HomeMy WebLinkAboutAgenda Report - February 1, 2012 C-05AGENDA ITEM COP5
'• CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Rejecting Non -Responsive Bids, Authorizing City Manager to
Execute Contract for Transit Station Facility Improvement Project with
Diede Construction, Inc., of Lodi ($127,596.50) and Appropriating Funds ($25,000)
MEETING DATE: February 1,2012
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution rejecting non-responsive bids; authorizing
City Manager to execute contract for Transit Station facility
improvement project with Diede Construction, Inc., of Lodi, in the
amount of $127,596.50; and appropriating funds in the amount of $25,000.
BACKGROUND INFORMATION: The project includes replacing the gutters, the damaged roof
structure, and composition roofing at the four passenger shelters;
rerouting and connecting eight existing downspouts to new gutters
at the passenger shelters; pressure washing and painting the passenger shelters, North Annex,
South Annex, and main Transit Station; removing and replacing concrete expansion caulk joints at the
platform surrounding all the buildings and shelters, and replacing the louvered covers at the South Annex.
There is also a $5,000 allowance to repairthe South Annex clock.
Plans and specifications for this project were approved on July 6, 2011. The City received the following five
bids for this project on November 30, 2011, The bid received from Triumph Construction, Inc., is
non-responsivefor failure to provide the required proof of qualification and listing of required subcontractors.
Triumph Construction also incorrectly totaled the Schedule of Values form; the correct total is shown below.
The bid received from Seven Islands Painting is non-responsivefor failure to providethe required proof of
qualification and listing of required subcontractors. The bid received from Bobo Construction, Inc., is
non-responsivefor failure to include the mandatory addenda acknowledgement.
Bidder
Location
Bid
Engineer's Estimate
$
150,000.00
Triumph Construction Group (non-responsive)
North Highlands
$
87,325.00
Seven Islands Painting (non-responsive)
Daly City
$
104,750.00
Bobo Construction, Inc. (non-responsive)
Elk Grove
$
118,997.50
Diede Construction, Inc.
Lodi
$
127,596.50
Color New Company
Woodland Hills
$
134,750.00
Angie McDaniel, of Guthrie Consulting, representingthe small business community, raised a concern
aboutthe City's bid process. Ms. McDaniel contendsthat Federal Transportation Administration (FTA)
and Federal Acquisition Regulation (FAR) regulations do not permit the City to require bidders to have
completed three prior similar projects to be considered to have submitted responsive bids. FAR
regulations are not applicable to this contract according to the FTA Manual entitled Third Party
Contracting Guidance (FTA 4220,1 F) Chapter 2 of the referenced manual notes: "The Federal
Acquisition Regulation (FAR), 48 CFR Chapter 1, does not apply to federally assisted procurements
absent federal laws or regulationsto the contrary. In the case of FTA programs, FAR cost principles
APPROVED:
Konradt Bartlam, City Manager
KAWPTROJECTSITRANS1-11Transit Facility Improvemen ,d Documents\Transit Station Facility Imp CAward 1-18.12.doc 112512012
Adopt Resolution Rejecting Non -Responsive Bids, Authorizing City Manager to Execute Contract for
Transit Station Facility Improvement Projectwith Diede Construction, Inc,, of Lodi ($127,596.50) and
Appropriating Funds ($25,000)
February 1,2012
Page 2
Part 31 apply to grants and cooperative agreements with private for profit entities." (See Page 11-.) This
procurement is not a cooperative agreement or a grant to a private entity. As such, FAR cost principles
do not apply. However, FTA regulations do indeed prohibit cities from instituting conditions on
federally -funded projects "that unduly restrict competition." Moreover, at least one FTA Frequently -
Asked -Questions bulletin suggests that job-related experience maybe an excessive hindrance to
competition (Exhibit A). However, other regulations suggest that contractor experience is a relevant
factor (see e,g. 49 USC 53250)). In order to clarify the FTA requirements, staff contacted Renee Marker,
staff Counsel for the FTA. Staff informed Ms. Markerthat staff has traditionally used a three -similar -job
requirement for all of its bid projects (locally and federally funded), either through a Request for
Qualifications Analysis or through a bid responsiveness requirement. Staff informed Ms. Markerfurther
that the requirement is consistentwith a California Industrial Relations DepartmentApproved
prequalification process attached to this report as Exhibit B. Ms. Maker also asked about the number of
responsive bids received. Her inquirywas focused on whether an adequate number of bidders was able
to successfully bid on the project. In this case, three bidders met the experience requirements (though
one failed to include an addendum). Relying on our past history with the requirement and a healthy bid
field, Ms Marker indicated that she did not believe the practice unduly restricted competition or violated
FTA regulations.
