HomeMy WebLinkAboutAgenda Report - April 18, 2012 C-06AGENDA ITEM C-06
CITY OF LODI
,. COUNCIL COMMUNICATION
Im
AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Contract for Roget Park
Improvements, 2229 Tienda Drive, with Hemington Landscape Services, of
Cameron Park ($543,207.50) and Appropriating Funds ($600,000)
MEETING DATE: April 18, 2012
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution authorizing City Managerto execute contract for
Roget Park Improvements, 2229 Tienda Drive, with Hemington
Landscape Services, of Cameron Park, in the amount of
$543,207.50 and appropriating funds in the amount of $600,000.
BACKGROUND INFORMATION: This project consists of developing four and one-half acres of park
land. The existing land will be re -graded and landscaped to tie into
the design concept of the proposed Eden Housing — Senior Housing
Project adjacent to the park property. Park development work shall include the installation of new
concrete walkways, bocce courts, horseshoe pits, game tables, security lighting, park benches, trash
receptacles, par -course equipment, park sign, five -horsepower variable frequency drive irrigation booster
pump, automatic irrigation system, hydro -seeded turf, native planting materials, underground utilities and
other incidental and related work.
Specifications for this project were approved on December 2 , 2011. The City received the following
14 bids for this project on April 4, 2012.
Bidder
Location
Bid
Engineer's Estimate
$642,547.60
Hemington Landscape Services
Cameron Park
$543,207.50"
WABO Landscape
Hercules
$543,852.00
Stan Construction
San Bruno
$547,366.75`
J.M. Slover
Placerville
$568,197.14
A.M. Stephens Construction
Lodi
$598,312.90
Saenz Landscape
Rancho Cordova
$601,202.46*
Stockbridge
Clovis
$613,767.90*
B.0 Construction
Ceres
$636,133.41*
Andrew L. Lee, Inc.
Lodi
$662,571.00
Dominguez Landscape
Sacramento
$667,152.58*
Abide Builders
Vacaville
$669,352.90
Diede Construction
Woodbridge
$684,783.30
Vinciguerra Construction
Jackson
$687,450.17*
Hobbs Construction
Fresno
$696,889.10
*Corrected Total
Adopt Resolution Authorizing City Managerto Execute Contractfor Roget Park Improvements, 2229
Tienda Drive, with Herrington Landscape Services, of Cameron Park ($543,207.50) and Appropriating
Funds ($600,000)
April 18, 2012
Page 2
Staff recommends the appropriation of $600,000 for the construction contract, staff time and
contingencies.
FISCAL IMPACT: There is no direct impact to the Parks and Recreation Department budget for
the park development improvements at Roget Park. Funds being used are
from the sale of the Tienda Drive property for the Senor Housing Project.
FUNDING AVAILABLE:
4a1'e--'2 1:2�
F. Wally S&fdelin
PublicWorks Director
FWS/pmf
Requested Appropriation:
General Fund Capital (1211): $555.000
Park Impact Fee1( 217): $45,000
NE5-�
Jordan A ers
DeputyCity Manager/Internal Services Director
4W
J
In _rim P; rks, Recreation& Cultural Services Director
K:\WP\PROJECTS\PARKS\Roget\Roget Park Improvements\CAward BlueSheet.doe 411812012
1. AA#
2. JV#
Deputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
FUND # BUS. UNIT # ACCOUNT # ACCOUNT TITLE
AMOUNT
A.
SOURCE OF
FINANCING
1211 3205 Unreserved Fund Balance
$ 555,00 .00
1217 3205 Fund Balance
$ 45 000.00
B.
1211 1211042 1825.2400 Ro et Park
$ 555,000.00
USEOF
1217 1217743 1825.2400 Ro et Park
$ 45,000.00
FINANCING
Please provide a description of the project, the total cost of the project, as well asjustification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Award contract for Roget Park Improvements project. Funds being used for this project are coming from the sale of Tienda Drive
(senior housing project). Revenue from the sale were received last fiscal year.
If Council has authorized the appropriation adjustment, complete the following:
Meeting Date:Res No: Attach copy of resolution to this form.
