HomeMy WebLinkAboutAgenda Report - April 19, 1989 (64)CITY OF LODI
PUBLIC WORKS DEPARTMENT
TO: City Council
FROM: City Manager
MEETING DATE: April 19, 1989
COUNCIL COMMUNICATION
Originally Budgeted:
Budgeted Fund:
Amount Budgeted:
Final Project Cost:
1988-89
10
$18,665
$15,047
AGENDA TITLE: Accept Improvements Under Lane Line Painting Various '
Streets, 1988, Contract and Direct the Public Works __.,>_.'•._.
Director to File a Notice of Completion with the County
Recorder's Office
RECOMMENDED A .TJ,That the City Council accept the improvements fob
"Lane Line Painting, Various Streets, 1988," and direct the Public
Works Director to file a Notice of Completion with the County
Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Central Striping Y ,
Service, Inc., Rancho Cordova; on December 21, 1988, in the amount of g
$14,990.20. The contract has been completed in substantial
conformance with the plans and specifications approved by the :City
Council.
..... ...�
The contract completion date was January 29, 1989, and the actual }
completion date was March 25, 1989. The delay in completing the j.
project was due to the City placing a "Temporary Suspension of Work"
until the weather was more conducive to the application of paint on f '
traffic stripes. The final contract price was $15,047.20. The t -
difference between the contract amount and the final contract price is
mainly due to exact measurements taken by the contractor of all lane
lines painted
j
(Jack L. Ronsko
ublic Works Director
Y j
:pa
cc: Purchasing Officer
Street Superintendent
APPROVED: FILE NO.
THOMAS A. PETERSON, City Mana er
50489.01