Staff recommends rejecting the non-responsive bids and awarding the contract to Diede Construction, I nc,
Staff also recommends appropriating $25,000 in addition to funds allocated in the FY 2011/12 budget to
cover City staff time, project -related costs and contingencies.
FISCAL IMPACT: The project will reduce the maintenance costs at the facility.
FUNDING AVAILABLE: This project will utilize $131,000 in Transportation DevelopmentAct (TDA)
funds (125179) allocated in the FY 2011/12 budget.
Requested Appropriation: TDA Funds (125179): $25,000
Jords) Ayers
Deputy City Manager/Internal Services Director
F. Wally Sindelin
Public Works Director
Prepared by Gary Wiman, Construction Manager
FWSIGWlpm#
Attachments
cc: Construction Project Manager Wiman
Transportation Manager Fernandez
ManagementAna lyst Areida-Yadav
Diede Construction, Inc.
Triumph Construction, Inc.
Seven Islands Painting
Bobo Construction. Inc.
KAWPTROJECTWRANSITITransit Facility lmprovementsTid Doauments\Tranait Station Facility ImpCAward 1-16-12.doc 11251207
FTA - Third Party Procurement FAQ Search - Determining Contractor Responsibility
Home Paue» About FT >> Doinq Business with FTA >> Third Party Procurement FAQ Search
N
Q What are the components of a responsibility determination?
A 49 U S C 53250) provides
"AWARDS TO RESPONSIBLE CONTRACTORS —
IN GENERAL —Federal financial assistance under this chapter may be provided for
contracts only if a recipient awards such contracts to responsible contractors possessing
the ability to successfully perform under the terms and conditions of a proposed
procurement
CRITERIA —Before making an award to a contractor under paragraph (1), a recipient
shall consider—
A the integrity of the contractor,
B the contractor's compliance with public policy,
C the contractor's past performance, including the performance reported in
the Contractor Performance Assessment Reports required under section
5309(1)(2); and
D the contractor's financial and technical resources "
To designate a prospective contractor "responsible" as required by 49 U S C Section 5325, FTA
expects the recipient, at a minimum, to determine and ensure that the prospective contractor satisfies
the following criteria described herein In addition to being otherwise qualified and eligible to receive
the contract award under applicable laws and regulations, a responsible contractor
1 Integrity and Ethics. Has a satisfactory record of integrity and business ethics, in
compliance with 49 U.S.C. Section 53250)(2)(A),
2 Debarment and Suspension. Is neither debarred nor suspended from Federal programs
under DOT regulations, "Nonprocurement Suspension and Debarment,"2 CFR Parts 180
and 1200, or under the FAR at 48 CFR Chapter 1, Part 9.4,
3 Affirmative Action and DBE. k in compliance with the Common Grant Rules' affirmative
action and FTA's Disadvantaged Business Enterprise requirements,
4 Public Policy. Is in compliance with the public policies of the Federal Government, as
required by 49 U.S.C. Section 53250)(2)(6),
5 Administrative and Technical Capacity. Has the necessary organization, experience,
accounting, and operational controls, and technical skills, or the ability to obtain them, in
compliance with 49 U.S.C. Section 53250)(2)(D),
6 Licensing and Taxes. Is in compliance with applicable licensing and tax laws and
regulations,
7 Financial Resources. Has, or can obtain, sufficient financial resources to perform the
contract, as required by 49 U.S.C. Section 53250)(2)(D),
8 Production Capability. Has, or can obtain, the necessary production, construction, and
technical equipment and facilities,
9 Timeliness. Is able to comply with the required delivery or performance schedule, taking
into consideration all existing commercial and governmental business commitments, and
10 Performance Record. Is able to provide a:
a. Current Performance. Satisfactory current performance record, and
b. Past Performance. Satisfactory past performance record in view of its
records of long-time performance or performance with a predecessor
entity, including:
1. Sufficient Resources. Key personnel with adequate
experience, a parent firm with adequate resources and
experience, and key subcontractors with adequate
experience and past performance,
2. Adequate Past Experience. Past experience in carrying out
similar work with particular attention to management
approach, staffing, timeliness, technical success,
budgetary controls, and other specialized considerations