Department Head Signature:
Deputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2012-
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
CONTRACT AND AUTHORIZING THE CITY MANAGER TO
EXECUTE CONTRACT FOR ROGET PARK IMPROVEMENTS,
2229 TIENDA DRIVE, AND FURTHER APPROPRIATING FUNDS
TTTTTf-f i TTT. i i i i i ii7 • TTTTTi i i i. i i i i i i i i �i i rTrrr�����1'7��TTTT TTTTTr rr���
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on April 4, 2012, at 11:00 a.m.,
for Roget Park Improvements, 2229 Tienda Drive, described in the plans and specifications
therefore approved by the City Council on December 21, 2011; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Bid
Hemington Landscape Services
$
543,207.50*
WABO Landscape
$
543,852.00
Stan Construction
$
547,366.75*
J.M. Slover
$
568,197.14
A.M. Stephens Construction
$
598,312.90
Saenz Landscape
$
601,202.46*
Stockbridge
$
613,767.90*
B.0 Construction
$
636,133.41 *
Andrew L. Lee, Inc.
$
662,571.00
Dominguez Landscape
$
667,152.58*
Abide Builders
$
669,352.90
Diede Construction
$
684,783.30
Vinciguerra Construction
$
687,450.17*
Hobbs Construction
$
696,889.10
*Corrected Total
WHEREAS, staff recommends awarding the contract for Roget Park Improvements,
2229 Tienda Drive, to the low bidder, Hemington Landscape Services, of Cameron Park,
California, in the amount of $543,207.50.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for Roget Park Improvements, 2229 Tienda Drive, to the low bidder, Hemington
Landscape Services, of Cameron Park, California, in the amount of $543,207.50; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract; and
BE IT FURTHER RESOLVED that funds in the amount of $600,000 be appropriated
from General Fund Capital and Park Impact Fee Fund for this project.
Dated: April 18, 2012
hereby certify that Resolution No. 2012- was passed and adopted by the City
Council of the City of Lodi in a regular meeting held April 18, 2012, by the following vote:
AYES: COUNCILMEMBERS—
NOES: COUNCILMEMBERS—
ABSENT: COUNCIL MEMBERS —
ABSTAIN: COUNCIL MEMBERS —
RANDIJOHL
City Clerk
2012-
AGENDA ITEM C010
CITY OF LODI
,. COUNCIL COMMUNICATION
AGENDA TITLE: Adopt Resolution Authorizing City Managerto Execute Contractfor Roget Park
Improvements, 2229 Tienda Drive, with Hemington Landscape Services, of
Cameron Park ($543,207.50) and Appropriating Funds ($600,000)
MEETING DATE: April 18, 2012
PREPARED BY: PublicWorks Director
RECOMMENDED ACTION: Adopt resolution authorizing City Managerto execute contractfor
Roget Park Improvements, 2229 Tienda Drive, with Hemington
Landscape Services, of Cameron Park, in the amount of
$543,207.50 and appropriating funds in the amount of $600,000.
BACKGROUND INFORMATION: This project consists of developing four and one-half acres of park
land. The existing land will be re -graded and landscaped to tie into
the design concept of the proposed Eden Housing — Senior Housing
Project adjacent to the park property. Park development work shall include the installation of new
concrete walkways, bocce courts, horseshoe pits, game tables, security lighting, park benches, trash
receptacles, par -course equipment, park sign, five -horsepower variable frequency drive irrigation booster
pump, automatic irrigation system, hydro -seeded turf, native planting materials, underground utilities and
other incidental and related work.
Specificationsfor this project were approved on December21, 2011. The City received the following
14 bids for this project on April 4, 2012.
Bidder
Location
Bid
Engineer's Estimate
$642,547.60
Hernington Landscape Services
Cameron Park
$543,207.50*
WABO Landscape
Hercules
$543,852.00
Stan Construction
San Bruno
$547,366.75*
J.M. Slover
Placerville
$568,197.14
A.M. Stephens Construction
Lodi
$598,312.90
Saenz Landscape
Rancho Cordova
$601,202.46*
Stockbridge
Clovis
$6 13,767.90*
B.0 Construction
Ceres
$636,133.41
Andrew L. Lee, Inc.
