HomeMy WebLinkAboutAgenda Report - October 5, 2011 C-11AGENDA ITEM CAI
Ah CITY OF LODI
COUNCIL COMMUNICATION
Im
AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Improvement Deferral
Agreement for 21 East Elm Street
MEETING DATE: October 5, 2011
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution authorizing City Managerto execute Improvement
Deferral Agreement for 21 East Elm Street.
BACKGROUND INFORMATION: Ann H. Peden (Owner) has submitted a building permit application
to allow tenant improvements to an existing building located at
21 East Elm Street. As a condition of the building permit
(B11-0970), the construction of public improvements is required.
The required public improvements along Elm Street and Main Street include the installation 180 feet of
concrete sidewalks, curb, gutter, a curb return, and 30 feet of 12 -inch storm drain pipe; replacement of
3,030 square feet of asphalt concrete; and the replacement of an above -ground powerfeed with an
underground power feed to the building (Exhibit A). Owner has requested that the required
improvements be deferred.
Owner has executed an Improvement Deferral Agreement and paid the necessary document preparation
and recording fees for the agreement. The agreement also states that the owner agrees to pay for and
complete the design and installation of the required improvements on Elm Street and Main Street in
accordance with City Standards, including payment of engineering and other applicable City fees, at the
time of the widening of Main Street, or at the request of the City, whichever occurs first.
Staff recommends approval of the Improvement Deferral Agreement.
FISCAL IMPACT: None.
FUNDING AVAILABLE: Property owner funding prior to construction.
Prepared by Chris Boyer, Junior Engineer
FWS/CRB/pmf
Attachment
cc: Senior Civil EngineerChang
Ann H. Peden
APPROVED
KAWP\DEV SERv1CC ImpDefA9mt 21 E ElmSt.doc
F. Wally Sapelin
PublicWorks Director
`'f�onradt Bartlam, City Manager
09/20/2011
City of Lodi
Publics Works Department
Development: 21 East Elm Street
Developer:
Engineer:
TOTAL COST OF PROJECT IMPROVEMENTS
IMPROVEMENT COST
ESTIMATE FOR
IMPROVEMENTS
Acres:
Date: 8/17/11
Item
Description
Quantitv
Unit
Price
Total
Quantitv
Total
Street System
1
Vertical Curb and Gutter
180
LF
25.00
4,500.00
180
4,500.00
2
Sidewalk
1,350
SF
6.00
8,100.00
1,350
8,100.00
3
Curb Return, including Handicap Ramp
1
EA
15,000.00
15,000.00
1
15,000.00
4
Concrete Subgrade Compaction
1,350
SF
3.00
4,050.00
1,350
4,050.00
5
Side Inlet Catch Basin
1
EA
2,272.00
2,272.00
1
2,272.00
6
12" Storm Drain Pipe (RCP)
30
LF
40.00
1,200.00
30
1,200.00
7
Aggregate Base, Class II (0.50')
3,030
SF
0.90
2,727.00
3,030
2,727.00
8
Asphalt Concrete, Type B (0.30')
3,030
SF
2.00
6,060.00
3,030
6,060.00
9
Compact Original Ground (0.50')
3,030
SF
0.20
606.00
3,030
606.00
10
Remove Existing Pavement
3,030
SF
7.00
21,210.00
3,030
21,210.00
11
Street Name Sign & Post
1
EA
511.00
511.00
1
511.00
12
Replace Aboveground Power Feed with Undergroi
1
EA
5,000.00
5,000.00
1
5,000.00
Subtotal
$66,236.00
Subtotal
$71,236.00
Total Construction
Cost
$71,236.00
Engineering
& Administration (10% of Construction Costs)
$7,123.60
Contingencies (10% of Construction Costs)
$7,123.60
TOTAL COST I A. Total $85,483.20
K:\DEV_SERV\Developments\Commercial-Industrial\21 E. Elm St\Improvement_Cost_Estimate - 21 E. Elm St - 8-15-11.xls
WHEN RECORDED, RETURN TO:
City Clerk
City of Lodi
221 West Pine Street
Lodi, CA 95240
I1VIPROVEMENT DEFERRAL, AGREEMENT
21 East Elm Street, Lodi, California
(APN 043-082-03)
THIS AGREEMENT is made and entered into by and between the CITY OF LODI, hereinafter
referred to as "City" and ANN H. PEDEN, hereinafter referred to as "Owner".