as described in the recipient's solicitation, and
3. Any Past Deficiencies Not the Fault of the Bidder or
Offeror. A prospective bidder or offeror that is or recently
Page 1 of 3
Exhibit A
Search
Ad,a a?d tie�rrh
A A A t<3 SHR RE
http://www.fta,dot,gov/ 13057_6118.html 1/17/2012
FTA - Third Party Procurement FAQ Search - Determining Contractor Responsibility Page 2 of 3
has been seriously deficient in contract performance is
presumed to be nonresponsible, unless the recipient
determines that the circumstances were properly beyond
the bidder or offeror's control, or unless the bidder or
offeror has taken appropriate corrective action. Past failure
to apply sufficient tenacity, perseverance, and effort to
perform acceptably is strong evidence of nonresponsibility.
Failure to meet the quality requirements of a contract is a
significant factor to consider in determining satisfactory
performance. FTA expects the recipient to consider the
number of the bidder or offeror's contracts involved and the
extent of deficient performance in each contract when
making this determination.
Before entering into a full funding contract for a fixed guideway project, the recipient
must now consider the prospective contractor's past performance in estimating costs
and ridership as reported in the Contractor Performance Assessment Reports, as
required by 49 U.S.C. Section 53250)(2)(C).
Certain procurements may require special standards of responsibility requiring contractors to have specialized
expertise or facilities in order to perform the contract adequately. These special standards of responsibility must be
set forth in the solicitation. Failure to meet the special standards will disqualify a bidder from consideration for
award. An example of a special responsibility standard would be the special quality assurance requirement
concerning measuring and testing facilities and manufacturing controls which must be met by prospective bus
manufacturers. (Revised: September 9, 2009)
Q. What is the Dollar Threshold for making a written Determination of Contractor Responsibility? Does it apply to
Purchase orders? How detailed must it be? Must it be in writing regardless of the threshold?
A. The Federal Transit Administration does not require its grantees to make a written determination of contractor
responsibility for small purchases (those under $100,000).
In reviewing the FAR Subpart 9. 1, it would seem that a determination of contractor responsibility is required for
"purchases" as well as "awards" - 9.103 (b). It is not clear, however, that FAR requires a written determination for
small purchases 9.103 (b) does require an "affirmative determination" of responsibility. FAR Subpart 13.101 deals
with procedures for small purchases and envisions a scenario when a CO determines a contractor to be
nonresponsible, in which case the CO is to comply with Subpart 19.6 with respect to Certificates of Competency
before rejecting a quotation. Once again, however, this does not clearly require a written determination of
responsibility for small purchases, only the CO's decision as to responsibility or nonresponsibility. We would
conclude from these FAR references that the FAR does envision the CO making a responsibility determination but
the FAR leaves a great deal of discretion in how the decision is made and to what extent it is documented.
(Reviewed: September 9, 2009)
* The FAR is available on the Internet at. http„//www,;,arnet;gov„/far/
Q. Can project -related experience be a condition of contract award? Can project -related experience be an
evaluation factor? We are requiring vendors to submit examples of at least three contracts of comparable size and
type as part of their proposals. We feel that previous experience is a necessary factor of project award. A
Contractor states that the minimum experience requirement indicated above is in conflict with FTA guidance that
prohibits grantees from requiring "unnecessary experiences” in all procurement transactions.
A. Project -related experience should be a factor related to the capability of the offeror to perform the contract; i.e.,
a factor for determining the offeror's responsibility, not responsiveness. As a responsibility issue, past experience
may be discussed with the company after proposals are submitted. For further guidance on determining contractor
responsibility, see the Best Practices Procurement Manual (BPPM), Section 5.1* - "Responsibility of Contractor."