Lodi
$662,571.00
Dominguez Landscape
Sacramento
$667,152.58*
Abide Builders
Vacaville
$669,352.90
Diede Construction
Woodbridge
$684,783.30
Vinciguerra Construction
Jackson
$687,450.17*
Hobbs Construction
Fresno
$696,889.10
*Corrected Total
APPROVED:
Ron radt Bartlam, City Manager
K:\WP\PROJECTS\PARKS\Roget\Roget Park Improvements\CAward.doc 4/5/2012
Adopt Resolution Authorizing City Manager to Execute Contract for Roget Park Improvements, 2229
Tienda Drive, with Herrington Landscape Services, of Cameron Park ($543,207.50) and Appropriating
Funds ($600,000)
April 18, 2012
Page 2
Staff recommends the appropriation of $600,000 for the construction contract, staff time and
contingencies.
FISCAL IMPACT: There is no direct impact to the Parks and Recreation Department budget for
the park development improvements at Roget Park. Funds being used are
from the sale of the Tienda Drive property for the Senor Housing Project.
FU NDI NG AVAI LABLE: Requested Appropriation:
General Fund Capital (1211): $600,000
AS "" — a. . 'J' "— -
F. Wally Sakelin
Public Works Director
FWS/pmf
an Ayers
Deputy City Manager/Internal Services Director
Jeff Hood
Interim_ Pe s, R:ecreatior Cultural Services Director
K:\WP\PROJECTS\PARKS\Roget\Roget Park Improvements\CAward.doo 4/5/2012
ROGET PARK IMPROVEMENTS
2229 TIENDA DRIVE
CITY OF LODI, CALIFORNIA
CONTRACT
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and HEMINGTON LANDSCAPE SERVICES, herein referred to as the
"Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other is to
be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees
with the City, at Contractor's cost and expense, to do all the work and furnish all the materials
except such as are mentioned in the specifications to be furnished by the City, necessary to
construct and complete in a good workmanlike and substantial manner and to the satisfaction
of the City the proposed improvements as shown and described in the Contract Documents
which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractorto provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
CONTRACTLOC 1 04/04/2012
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division
2 of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing
wage rate and other employer payments for health and welfare, pension, vacation, travel time,
and subsistence pay, apprenticeship or other training programs. The responsibility for
compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for
all risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of developing 4.5 acres of park land. The existing land must be regarded
and landscaped. Work shall also include the installation of new concrete walkways, bocce
courts, horseshoe pits, game tables, lighting, park benches, trash receptacles, par -course
equipment, park sign, 5HP VFD irrigation booster pump, automatic irrigation system, hydro
seeded turf, native planting materials, underground utilities and other incidental and related
work, all as shown on the plans and specifications for "Roget Park Improvements, 2229 Tienda
Drive".
CONTRACT ITEMS
ITEM EST'D.
NO DESCRIPTION UNIT QTY UNIT PRICE
1. Clearing and Grubbing Tree
Removal and Stump Grinding LS 1 $ 28,758.80
2. Dust Control LS 1 $ 3,981.00
3. Furnish, Install and Maintain
Storm Water Pollution
Prevention Plan LS 1 $ 10,976.00
4.
5.
Furnish and Maintain Temporary
Chain Link Fencing LF 1,040
Furnish and Install Temporary
Project Sign
Rough, Fine Grading and
Compaction
CONTRACTMOC
LS 1
SF 196,020
2
$ 2.50
$ 700.00
TOTAL PRICE
$28,758.80
$ 3,981.00
$10,976.00
$ 2,600.00
$ 700.00
$15,681.60
04/04/12
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
7.
Furnish and Install New4-Inch
Water Gate Valve and Water
Meter Box
LS 1
8.
Furnish and Install 4 -Inch Ductile
Iron Water Line
LF 80
9.
Furnish and Install I -Inch
Schedule 40 PVC Potable Water
Line
LF 175
10.
Furnish and Install 30 -Inch
Diameter x 12 -Foot Deep Dry
Well and Associated Plumbing
EA 1
11.
Furnish and Install 4 -Inch
Backflow Device
EA 1
12.
Furnish and Install Underground
Primary Electrical
LS 1
13.
Furnish and Install 200 Amp
Metered Switchboard Panel and
Pedestal Enclosure
LS 1
14.