RECITALS:
Owner is the owner of that certain real property situated in the City of Lodi, County of San
Joaquin., known as 21 East Elm Street (APN 043-082-03) and described as follows:
The East 50 feet of the South half of Block 25, as said Block is delineated and designated
on that certain map entitled, "Mokelumne" (now City of Lodi), filed for record August
25, 1869, at 8:40 a.m. and recorded in Book of maps and plats, Volume 4, page 12, San
Joaquin County Records.
Building application(B 11-0970)has been submittedto allow a tenant improvementto an
existingbuilding on the subjectproperty. Installation ofpublic improvements along Elm Street
and Main Street are required as a condition of permit issuance in accordance with existing City
ordinances and policies regarding off-site improvements as set forth in Title 15, Chapter 15.44 of
the Lodi Municipal Code. Required improvements include, but are not limited to, the installation
180-feetof concrete sidewalks, curb, gutter, a curb return, 30 -feet of 12 -inch storm drainpipe,
replacement/instalhnent of 3,030 square feet of asphalt concrete and the replacement of an
abovegroundpower feed with an underground power feed to the building. Owner is desirous of
complying with existing City ordinances and policies regarding off-site improvements. Owner
has requested that the improvements on Ehn Street and Main Street be deferred.
Council of the City will approve the deferral of the required Elm Street and Main Street
improvements on conditionthat the Owner first enters into and execute this agreement v&h City.
NOW THEREFORE, in order to insure satisfactoryperformance by Owner of Owner's
obligations under said City Code, the parties agree as follows:
1. Owner agrees to pay for and complete the design and installation of the required
improvements on Ehn Street and Main Street in accordance with City Standards, including
payment for engineering and other applicable City fees, at the time of the widening of Main
Street, or at the request of the City, whichever occurs first.
2. Owner agrees to undertake the design and construction of the required improvements within
30 days after written notice is given by the City, subject to Item#1 above, and will complete
the required improvements within 120 days from the date of notice.
KADEV_SERVOeferral agrwmeats\21 E. Elm St.doc
3. This agreement shall run with the land and be binding on the Owner, its heirs, successors or
assigns.
4. If Owner fails to complete the required improvements, or make the fee payments as required
by Item # 1 of this Agreement within the time period specified in Item #2 above, the City
shall be entitled, at its election, to either 1) file suit against Owner, its heirs, successors or
assigns, for the full value of the improvements at the time period specific in Item #2 above
plus attorney fees, or 2) complete the improvements at the expense of Owner, and file suit
against Owner, its heirs, successors or assigns for the costs incurred, plus attorney fees. In
either case, the City shall be entitled to file a lien against said property for the full value of
the improvement costs.
5. A copy of the Agreement shall be recorded in the office of the San Joaquin County Records,
P. O. Box 1968, Stockton, California 95201-1968.
6. All notices herein required shall be in writing, and delivered in person or sent by registered
mail, postage prepaid.
Notices required to be given to City shall be addressed as follows:
F. Wally Sandelin
Public Works Director
City of Lodi
P. O.Box 3006
Lodi, CA 95240-1910
Notices required to be given to Owner shall be addressed as follows:
Ann H. Peden
12272 Jerri Drive
Glen Ellen, CA 95442
KADEV_SERVOeferral agreements\21 E. Elm St.doc
IN WITNESS WHEREOF, the parties hereto have set their hands the day, month and
year appearing opposite their names.
Dated:
2011
Dated' 2 2011
CITY OF t_ODI, a Municipal Corporation
By:
Konradt Bartlam, City Manager
Rand! Johl, City Clerk
ANN H. PEDEN
Approved as to form:
D. S c wa aue
City Attorney
Dated: i" b 2011
KADEV_SERVOeferral agreements\21 E. Elm St.doc
��'x� x✓ nom.
