Project Data
T0: City Council
Originally Budgeted: 1987/88
FROM : City Manager Budgeted Fund: Water Capital Outlay
Final Project Cost: Phase I - $38,000
MEETING DATE: May 4, 1988
AGENDA TITLE: Accept Improvements Under Building Detrol i tions, 125 North
Stockton Street, 122 North Main Street, and 208 East Locust
Street, Contract
RECOMMENDED ACTION: That the City Council accept the improvements for the
'Building Demolitions, 125 N. Stockton Street, 122 N. Main Street and
208 E. Locust Street" contract and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION The contract was awarded to Sterling P. Holloway
of Auburn on February 17, 1988, in the amount of $32,916.00. The contract
has been completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was May 16, 1988, and the actual completion date
was April 15, 1988. The final contract price was $35,853.50. The difference
between the contract amount and the final contract price is nainly due to
abandonment of an additional unrecorded well, removal of additional concrete,
and salvaging additional block of historical value.
ck CRonsko
blit Works Director