Furnish and Install Parking
Lighting Conduit and Conductor
LF 1,650
15.
Furnish and Install Electrical Pull
Boxes
EA 14
16.
Furnish and Install Decorative
Park Lights with Concrete
Foundations
EA 11
17.
Furnish and Install Drop Inlet
Catch Basin
EA 1
$ 750.00 $ 750.00
$ 65.25 $ 5,220.00
$ 3.00 $ 525.00
$ 950.00 $ 950.00
$ 6,500.00 $ 6,500.00
$ 5,205.60 $ 5,205.60
$ 6,864.00 $ 6,864.00
$ 8.62 $14,223.00
$ 298.10 $ 4,173.40
$ 5,845.00
$ 2,525.00
$64,295.00
$ 2,525.00
CONTRACTMOC 3 04/04/12
ITEM
EST'D.
NO.
DESCRIPTION
UNIT QTY
UNIT PRICE
TOTAL PRICE
18.
Furnish and Install 6 -Foot Wide
Concrete Walkways
LF
1,660
$
24.00
$39,840.00
19.
Furnish and Install
Miscellaneous Concrete Flat
Work
SF
2,035
$
5.00
$10,175.00
20.
Furnish and Install 2 -Foot Wide
Concrete Mow Strip
LF
225
$
13.00
$ 2,925.00
21.
Furnish and Install Concrete Pad
with Macro Fiber and Saw Cut
Joints
SF
7,144
$
5.00
$35,720.00
22.
Furnish and Install 12 -Inch x
18 -Inch Concrete Curbing for
Bocce Court
LF
324
$
25.00
$ 8,100.00
23.
Furnish and Install Concrete
Utility Enclosure Pad and Post
Footings
LS
1
$
3,025.00
$ 3,025.00
24.
Furnish and Install 5
Horsepower Variable Frequency
Drive (VFD) Irrigation Booster
Pump and Electrical
EA
1
$
21,707.50
$21,707.50
25.
Furnish and install Maxicom
Irrigation Controls and Electrical
IS
1
$
15,661.70
$15,661.70
26.
Furnish and Install Automatic
Irrigation System
SF
181,310
$
0.29
$52,579.90
27.
Furnish and Install Soil
Amendments, Fertilizer and Soil
Preparation LBS
4,500
$
2.75
$12,375.00
28.
Furnish and install
Pre -Emergent Herbicide
LS
1
$
1,122.00
$ 1,122.00
CONTRACTLOC 4 04/04/12
ITEM
EST'D.
NO.
DESCRIPTION
UNIT
QTY
UNIT
PRICE
TOTAL
PRICE
29.
Furnish and Install Hydro
Seeded 90/10 Turf Grass
SF 48,300
$
0.07
$
3,381.00
30.
Furnish and Install Shrub and
Ground Cover Plant Material
LS
1
$
14,700.00
$14,700.00
31.
Furnish and Install 15 -Gallon
Trees
EA
82
$
100.00
$
8,200.00
32.
Furnish and Install Mulch
Ground Cover
CY
1,250
$
37.00
$46,250.00
33.
Furnish and Install Bocce
Court(s) Section Material
LS
1
$
8,470.00
$
8,470.00
34.
Furnish and Install Horseshoe
Pit(s) Metal Work and
Backboards
LS
1
$
2,627.00
$
2,627.00
35.
Furnish All Labor Plaster Sand
for Horseshoe Pit(s)
BAGS
24
$
10.00
$
240.00
36.
Furnish and Install Utility
Enclosure with Custom Wood
Fencing and Gate
LF
82
$
109.00
$
8,938.00
37.
Furnish and Install 6 -Foot Park
Benches with Backs
EA
5
$
1,221.00
$
6,105.00
38.
Furnish and Install 7 -Foot Park
Benches with Backs
EA
8
$
990.00
$
7,920.00
39.
Furnish and Install Trash
Receptacles
EA
7
$
1,232.00
$
8,624.00
40.
Furnish and Install ADA Drinking
Fountain with Concrete Pad and
Plumbing
EA
1
$
4,818.00
$
4,818.00
CONTRACT.DOC 5 04/04/12
ITEM EST'D.