Sw (3--tkC G -u � For
n off- a- r i z o �f ' o n
State of California
Countyof �or)0 fl) a�
CALIFORNIA ALL-PURPOSE
CERTIFICATE OF ACKNOWLEDGMENT
On Au Q u s4 6, 7B I I before me, "O lefV C" r -%r' q ta , N) 04 a rq U
(here insert n e and itle of the officef)
personally appeared 11 n ,r\ � �> � C1.� n
who proved tome on the basis of satisfactory evidence to be the person whose nameN is/arksubscribed to
the within instrument and acknowledged to me that 11�e/she/tkey executed the same in hjs/her/t eir
authorized capacity(k), and that by Ns/her/their signature(l�on the instrument the person(, or the entity
upon behalf of which the personN acted, executedthe instrument.
_
I certify under PENALTY OF PERJURY under the laws of the
State of California that the foregoing paragraph is true and correct.
y4
t�
WITNESS my hand and official seal.
Signature
C�
OPTIONAL INFORMATION
(Seal)
Although the information in this section is not required bylaw, it could prevent fraudulent removal and reattachment of this
acknowledgment to an unauthorized document and may prove useful to persons relying on the attached document
Description of Attached Document
The preceding Certificate of Acknowledgment is attached to a document Method of Signer identification
titledlfor the purpose of TM -P N \J em N -� V� F(< IR RA L_ Proved to me on the basis of satisfactoryevidence:
L U form(s) of ideritification O credible witness(es)
_�G2EEiv) c -NT
containing 5 pages, and dated O - Z (j ( I
The signer(s) capacity or authority is/are as:
❑ Individual(s)
❑ Attorney -in -Fact
❑ Corporate Officer(s)
Title(s)
❑ Guardian/Conservator
❑ Partner- Limited/General
❑ Trustee(s)
❑ Other: —
representing:
Name(s) of Person(s) or Entity(ies) Signer is Representing
Notarial event is detailed in notaryjournal on:
Page # Entry #
Notary contact:__
Other
❑ Additional Signer(s) ❑ Signer(s) Thumbprint(s)
❑
I
0 Copyright 2007 Notary Rotary, Inc. 925 29th St., Des Moines, IA 50312-3612 Form ACK03. 10/07. To reorder, call toll-free 1-877-349-6588 or visit us on the Internet at http://www.notaryrotary.com
RESOLUTION NO. 2011-154
A RESOLUTION OF THE LODI CITY COUNCIL
APPROVING IMPROVEMENT DEFERRAL
AGREEMENT WITH ANN H. PEDEN FOR
21 EAST ELM STREET
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
approve the Improvement Deferral Agreement between the City of Lodi and
Ann H. Peden for installation of public improvements for the facility located at
21 East Elm Street; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to
execute the agreement on behalf of the City of Lodi.
Dated: October 5, 2011
I hereby certify that Resolution No. 2011-154 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held October 5, 2011, by the
following vote:
AYES: COUNCIL MEMBERS — Hansen, Katzakian, Mounce, Nakanishi,
and Mayor Johnson
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS— None
&OHL
City Clerk
2011-154
CITY COUNCIL
BOB JOHNSON, Mayor
JOANNE L. MOUNCE,
Mayor Pro Tempore
LARRY D. HANSEN
PHIL KATZAKIAN
ALAN NAKANISHI
Ann H. Peden
12272 Jerri Drive
Glen Ellen, CA 95442
CITY OF LODI
PUBLIC WORKS DEPARTMENT
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209)333-6706
FAX (209) 333-6710
EMAI L pwdept@lodi.gov
http :\\www .lod i.g ov
September 29, 2011
KONRADT BARTLAM
City Manager
RANDI JOHL
City Clerk
D. STEVEN SCHWABAUER
City Attorney
F. WALLY SAN DELIN
Public Works Director
SUBJECT: Adopt Resolution Authorizing City Managerto Execute Improvement
Deferral Agreement for 21 East Elm Street
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, October 5, 2011. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunityto address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand-deliverthe letterto City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Randi Johl, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Chris Boyer, Junior Engineer,
at (209) 333-6800, extension 3321.
` f 9
F. Wally Sandelin
.�✓ • Public Works Director
FWS/pmf
Enclosure
cc: City Clerk
NCC_IMPDEFAGMT 21 E ELMSTMOC