We would think that requiring three previous projects of the same size as the present procurement would be an
excessive experience requirement. And to insist on this as a condition of bidding would seem unreasonable. Our
opinion would be that to require one project of similar size, successfully completed, with perhaps several more of
smaller size would be sufficient to demonstrate that the offeror has the capability to perform your contract. In any
case, we would advise you to be flexible about the number of past projects completed and their size. It may be
virtually impossible, for example, for a supplier to have completed three projects of the size you are now procuring
(Reviewed: September 9, 2009)
* Section 5.1 of the BPPM is available on the Internet.
Q. Is there a requirement that a request for financial statements be made of all proposing contractors (to be used
to help determine financial responsibility) and be included in the RFP, or can they be requested prior to award from
the selected contractor only? This is for a T&M master contract where prices are being considered as part of the
evaluation criteria.
A. The topic of Contractor Responsibility is covered in the Best Practices Procurement Manual, Section 5.1 -
Responsibility of Contractor. Any issue related to the determination of responsibility may be discussed with the
apparent low bidder or winning offeror prior to award. Thus you may ask for financial statements from the apparent
winning contractor after proposals have been evaluated. You need not request this information from all offerors in
the RFP. The types of information that may prove useful in the responsibility determination are discussed in the
BPPM section 5.13 - Obtaining Information for Determination of Responsibility. All of this information may be
obtained after proposals are evaluated and need not be included in the RFP. (Reviewed: September 9, 2009)
1) In a recipient's determination of responsibility or capacity to deliver, may a recipient require a dealer's license
(versus an in-state dealer's license) as proof that a bona fide relationship exists between a dealer and a specific
manufacturer?
2) In a recipient's determination of responsibility or capacity to deliver, may a recipient consider the fact that state
enforcement actions (as permitted in 4220.1 F, ch. VI.2.a.4.2) may prevent delivery? 4220.1 F stipulates that
awards may only be made to responsible contractors, specifically, that awards may be made only to contractors
who are capable of successfully performing under the terms of a proposed contract, generally known as "delivery."
http://www.fta.dot.gov/13057_6118.html 1/ 17/2Q 2
FTA - Third Party Procurement FAQ Search - Determining Contractor Responsibility
VI 2 a (4)(g) says recipients may not specify geographic preferences and may not limit bus purchases to in-state
dealers, but provides an exception in VI 2 a 4 2 that state licensing laws may be enforced. Licensing enforcement
actions include fines and issuance of cease and desist orders that would prevent a delivery.
A
1. It is reasonable in connection with a responsibility determination, for a grantee to request proof of a
dealer's eligibility to distribute a particular manufacturer's products.
2. A grantee may consider that a state's enforcement actions may prevent delivery, however, state
enforcement actions cannot unduly hinder or burden interstate commerce. In other words, a state may
not impose requirements on out-of-state vehicles that are not similarly imposed on in-state vehicles. If
the potential of state enforcement or licensing actions affect a grantee's ability to comply with the
Common Grant Rule's ban on geographic preferences, the grantee should immediately contact the
appropriate FTA Regional Office (Posted: March 2009)
F=edcr,1 1;ans!i,IAAr!ni Strai ot,
...i0 tic:m-.ler�eyA emte, 5;F
VV:35h n�jton GC 2059t)
i Jt.}•�'y'jS�
Find transit with Google Transit
Report Problems
1 -Met your (-"mail
p2eq]' iklm5 go,
Page 3 of 3
JS Ootzrv�!estl n"'aarE�onaf: x;
http://www.fta.dot.gov/13057-6 118.html 1/17/2012
Exhibit B
Questions concerning recent construction projects completed:
(one question, plus 11 interview questions)
The following question to be scored o, ly where a public agency is undertaking a pre-
qualificationprocedure valid for a single project only,
1. Contractor shall provide information about its six most recently completed public works
projects and its three largest completedprivate projects within the last three years." Names
and references must be current and verifiable. Use separate sheets of paper that contain all
of the following information:
Project Name:
Location:
Owner:
Owner Contact (name and current phone number):
Architect or Engineer:
Architect or Engineer Contact (name and currentphone number):
Construction Manager (name and current phone number):
Description of Project, Scope of Work Performed:
Total Value of Construction (including change orders):
Original Scheduled Completion Date:
T i e Extensions Granted (number of days):
Actual Date of Completion:
10 If you wish, you may, using the same format, also provide information about other projects that you have
completedthat are similarto the project(s) for which you expectto bid.