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
41. Furnish and Install Precast
Concrete Game Tables EA 6 $ 1,546.00 $ 9,276.00
42. Furnish and Install Custom
Natural Stone Park Sign with
Concrete Foundations —
Aluminum Lettering and Log LS 1 $ 11,753.00 $11,753.00
43. Furnish and Install Par -Course
Equipment EA 5 $ 3,322.00 $16,610.00
44. Furnish All Labor, Materials and
Equipment for 90 -Day
Maintenance Period LS 1 $ 8,136.00 $ 8,136.00
TOTAL $543,207.50
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor or
materials not mentioned specifically as being done by the City will be supplied by the Contractor
to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 5
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 120 WORKING DAYS.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
CONTRACTMOC 6 04/04/12
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI
By:
Konradt Bartlam
City Manager
By: Date:
Title
Attest:
City Clerk
(CORPORATE SEAL) Approved As To Form
D. Stephen Schwabauer
City Attorney
CONTRACT, DOC 04/04/12
1. AA#
2. JV#
DITT OF I=ODI
APPROPRIATION AOJQSTMENrREQUEST
TO. Internal Services Dept. - Budget Division
3 FROM: I Rebecca Areida-Yadav 15. DATE: 02/28/2012
4. DEPARTMENT/DIVISION: Public Works
6, REQUEST ADJUSTMENT, OF APPROPR(ATIQN AS LI8 TED BELOW
FUND # BUS. UNIT # ACCOUNT # ACCOUNT TITLE AMOUNT
A.
1211 3205 Unreserved Fund Balance $ 600 000.00
SOURCE OF
FINANCING
B.
1211 1211042 1825.2400 Ro et Park $ 600 000.00
USE OF
FINANCING
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Award contract for Roget Park Improvements project. Funds being used for this project are coming from the sale of Tienda Drive
(senior housing project). Revenuefrom the sale were received last fiscal year.
If Council has authorized the appropriation adjustment, complete the following:
Meeting Date: Res No: Attach copy of resolution to this form.
Department Head Signature:
APPROVAL SIGNATURES
)eputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Divisionwith any required documentation
Final approval will be provided in electroniccopy format.
RESOLUTION NO. 2012-45
A RESOLUTION OF THE LODI CITY COUNCILAWARDING
CONTRACTAND AUTHORIZINGTHE CITY MANAGERTO
EXECUTE CONTRACT FOR ROGET PARK IMPROVEMENTS,
2229 TIENDA DRIVE, AND FURTHER APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on April 4, 2012, at 11:00 a.m.,
for Roget Park Improvements, 2229 Tienda Drive, described in the plans and specifications
therefore approved by the City Council on December 21, 2011; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Bid
Hemington Landscape Services
$
543,207.50*
WABO Landscape
$
543,852.00
Stan Construction
$
547,366.75*
J.M. Slover
$
568,197.14
A.M. Stephens Construction
$
598,312.90
Saenz Landscape
$
601,202.46*
Stockbridge
$
613,767.90*
B.0 Construction
$
636,133.41*
Andrew L. Lee, Inc.
$
662,571.00
Dominguez Landscape
$
667,152.58*
Abide Builders
$
669,352.90
Diede Construction
$
684,783.30
Vinciguerra Construction
$
687,450.17*
Hobbs Construction
$
696,889.10
*Corrected Total
WHEREAS, staff recommends awarding the contract for Roget Park Improvements,
2229 Tienda Drive, to the low bidder, Hemington Landscape Services, of Cameron Park,
California, in the amount of $543,207.50.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for Roget Park Improvements, 2229 Tienda Drive, to the low bidder, Hemington
Landscape Services, of Cameron Park, California, in the amount of $543,207.50; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract; and
BE IT FURTHER RESOLVED that funds in the amount of $600,000 be appropriated
from General Fund Capital and Park Impact Fee Fund for this project.
Dated: April 18, 2012
hereby certify that Resolution No. 2012-45 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held April 18, 2012, by the following vote:
AYES: COUNCIL MEMBERS— Hansen, Johnson, Nakanishi, and Mayor Mounce
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Katzakian
ABSTAIN: COUNCIL MEMBERS— None
I JOHL
City Clerk
2012-45