDA TITLE: Accept Improvements Under White Slough Water Pollution
Control Facility Aeration System Diffuser Retrofit 1987
Contract
RECOMMENDED ACTUN: That the City Council accept the improvements for the
"Aeration System Diffuser Retrofit 1987", and direct the Public Works
Director to file a Notice of Completion with the County Recorder's office.
BACKGROUND MURMAIION: The contract was awarded to Kaweah Construction of
Visalia on October 21, 1987 in the amount of $76,500. The contract has been
completed in substantial conformance with the plans and specifications
approved by the City Council.
The contract ombletion date was March 4, 1988 and the actual completion date
The final contract price was $765690.80.
ack.L Ronsko
P 1tit Rdmkbi rector
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED:
FILE NO.
..as.nwtm�sW...'.,...,•.....•,••- �.._:__.._-..._..,a, ,�w;,.. �ra:.aeaaxv�...,<n-asvYx�vr, aa:.a.:,•••...:m..w.aswz�-^-_. �.••.•••.w.�n.,.m,,eAawwn:.s�:ee,..r�,�.emc+sme„<> � :.uy.,enm...