33
City of Lodi
Transit Station Facility Improvement Project
CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred to as
the "City," and DIEDE CONSTRUCTION, INC., herein referred to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and
agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by this
reference, to -wit:
PART A: Request for Design/Build Proposal
PART B: Bid Proposal Pricing Forms
PART C: Special Conditions
PART D: Federal Requirements
Specifications/Bridging Documents
Federal Minimum Wage Rates
Drawings:
Site Plan and Exhibits
Addenda
All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are intended
to cooperate so that any work called for in one and not mentioned in the other is to be executed the same
as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter mentioned, to be
made and performed by the City and under the condition expressed in the two bonds bearing even date
with these presents and hereunto annexed, the Contractor agrees with the City, at Contractor's cost and
expense, to do all the work, furnish all labor and furnish all the materials except such as are mentioned in
the specifications to be furnished by the City, necessary to construct and complete in a good workmanlike
and substantial manner and to the satisfaction of the City the proposed improvements as shown and
described in the Contract Documents which are hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does hereby
employ, the Contractor to provide all materials and services not supplied by the City and to do the work
according to the terms and conditions for the price herein, and hereby contracts to pay the same as set
forth in Clauses 65 and 66 Special Conditions, in the manner and upon the conditions above set forth; and
the said parties for themselves, their heirs, executors, administrators, successors and assigns, do hereby
agree to the full performance of the covenants herein contained.
ARTICLE III- The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2 of the
Labor Code. The Contractor and any Subcontractor will pay the general prevailing wage rate and other
employer payments for health and welfare, pension, vacation, travel time, and subsistence pay,
apprenticeship or other training programs. The responsibility for compliance with these Labor Code
requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full compensation
for furnishing all materials and for doing all the work contemplated and embraced in this agreement; also
for all loss or damage arising out of the nature of the work aforesaid or from the action of the elements, or
from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of
the work until its acceptance by the City, and for all risks of every description connected with the work;
also for all expenses incun-ed by or in consequence of the suspension or discontinuance of work and for
well and faithfully completing the work, and the whole thereof, in the manner and according to the Plans
and Contract Documents and the requirements of the Engineer under theni, to -wit:
TOTAL CONTRA CTAMO UNT Guaranteed
2klaximum Price $127,596.50
"ExhibitA is the Schedule of Values from the Contractor dated November 30,2011.
ARTICLE V - By niy signature hereunder, as Contractor, I certify that I am aware of the provisions of
Section 3700 of the Labor Code, which requires every employer to be insured against liability for
workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and
I will comply with such provisions before commencing the performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there be any
conflict between the terns of this instrument and the Bid Proposal of the Contractor, then this instrument
shall control and nothing herein shall be considered as an acceptance of the said terms of said proposal
conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements for the work as
specified under the Special Provisions. All labor or materials not mentioned specifically as being done by
the City will be supplied by the Contractor to accomplish the work as outlined in the documents.
ARTICLE VIII — The Contractor agrees to commence work pursuant to this contract and to diligently
prosecute to completion in accordance with the following schedule:
Total Project: 45 calendar days
When signing this contract, the Contractor agrees that the times of completion for this contract are
reasonable, that failure to meet the milestones completion shall result in the assessment of liquidated
damages charges to the Contractor, and that the Contractor agrees to pay the City liquidated damages of
$1,000.00 per day for each day the work is not totally completed beyond the times specified in the
preceding paragraph. Contractor agrees that this amount may be deducted from the amount due the
Contractor under the contract.
2
IN VN71TNESS WHEREOF,the parties to these presents have hereunto set their hands the year and date
written belov,,.
CONTRACTOR: CITY OF LODI
In
Title
(CORPORATESEAL)
By:
Konradt Bartlam, City Manager
Date:
Attest:
Randi Johl, City Clerk
Approved as to form:
D. Stephen Schwabauer, City Attorney
1. AA#
2. JV#
NOi
TO: Internal Services Dept. - Budget Division
3. FROM: Rebecca Areida-Yadav 15. DATE: 01/19/2012
4. DEPARTMENT/DIVISION; PublicWorks
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Contract with Diede Constructionfor Transit Station Facility Improvement project
If Council has authorizedthe appropriation adjustment, complete the following:
Meeting Date: Res No: Attach copy of resolution to this form.
Department Head Signature:
Deputy City Manager/Internal Services Manager Date
Submit completed form to the Budget Divisionwith any required documentation.
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2012-06
A RESOLUTION OF THE LODI CITY COUNCIL REJECTING NON.
RESPONSIVE BIDS, AWARDING CONTRACT FOR TRANSIT STATION
FACILITY IMPROVEMENT PROJECT, AUTHORIZING THE CITY MANAGER
TO EXECUTE CONTRACT, AND FURTHER APPROPRIATING FUNDS
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on November 30, 2011, at
11:00 a.m., for the Transit Station Facility Improvement Project, described in the plans and
specifications therefore approved by the City Council on July 6, 2011; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder Bid
Triumph Construction Group (non-responsive) $ 87,325.00
Seven Islands Painting (non-responsive) $ 104,750.00
Bobo Construction, Inc. (non-responsive) $ 118,997.50
Diede Construction, Inc. $ 127,596.50
Color New Company $ 134,750.00
WHEREAS, the bid received from Triumph Construction, Inc., is non-responsive for
failure to provide the required proof of qualification and listing of required subcontractors and
incorrectly totaling the Schedule of Values form, The bid received from Seven Islands Painting
is non-responsive for failure to provide the required proof of qualification and listing of required
subcontractors. The bid received from Bobo Construction, Inc., is non-responsive for failure to
include the mandatory addenda acknowledgement; and
WHEREAS, staff recommends rejecting the non-responsive bids and awarding the
contract for the Transit Station Facility Improvement Project to the lowest responsive bidder,
Diede Construction, of Lodi, California, in the amount of $127,596.50.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby reject
the non-responsive bids and award the contract for the Transit Station Facility Improvement
Project to the lowest responsive bidder, Diede Construction, of Lodi, California, in the amount of
$127,596.50; and
BE IT FURTHER RESOLVED that the City Council does hereby authorize the
City Manager to execute the contract; and
BE IT FURTHER RESOLVED that funds in the amount of $25,000 be appropriated from
Transportation Development Act Funds for this project.
Dated: February 1, 2012
I hereby certify that Resolution No. 2012-06 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held February 1, 2012, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, Nakanishi, and
Mayor Mounce
NOES: COUNCIL MEMBERS —None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS —None
L��HL
City Clerk
2012-06
RECE1YED
GUTHRIE CONSULTING 20121AN 17 Aft 8: 39
CITY CLERK
January 13th, 2012 CITY OF L 4 D 1
City of Lodi
221 West Pine Street
Lodi, California 95240
Re: Transit Station Facility Improvement Project
Dear City Council,
f
2215 West Wabmt Sweet
Lol, California 95242
www. utbrieConsulting.biz
Phone: 209-365-3541
E-mail:
angie@gnthriewnsuW%.biz
I am a small business advocate and a citizen of Lodi. The Transit Station Facility Im-
provement Project must be rebid (again) for the following reasons:
1. Restricted Competition
This project has a past performance sheet imposing unnecessary experience re-
quirements for bidders. It is the opinion of the FTA that to insist on 3 previous projects
of the same size would be unreasonable; this is what the City is requesting and is an
FTA prohibited solicitation requirement. This gives all the bidders on this project an
unfair advantage over those who could have participated.
2. Design -Build Proposal Language
Instead of a notice for "Invitations for Bid" this project has been advertised as a
Design -Build "Request for Proposal" which is a negotiated solicitation awarded to the
"Best Value" for the City. As per Lodi municipal code, projects over twenty thousand
dollars must use the formal contract procedure of sealed bidding awarded to the lowest
responsible bidder. Additionally, this contract is being awarded for a "Guaranteed
Maximum Price", another negotiated Design -Build term meaning that the City will
only pay actual costs plus overhead and profit; not the full amount of the award if
these costs fall below that amount.
3. Contractor's Response to Protest
A protest has been issued challenging several of the contractors' licenses. A
valid response was submitted yet the recommended action was to continue with award
to the protesting contractor. Would Council please review and address this issue as it
will affect future City bids.
Sincerely,
A>tkgfe McDaniel
FTA - Third Party Procurement FAQ Search - Determining Contractor Responsibility Page 3 of 5
(Reviewed: September 9,2009)
* The FAR is available on the Internet at: http:1/www.arnet.govlfarl
Q. Can project -related experience be a conditiZ;„ 3, Z3,,)ract award? Can project -related experience be an
evaluation factor? We are requiring vendors to submit examples of at least three contracts of comparable size and
type as part of their proposals. We feel that previous experience is a necessaryfactor of project award. A
Contractor states that the minimum experience requirement indicated above is in conflictwith FTA guidance that
prohibits grantees from requiring "unnecessary experiences" in all procurementtransactions.
A. Project -related experience should be a factor related to the capability of the offeror to perform the contract; i, e,,
a factor for determining the offeror's responsibility, not responsiveness.As a responsibility issue, past experience
may be discussed with the company after proposals are submitted. Forfurther guidance on determining contractor
responsibility, see the Best Practices Procurement Manual (BPPM). Section 5.1* - "Responsibility of Contractor."
We would think that requiring three previous projects of the same size as the present procurement would be an
excessive experience requirement. And to insist on this as a condition of bidding would seem unreasonable. Ou
opinion would be that to require one Droiect of similar size. successfully completed. with perhaps several more cf
smaller size would be sufficient to demonstrate that the offeror has the capability to perform your contract. In any
case, we would advise you to be flexible about the number of past projects completed and their size. It may be
virtually impossible, for example, for a supplierto have completedthree projects of the size you are now procuring.
(Reviewed: September 9,2009)
• Section 5.1 of the BPPM is available on the Internet.
Q. Is there a requirement that a request for financial statements be made of all proposing contractors (to be used
to help determine financial responsibility)and be included in the RFP, or can they be requested prior to award from
the selected contractoronly? This is for a T&M master contract where prices are being considered as part of the
evaluation criteria.
A. The topic of Contractor Responsibility is covered in the Best Practices Procurement Manual, Section 5.1 -
Responsibility of Contractor. Any issue relatedto the determination of responsibility may be discussed with the
apparent low bidder or winning offeror priorto award. Thus you may ask for financial statementsfrom the apparent
winning contractor after proposals have been evaluated. You need not requestthis information from all offerors in
the RFP. The types of information that may prove useful in the responsibility determination are discussed in the
BPPM section 5.1.3 -Obtaining Information for Determinationof Responsibility. All I of this information may be
obtained after proposals are evaluated and need not be included in the RFP. (Reviewed: September9, 2009)
p�
I ) In a recipient's determination of responsibility or capacity to deliver, may a recipient require a dealer's license
(versus an in-state dealer's license) as proof that a bona tide relationship exists between a dealer and a specific
manufacturer?
2) In a recipient's determinationof responsibility or capacity to deliver, may a recipient considerthe fact that state
enforcement actions (as permitted in 4220.1 F, ch. VI.2.a.4.2) may prevent delivery? 4220.1 F stipulates that
awards may only be made to responsible contractors, specifically, that awards may be made only to contractors
who are capable of successfully performing underthe terms of a proposed contract, generally known as "delivery."
VI 2 a (4)(g) says recipients may not specify geographic preferencesand may not limit bus purchasesto in-state
dealers, but provides an exception in VI 2 a 4 2 that state licensing laws may be enforced. Licensing enforcement
actions include fines and issuance of cease and desist orders that would preventa delivery.
4.
1. It is reasonable in connection with a responsibility determination, for a grantee to request proof of a
dealer's eligibilityto distribute a particular manufacturer's products.
2. A grantee may consider that a state's enforcement actions may prevent delivery, however, state
enforcement actions cannot unduly hinder or burden interstate commerce. In other words, a state may
not impose requirements on out-of-state vehicles that are not similarly imposed on in-state vehicles. If
the potential of state enforcement or licensing actions affect a grantee's ability to comply with the
Common Grant Rule's ban on geographic preferences, the grantee should immediately contact the
appropriate FTA Regional Office. (Posted: March 2009)
Report Problems
http://www.ta.dot.gov/13057�6118.html 1/16/2012
FTA C 4220.1 F
11/01/2008
Page VI -3
contract rights to property or services excess to the recipient's immediate needs,
even though the recipient may assign its excess contract rights to others.
(3) Brand Name or Eaual. When it is impractical or uneconomical to provide a clear
and accurate description of the technical requirements of the property to be
acquired, a "brand name or equal" description may be used to define the
performance or other salient characteristics of a specific type of property. The
recipient must identify the salient characteristics of the named brand that offerors
must provide. When using a "brand name" specification, the recipient does not
need to reverse -engineer a complicated part to identify precise measurements or
specifications in order to describe its salient characteristics. FTA's "Best Practices
Procurement Manual," (BPPM) contains additional information on preparation of
specifications including examples with specific language.
Prohibitions. The Common Grant Rules prohibit solicitation requirements that
contain features that unduly restrict competition. FTA recipients are also
prohibited by 49 U.S.C. Section 5325(h) from using FTA assistance to support an
exclusionary or discriminatory specification. Some situations considered to be
restrictive of competition include, but are not limited to, the following, all of
which are identified in one or both Common Grant Rules:
(a) Excessiize. Ujalifications. Imposing unreasonable business requirements for
bidders or offerors.
(b) Unnecessarx Experience. Imposing unnecessary experience requirements for
biclders and offerors.
(c) Improper Preaualification. Using prequalification procedures that conflict
with the prequalification standards described in subsection Lc of this Chapter.
(d) Retainer Contracts. Making a noncompetitive award to any person or firm on
a retainer contract with the recipient if that award is not for the property or
services specified for delivery under the retainer contract.
(e) Excessive Bonding. To encourage greater contractor participation in FTA
assisted projects, FTA does not require the recipient to impose bonding
requirements on its third party contractors other than construction bonding
specified by the Common Grant Rules and this circular for construction. FTA
discourages unnecessary bonding because it increasesthe cost of the contract
and restricts competition, particularly by disadvantaged business enterprises.
Bond companies exercise their discretion and assure their profits primarily by
declining to undertake excessive risks. Consequently many bidders have
limited "bonding capacity." Unnecessary performance bonding requirements
reduce a prospective bidder's or offeror's capability to bid or offer a proposal
on bonded work. Small businesses with short histories may have particular
difficulty obtaining bonds as may be specified.
CITY COUNCIL
JOANNE L MOUNCE, Mayor
ALAN NAKANISHI,
Mayor Pro Tempore
LARRY D. HANSEN
BOBJOHNSON
PHIL KATZAKIAN
Diede Construction, Inc.
P.O. Box 1007
Woodbridge, CA 95258
Seven Islands Painting
6548 Mission Street
Daly City, CA 94014
CITY OF LODI
PUBLIC WORKS DEPARTMENT
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209)333-6706
FAX (209)) 333-6710
EMAIL ppwdeptVQodi.gov
http:\ www.l Lgov
January 25,2012
Triumph Construction, Inc.
3601 Plymouth Drive
North Highlands, CA 95660
Bobo Construction, Inc.
9728 Kent Street
Elk Grove, CA 95624
KONRADT BARTLAM
City Manager
RANDI JOHL
City Clerk
D. STEVEN SCHWABAUER
City Attorney
F. WALLY SANDELIN
Public Works Director
SUBJECT: Adopt Resolution Rejecting Non -Responsive Bids, Authorizing City Manager to
Execute Contract for Transit Station Facility Improvement Project with
Diede Construction, Inc., of Lodi ($127,596.50) and Appropriating Funds ($25,000)
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, February 1, 2012. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunityto address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letter to City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Randi Johl, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Gary Wiman,
Construction Project Manager, at (209) 333-6800, extension 2054.
`AA��
F. Wally Sandelin
r ' Public Works Director
F W Slpmf
Enclosure
cc: City Clerk
NTRANSrr STATION FAC1LrrY IMP CAWARD 1-18-12.130C